Chester County Solid Waste Authority (CCSWA) is soliciting bids through Invitation for Bid for construction of the Area E Stage 2 Final Cover System at the Lanchester Landfill & Reclamation Center in Narvon, Pennsylvania, with a mandatory prebid meeting on December 2, 2026. Attendance at that meeting is required for bid eligibility, and the meeting is held at the project site at 1:00 PM EST. Bidders must register with PennBid at no cost, and electronic submission through PennBid is the only accepted bid method.
The scope covers site preparation, erosion and sediment control, earthwork, anchor trench installation, geosynthetic final cover system installation, piping installation, and exposure and preparation of existing tie-ins. It also includes landfill gas management system modification, stormwater management system installation, and construction layout and as-built surveying. The construction drawings, prepared in November 2026 by Civil & Environmental Consultants, Inc. of Langhorne, Pennsylvania, comprise 15 sheets. Each bid must include bid security equal to 10 percent of the total bid amount. All work must be completed by October 30, 2027.
The project spans Salisbury and Caernarvon Townships in Lancaster and Chester Counties. Questions are due by 4:00 PM EST on December 11, 2026, with responses issued by December 18, 2026. A second question round closes at 4:00 PM EST on January 5, 2027, with responses due January 11, 2027. Bids are due electronically through PennBid by 2:00 PM EST on January 15, 2027, and CCSWA will award to the lowest responsible bidder under Pennsylvania law. CCSWA reserves the right to reject any or all bids and to waive informalities to the extent Pennsylvania law permits. Technical questions go to Christopher Toevs, P.E., Director of Engineering, through PennBid, and all official clarifications and addenda are issued exclusively through PennBid.
Opportunity text
The Scope of Work includes furnishing all labor, materials, equipment, tools, transportation, supervision, and services necessary to complete the following activities: • Site preparation; • Erosion and sediment control; • Earthwork; • Geosynthetic final cover system installation; • Piping installation; • Exposure and preparation of existing tie-ins; • Stormwater management system installation; • Construction layout surveying; and • Construction as-built surveying.