About this opportunity
Guilford County Schools is soliciting sealed bids for the Northern Guilford High School boiler replacement at 7101 Spencer-Dixon Road in Greensboro, North Carolina (GCS Quote #6855), with bids due November 12, 2026 at 2:00 p.m. No set-aside or preference program is named. Eligibility turns on contractor licensing under Section 87 of the North Carolina General Statutes and E-Verify compliance.
The scope covers full removal of existing cabinet boilers, integral and base-mounted pumps, and associated piping, valves, and controls, with owner-tagged items delivered to the GCS maintenance facility. The contractor installs new condensing boilers, primary and secondary pumps, condensate neutralization, gas trains, and housekeeping pad modifications. Additional work includes new flue and combustion air ductwork using materials listed for condensing appliances, and DDC controls integrated with the existing building automation system for boiler staging, pump control, outdoor air reset, alarms, and system graphics. The contractor also patches abandoned penetrations, drains, refills, and treats the heating water system, and coordinates electrical disconnection and reconnection with Division 26.
Bonding requirements are a 5% bid bond and 100% performance and labor and material payment bonds. No bid may be withdrawn for 60 days after the closing time.
Consultant Engineering Service, Inc. distributes bid documents, which were available beginning October 15, 2026, and receives written questions at 1111 S. Marshall Street, Suite 250, Winston-Salem, North Carolina. Sealed bids are delivered to 714 Green Valley Road, Room 2A, Greensboro. The highly encouraged pre-bid meeting at the project site was scheduled for October 22, 2026, and has passed. Prospective bidders who did not attend were required to email to register for current bid information.
Opportunity text
Existing cabinet boilers shall be removed in their entirety, including burners, trim, breeching, flue, combustion air connections, and associated piping, valves, and control wiring back to the points of connection indicated on the drawings; cap all abandoned piping at the main or as indicated. Integral boiler pumps and base mounted secondary pumps shall be demolished as indicated on the demolition plans, including associated piping, valves, specialties, and starters/vfd's not indicated to be reused. Prior to demolition, the owner shall tag all items to be retained from the existing boilers and/or pumps; contractor shall carefully remove tagged items and deliver them to the owner at gcs maintenance facility, and all untagged items shall become the property of the contractor and be removed from the site and legally disposed of. Contractor shall drain, refill, vent, and treat the heating water system as required and shall coordinate all shutdowns with the owner in advance. Provide and install new condensing boilers, primary and secondary pumps, including all accessories, trim, valves, specialties, condensate neutralization, gas trains, and housekeeping pad modifications as scheduled and specified in these documents. Boiler plant controls shall be integrated to ddc controls integrated with the existing building automation system for all new equipment, including boiler staging, pump control, outdoor air reset, alarms, and new or updated system graphics; refer to sequence of operations. New flue and combustion air duct shall be provided and installed in accordance with the boiler manufacturers installation instructions and applicable codes, using materials listed for condensing appliances and maintaining all required termination clearances; patch and seal all abandoned wall and roof penetrations to match existing construction, fire ratings and warranties. Coordinate all electrical disconnection and reconnection with division 26. Boiler start-up shall be performed by a factory-authorized representative, and contractor shall provide combustion analysis reports, controls checkout, owner training, and o&m manuals.
Files
| File | Type | Posted |
|---|---|---|
| Northern Guilford Boiler Replacement.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity