Wolf Creek GSU Transformer Replacement

Closed Special Notice Posted

This opportunity was awarded. See the award notice from , or the latest solicitation from .

Solicitation number
W912P524R0004
Agency
ENDIST Nashville US Army Corps of Engineers, Department of Defense
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Z2KA Repair Or Alteration Of Dams
Place of performance
Jamestown, Kentucky 42629, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This Special Notice was published by the U.S. Army Corps of Engineers, Nashville District regarding the Wolf Creek GSU Transformer Replacement project in Jamestown, Kentucky. The notice provides advance information on an upcoming Request for Proposal solicitation for a firm fixed-price construction contract to replace aging generator step-up transformers at the Wolf Creek power plant.

The Special Notice outlines requirements for contractors interested in the future project opportunity, including attendance at a mandatory pre-proposal site visit on January 3, 2024 to view project details. Questions must be submitted by specified deadlines to listed points of contact. Eligible contractors must be registered in the System for Award Management database and the work is expected to include design, removal and installation services associated with replacing the aging transformers. The estimated price range for the project is between $25-49 million.

Notice text

3 versions

Update #3 · Latest ·

The U.S. Army Corps of Engineers (USACE), Nashville District (LRN) intends to issue a Request for Proposal (RFP) solicitation for a firm fixed-price (FFP) construction (with incidental supply) contract for the Wolf Creek Power Plant GSU Replacement Project in Jamestown, Kentucky.

This Special Notice is being issued for planning and information purposes only. This notice is not a solicitation, nor is it to be construed as a commitment by the Government. The Government will not pay for any effort expended in responding to this notice, nor will the Government accept proposals as a result of this notice.

Security: In order to view the plans and specifications for this requirement, please submit a site visit request form to Alison Abernathy. 

Industry Day: Pre-Proposal Site Visit remains on 3 January 2024 at 10:00 am Central Time at Wolf Creek Dam in Jamestown, KY. Address to arrive at is:

50 Kendall Road

Jamestown KY 42629

** All participants are required to have personal protective equipment, i.e. hard hat, safety glasses, reflective vests, and steel-toed shoes before entering the project site. Contractors who do not have these items present at the site visit may not be able to participate in the visit.

An approved site visit request form will be needed for each individual attendee.

Questions: Please submit any questions regarding this requirement to Alison Abernathy at Alison.T.Abernathy@usace.army.mil copying Dellaria Martin at dellaria.l.martin@usace.army.mil and Sam Jaser at sulaiman.r.jaser@usace.army.mil .

Project Description:  The scope of the project is to replace ten (10) 13.8/161kV single phase Generator Step-up Unit (GSU) transformers at the Wolf Creek power plant. The single phase transformers will be replace with three (3) 3-phaser GSUs. The contractor may be responsible for:

-         The design, manufacture, testing, and delivery three new 3-phase GSU transformers with internal neutral CTs by the transformer manufacturer

-         Removal the existing surge arresters and retaining for installation on the new 3-phase transformers

-         Draining and disposal of the existing transformer oil

-         Removal and proper disposal of existing GSU transformers, and ancillary equipment, including spare transformer

-         Removal of existing 15kV tubular bus system, including the metering instrument transformers for each existing transformer

-         Removal of the existing 161kV conductors, and insulators for each existing transformer

-         Installation of the new 15kV tubular bus system, including metering instrument transformers for the new 3-phase transformers

-         Installation of the new 161kV conductors, and insulators on the new takeoff towers for the new 3-phase transformers

-         Installation of two new 480V AC power cabinets in the switchyard

-         Installation of new conduit and feeders to the new 480V AC power cabinets in the switchyard

-         Installation of new conduit and feeders from the new 480V AC power cabinets in the switchyard to the new transformer power cabinets

-         Installation of 125V DC wiring and conduit for control power, controls, and annunciation from the battery switchboard AS to each new transformer control cabinet

-         Installation of three new 3-phase GSU transformers on the new transformer foundations

-         Installation of the existing surge arresters onto the new 3-phase transformers

-         Repair of the existing ground grid around each transformers and surrounding area as needed

-         Modification of existing 161kV copper bus to accommodate the new three-phase transformers

-         Removal of existing structures including the rails, the 15kV tubular bus support structures and foundations, the transformer foundations, and the take-off towers and foundations.

This description is not intended to be all encompassing and is subject to change. Only draft plans and specs are available at this time. The final plans and specifications will be available with the solicitation announcement. The solicitation is expected to be released on or around 15 January 2024.

Disclosure of the Estimated Magnitude of the Construction Project: The estimated price range is between $25,000,000.00 not to exceed (NTE) $49,000,000.00.

NAICS Code and Size Standard: 237990 – Other Heavy and Civil Engineering Construction; $45,000,000.00

Type of Set Aside: None (Full and Open/ Unrestricted)

SYSTEM FOR AWARD MANAGEMENT (SAM): Offerors are required to be registered in the System for Award Management (SAM) database (https://sam.gov) and Procurement Integrated Enterprise Environment (PIEE) at the time a proposal is submitted in order to comply with the annual representations and certifications requirements. Registration for PIEE is required as this is the only place proposals shall be submitted.

ADDITIONAL INFORMATION:

Information regarding USACE’s process for settling requests for equitable adjustments and duration goals to achieve definitization of equitable adjustments for change orders under construction contracts can be found by going to https://www.usace.army.mil/Business-With-Us/Partnering/ then clicking on “View FFP Contract Changes Playbook Here”.

Update #2 ·

The U.S. Army Corps of Engineers (USACE), Nashville District (LRN) intends to issue a Request for Proposal (RFP) solicitation for a firm fixed-price (FFP) construction (with incidental supply) contract for the Wolf Creek Power Plant GSU Replacement Project in Jamestown, Kentucky.

This Special Notice is being issued for planning and information purposes only. This notice is not a solicitation, nor is it to be construed as a commitment by the Government. The Government will not pay for any effort expended in responding to this notice, nor will the Government accept proposals as a result of this notice.

Security: In order to view the plans and specifications for this requirement, please submit a site visit request form to Alison Abernathy. 

Industry Day: Pre-Proposal Site Visit remains on 3 January 2024 at 10:00 am Central Time at Wolf Creek Dam in Jamestown, KY. Address to arrive at is:

980 Power Plant Road

Jamestown KY 42629

** All participants are required to have personal protective equipment, i.e. hard hat, safety glasses, reflective vests, and steel-toed shoes before entering the project site. Contractors who do not have these items present at the site visit may not be able to participate in the visit.

An approved site visit request form will be needed for each individual attendee.

Questions: Please submit any questions regarding this requirement to Alison Abernathy at Alison.T.Abernathy@usace.army.mil copying Dellaria Martin at dellaria.l.martin@usace.army.mil and Sam Jaser at sulaiman.r.jaser@usace.army.mil .

Project Description:  The scope of the project is to replace ten (10) 13.8/161kV single phase Generator Step-up Unit (GSU) transformers at the Wolf Creek power plant. The single phase transformers will be replace with three (3) 3-phaser GSUs. The contractor may be responsible for:

-         The design, manufacture, testing, and delivery three new 3-phase GSU transformers with internal neutral CTs by the transformer manufacturer

-         Removal the existing surge arresters and retaining for installation on the new 3-phase transformers

-         Draining and disposal of the existing transformer oil

-         Removal and proper disposal of existing GSU transformers, and ancillary equipment, including spare transformer

-         Removal of existing 15kV tubular bus system, including the metering instrument transformers for each existing transformer

-         Removal of the existing 161kV conductors, and insulators for each existing transformer

-         Installation of the new 15kV tubular bus system, including metering instrument transformers for the new 3-phase transformers

-         Installation of the new 161kV conductors, and insulators on the new takeoff towers for the new 3-phase transformers

-         Installation of two new 480V AC power cabinets in the switchyard

-         Installation of new conduit and feeders to the new 480V AC power cabinets in the switchyard

-         Installation of new conduit and feeders from the new 480V AC power cabinets in the switchyard to the new transformer power cabinets

-         Installation of 125V DC wiring and conduit for control power, controls, and annunciation from the battery switchboard AS to each new transformer control cabinet

-         Installation of three new 3-phase GSU transformers on the new transformer foundations

-         Installation of the existing surge arresters onto the new 3-phase transformers

-         Repair of the existing ground grid around each transformers and surrounding area as needed

-         Modification of existing 161kV copper bus to accommodate the new three-phase transformers

-         Removal of existing structures including the rails, the 15kV tubular bus support structures and foundations, the transformer foundations, and the take-off towers and foundations.

This description is not intended to be all encompassing and is subject to change. Only draft plans and specs are available at this time. The final plans and specifications will be available with the solicitation announcement. The solicitation is expected to be released on or around 15 January 2024.

Disclosure of the Estimated Magnitude of the Construction Project: The estimated price range is between $25,000,000.00 not to exceed (NTE) $49,000,000.00.

NAICS Code and Size Standard: 237990 – Other Heavy and Civil Engineering Construction; $45,000,000.00

Type of Set Aside: None (Full and Open/ Unrestricted)

SYSTEM FOR AWARD MANAGEMENT (SAM): Offerors are required to be registered in the System for Award Management (SAM) database (https://sam.gov) and Procurement Integrated Enterprise Environment (PIEE) at the time a proposal is submitted in order to comply with the annual representations and certifications requirements. Registration for PIEE is required as this is the only place proposals shall be submitted.

ADDITIONAL INFORMATION:

Information regarding USACE’s process for settling requests for equitable adjustments and duration goals to achieve definitization of equitable adjustments for change orders under construction contracts can be found by going to https://www.usace.army.mil/Business-With-Us/Partnering/ then clicking on “View FFP Contract Changes Playbook Here”.

Update #1 ·

The U.S. Army Corps of Engineers (USACE), Nashville District (LRN) intends to issue a Request for Proposal (RFP) solicitation for a firm fixed-price (FFP) construction (with incidental supply) contract for the Wolf Creek Power Plant GSU Replacement Project in Jamestown, Kentucky.

This Special Notice is being issued for planning and information purposes only. This notice is not a solicitation, nor is it to be construed as a commitment by the Government. The Government will not pay for any effort expended in responding to this notice, nor will the Government accept proposals as a result of this notice.

Security: In order to view the plans and specifications for this requirement, please submit a site visit request form to Alison Abernathy. 

Industry Day: Pre-Proposal Site Visit remains on 3 January 2024 at 10:00 am Central Time at Wolf Creek Dam in Jamestown, KY. Address to arrive at is:

Wolf Creek National Fish Hatchery Visitor and Environmental Education Center

50 Kendall Road

Jamestown, KY 42629

** All participants are required to have personal protective equipment, i.e. hard hat, safety glasses, reflective vests, and steel-toed shoes before entering the project site. Contractors who do not have these items present at the site visit may not be able to participate in the visit.

An approved site visit request form will be needed for each individual attendee.

Questions: Please submit any questions regarding this requirement to Alison Abernathy at Alison.T.Abernathy@usace.army.mil copying Dellaria Martin at dellaria.l.martin@usace.army.mil and Sam Jaser at sulaiman.r.jaser@usace.army.mil .

Project Description:  The scope of the project is to replace ten (10) 13.8/161kV single phase Generator Step-up Unit (GSU) transformers at the Wolf Creek power plant. The single phase transformers will be replace with three (3) 3-phaser GSUs. The contractor may be responsible for:

-         The design, manufacture, testing, and delivery three new 3-phase GSU transformers with internal neutral CTs by the transformer manufacturer

-         Removal the existing surge arresters and retaining for installation on the new 3-phase transformers

-         Draining and disposal of the existing transformer oil

-         Removal and proper disposal of existing GSU transformers, and ancillary equipment, including spare transformer

-         Removal of existing 15kV tubular bus system, including the metering instrument transformers for each existing transformer

-         Removal of the existing 161kV conductors, and insulators for each existing transformer

-         Installation of the new 15kV tubular bus system, including metering instrument transformers for the new 3-phase transformers

-         Installation of the new 161kV conductors, and insulators on the new takeoff towers for the new 3-phase transformers

-         Installation of two new 480V AC power cabinets in the switchyard

-         Installation of new conduit and feeders to the new 480V AC power cabinets in the switchyard

-         Installation of new conduit and feeders from the new 480V AC power cabinets in the switchyard to the new transformer power cabinets

-         Installation of 125V DC wiring and conduit for control power, controls, and annunciation from the battery switchboard AS to each new transformer control cabinet

-         Installation of three new 3-phase GSU transformers on the new transformer foundations

-         Installation of the existing surge arresters onto the new 3-phase transformers

-         Repair of the existing ground grid around each transformers and surrounding area as needed

-         Modification of existing 161kV copper bus to accommodate the new three-phase transformers

-         Removal of existing structures including the rails, the 15kV tubular bus support structures and foundations, the transformer foundations, and the take-off towers and foundations.

This description is not intended to be all encompassing and is subject to change. Only draft plans and specs are available at this time. The final plans and specifications will be available with the solicitation announcement. The solicitation is expected to be released on or around 15 January 2024.

Disclosure of the Estimated Magnitude of the Construction Project: The estimated price range is between $25,000,000.00 not to exceed (NTE) $49,000,000.00.

NAICS Code and Size Standard: 237990 – Other Heavy and Civil Engineering Construction; $45,000,000.00

Type of Set Aside: None (Full and Open/ Unrestricted)

SYSTEM FOR AWARD MANAGEMENT (SAM): Offerors are required to be registered in the System for Award Management (SAM) database (https://sam.gov) and Procurement Integrated Enterprise Environment (PIEE) at the time a proposal is submitted in order to comply with the annual representations and certifications requirements. Registration for PIEE is required as this is the only place proposals shall be submitted.

ADDITIONAL INFORMATION:

Information regarding USACE’s process for settling requests for equitable adjustments and duration goals to achieve definitization of equitable adjustments for change orders under construction contracts can be found by going to https://www.usace.army.mil/Business-With-Us/Partnering/ then clicking on “View FFP Contract Changes Playbook Here”.

Attachments

Files attached to this notice, newest first
File Type Posted
US Citizen Pre_Bid or Site Visit Form JAN 2019.pdf PDF
FN Pre_Bid or Site Visit Form JAN 2019.pdf PDF

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Wolf Creek GSU Replacement Award Award Notice
Wolf Creek GSU Replacement Latest solicitation Solicitation
Synopsis- Wolf Creek GSU Transformer Replacement Pre-Solicitation
Notice of Intent to Include Brand Name or Equal Specs- Wolf Creek GSU Transformer Replacement Special Notice
Wolf Creek GSU Transformer Replacement This notice Special Notice
Wolf Creek GSU Transformer Replacement Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity