WY FLAP CR CN10-277(1) Wiggins Creek Bridge

Closed Pre-Solicitation Posted

This opportunity was awarded. See the award notice from , or the latest solicitation from .

Solicitation number
6982AF23SS0006
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Dubois, Wyoming, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This pre-solicitation notice is seeking to determine interest from small businesses, HUBZone small businesses, woman owned small businesses, 8(a) small businesses, or service disabled veteran-owned small businesses to set aside the forthcoming solicitation for the WY FLAP CR CN10-277(1) Wiggins Creek Bridge project. The project involves removal of an existing one-lane bridge and construction of a new modular steel vehicular bridge, and includes principal work items such as cofferdams, structural concrete, reinforcing steel, bridge railing, and drilled shafts. Interested contractors must submit statements of intention to bid as a prime, applicable socioeconomic certifications, bonding capacity documentation, and descriptions of previous relevant projects by November 30, 2022.

The solicitation does not specify set-aside designations. The work involves heavy construction activities for bridge and road projects valued between $2-5 million. The Department of Transportation Federal Highway Administration is seeking a contractor to remove the existing bridge and construct a new one-lane bridge along East Fork Road in Fremont County, Wyoming, with an estimated completion date of January 18, 2024. The project is funded in part through the FLAP program with county matching funds.

Notice text

THIS IS NOT A REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.

THIS NOTICE IS BEING ISSUED TO DETERMINE IF THERE IS SUFFICIENT  INTEREST FROM QUALIFIED PRIME CONTRACTORS who are small businesses, HUBZone small businesses, woman owned small business concerns, 8(a) small businesses, or service disabled veteran-owned small businesses and who intend to submit a bid for this solicitation to allow for a set-aside in one of these programs.  Interested businesses must submit the following by e-mail to CFLAcquisitions@dot.gov (Attn:  Leslie Karsten) for receipt by close of business (2 p.m. local Denver time) on November 30, 2022: 

(1) A positive statement of your intention to submit a bid for this solicitation as a Prime Contractor;

(2) A list of all confirmed socioeconomic categories (i.e., 8(a), small disadvantaged business, HUBZone small business, service-disabled veteran-owned small business, EDWOSB, or WOSB status) that apply to your business;

(3) A letter from a bonding agent stating your firm’s capability to bond for a single project of $5 million, and your firm’s aggregate bonding capacity; and

(4) Provide a list of road construction projects of equal or greater value and scope to the WY FLAP CR CN10-277(1) Wiggins Creek Bridgeproject in which you performed removal of bridge, cofferdams, structural concrete, reinforcing steel, prefabricated steel bridge, bridge railing, drilled shafts, and construction and maintenance of a diversion.  DO NOT SEND INFORMATION ON PROJECTS THAT DO NOT INCLUDE THE ABOVE WORK.

The size of a small business firm includes all parents, subsidiaries, affiliates, etc.  Refer to the Code of Federal Regulations 13 CFR 121.103 for information on how the SBA determines affiliation and 13 CFR 121.108 regarding the penalties for misrepresentation of size status.  All firms should be certified in the System for Award Management (SAM) located at https://www.sam.gov/

PROJECT NUMBER:  WY FLAP CR CN10-277(1)

PROJECT NAME:  WIGGINS CREEK BRIDGE

PROJECT DESCRIPTION:  The project is in Fremont County, Wyoming along the East Fork Road, approximately 6 miles north of the intersection with U.S Highway 26. The nearest town is Dubois Wyoming located approximately 15 miles west of the project location. The terrain is mountainous with an elevation of approximately 6700 feet. This project is for bridge replacement.

SCOPE OF THE WORK:  The project includes removal of a one-lane bridge. A one lane diversion will be required before the removal of the existing bridge can begin as the roadway must remain open throughout the project. The creek is a sensitive resource area for the Yellowstone cutthroat trout and Brown trout. The construction season that is currently anticipated is that most work will be performed in late summer and through the winter to minimize the impact to the fisheries. There will be some level of public scrutiny as there are three private properties that are adjacent to the bridge.

PRINCIPAL WORK ITEMS: The major items of work include the following:

  • Removal of bridge (LPSM)
  • Cofferdams (LPSM)
  • Structural Concrete, Class A (AE) – 150 (CUYD)
  • Reinforcing Steel – 21,700 (LB)
  • Reinforcing Steel, Epoxy Coated – 13,000 (LB)
  • Prefabricated steel bridge (100’x 29’ Modular Steel Vehicular Bridge) (LPSM)
  • Bridge Railing, Steel (WYDOT TL-3) – 290 (LNFT)
  • Drilled Shaft, 30-inch diameter – 250 (LNFT)
  • Construction and maintenance of diversion (LPSM)

ANTICIPATED SCHEDULE: It is anticipated this project will be advertised in early 2023 and be under construction in August 2023.  The project has an estimated completion date of January 18, 2024.

No in-water work can occur between May 15th and July 31st to avoid the Yellowstone cutthroat trout spawning and no in-water work between September 15th through November 30th to avoid brown trout spawning.

ESTIMATED COST RANGE:  The estimated price range of the project work is between: $2,000,000 and $5,000,000

FUNDING SOURCE:  The project is funded through the FLAP program which includes a portion of the project being funded through match from Fremont County.

Notice history

Notice Type Posted
WY FLAP CR CN10-277(1) Wiggins Creek Bridge Award Award Notice
WY FLAP CR CN10-277(1) Wiggins Creek Bridge Latest solicitation Solicitation
WY FLAP CR CN10-277(1) Wiggins Creek Bridge Pre-Solicitation
This notice Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
WY BR WYAO US20(1) US 20 and Hayden Arch Bridge Repairs Cody, Wyoming 82414, United States · NAICS 237310 Federal Highway Administration No set-aside
UT NP ARCH 100(2) Bridges on Delicate Arch Road Moab, Utah 84532, United States · NAICS 237310 Federal Highway Administration No set-aside
Access Road Repair National Elk Refuge NAICS 237310 — Total Small Business
ID FLAP KOOTEN 8450(1), Yellowstone Trail Road, Segment 1 Coeur d Alene, Idaho, United States · NAICS 237310 Federal Highway Administration No set-aside
TX FW LGA 10(5) Steve Thompson Wildlife Drive Los Fresnos, Texas 78566, United States · NAICS 237310 Federal Highway Administration Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity