The Town of Putnam Water Pollution Control Authority (WPCA) is requesting bids on a lead service line replacement program covering up to 223 service line replacements within its service territory, with bids due September 16, 2026 at 2:00 p.m. EDT under ITB solicitation.

Scope covers replacement of lead and galvanized-steel service lines, typically on the private side from the curb stop to the first fitting in the building using copper pipe. Public-side replacements will be performed only if lead is identified onsite upstream of the curb stop during test pit or private-side replacement activities. Certain locations may require special replacement procedures, including service line relocation from the water main to the building. Addresses may be added to or removed from the work list by the Engineer or Owner throughout the project duration.

The bid structure is a single line item priced per unit for a quantity of 1.00; vendors provide their own pricing for the scope of work. Payment terms and delivery are vendor-specified with Free On Board Destination basis. No estimated contract value is disclosed.

The solicitation document (38479_Aug_13_26_solicitation_doc.pdf) is attached. Questions should be directed to Denise Geeza, Town of Putnam, 200 School Street, Putnam, CT 06260, at 860-963-6800 or denise.geeza@putnamct.us.

Opportunity text

The Lead Service Line Replacement Program will target replacements of lead service lines within multiple areas of the Town of Putnam WPCA service territory. For the purposes of this project, galvanized steel is defined as a lead service line and should be removed and treated as if it was a lead pipe. Addresses may be added to and removed from the list by the Engineer or Owner within the defined Work Area throughout the project duration for a total of up to 223 service line replacements. Replacements will typically be on the private side only, typically from the curb stop to the first fitting in the building using copper pipe. Public side replacements will be performed only if lead is identified onsite upstream of the curb stop during a test pit or private side replacement. Certain locations may require special replacement procedures, including the relocation of the service line from the water main to the building.