- Contract number
- 12569R18C0006 Federal contract award
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- PSC
- Not on record
- Place of performance
- From the intersection of US-23 and River Road in Oscoda MI, go 3.1 miles West on River Road to FSR 4851/ Whirlpool Rd, go north on FSR 4851 0.6 miles until you reach the project location. Oscoda, Michigan, United States
Notice details come from SAM.gov. Updated .
Notice text
3 versions
Update #3 · Latest ·
Added: May 29, 2018 11:25 am Contractor was awarded base and option Items
Update #2 ·
Added: Mar 19, 2018 11:29 am THE SOLICITATION NUMBER LISTED INITIALLY IS INCORRECT (12569R18R0004) AND SHOULD READ AS FOLLOWS: 12569R18R0007.
Update #1 ·
Added: Mar 01, 2018 10:27 am
The Lake States Acquisition Team is announcing an opportunity to bid on the Whirlpool Parking Area Paving project located on the Huron-Manistee National Forests in Michigan.
The project is estimated to be between $150,000 and $500,000. The applicable North American Industry Classification System (NAICS) Code is 237310. The Small Business Administration size standard is $36.5 million. Contractors are required to be actively registered with the System for Award Management (SAM) database and completed their online representations and certifications.
Bacon-Davis wage rates will apply to this contract.
No reimbursement will be made for any costs associated with providing information in response to this solicitation, amendments, or any follow up information requests. No hard copies of the solicitation, supporting documents and applicable amendments, if any, will be provided. To receive the entire solicitation package and any applicable amendments, prospective offerors must download them from the FedBizOpps website.
Project dates are scheduled for September 2018 and the contract is estimated to require approximately 25 days for completion.
The scope of work includes, but is not limited to, drainage improvements and HMA placement. Work includes mobilization, construction staking, earthworks, placing aggregate, placing HMA-LVSP, installing CMP's, removing and transporting timber wheel stops, furnishing and placing topsoil, placing conserved topsoil, turf establishment, and placing pavement markings.
All invoices must be submitted via the electronic Invoice Processing Platform (IPP). This is a mandatory requirement initiated by the U.S. Department of Treasury. For more information see website https://www.ipp.gov/index.htm. Please make sure that your company has registered for an account at https://www.ipp.gov/vendors/enrollment-vendors.htm.
Attachments
| File | Type | Posted |
|---|---|---|
| amend1_sf_30.pdf | ||
| prebid_notes.pdf | ||
| attendee_record.pdf | ||
| Plans.pdf | ||
| Experience_Questionnaire.pdf | ||
| davis_bacon_wages.pdf | ||
| whirlpool_sol.pdf | ||
| SectionC.pdf | ||
| Maps.pdf |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity