Weld Substation Stage 05

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
89503226BWA000074
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

More information

Notice details come from SAM.gov. Updated .

About this opportunity

The Western Area Power Administration, Rocky Mountain Region, seeks construction of the Weld Substation Stage 05, a 230/115–13.8 KV transformer installation project, with proposals due August 5, 2026. The procurement carries no set-aside.

Scope includes removal and installation of a 230/115–13.8-KV, 150 MVA transformer (KV1A), removal and installation of associated 230/115 KV take-off structure, tertiary station service feeds (KV1A and KV2A), new station service installation, removal of existing station service, replacement of control building single-phase AC panels with 3-phase AC panels, associated foundations, structures, electrical equipment, and site development. The NAICS code is 237130, Power and Communication Line and Related Structures Construction; the PSC code is Y1PZ, Construction Of Other Non-Building Facilities.

Multiple amendments have revised the solicitation. Amendment 0002 added Clause RFO 52.211-12 (Liquidated Damages — Construction). Amendments 0003, 0005, and 0008 extended bid closing and changed the virtual bid opening date. Amendment 0004 set the bid opening date to July 20, 2026, at 9:00 a.m. Amendment 0006 added the Weld Geotech Report and posted industry Q&A. Amendment 0007 updated Q&A responses. Amendment 0009 updated drawings. Amendment 0008 also revised the bid schedule and updated specifications.

Notice text

9 versions

Update #9 · Latest ·

Amendment (0009) is to update drawings as part of the Weld Substation Stage 05.

Update #8 ·

Amendment (0008) is to extend bid closing date, change the virtual bid opening date, revise bid schedule, and update specifications as part of the Weld Substation Stage 05.

Update #7 ·

Amendment (0007) is to update Q/A from industry as part of the Weld Substation Stage 05.

Update #6 ·

Amendment (0006) is to add Weld Geotech Report and post Q/A from industry.

Update #5 ·

Amendment (0005) is to extend the Solicitation Close and change the Virtual Bid Opening Date.

Update #4 ·

Amendment (0004) is to Correct Bid Opening date to 20 July 2026, 9:00 a.m..

Update #3 ·

Amendment (0003) is to extend the Solicitation Close and change the Bid Opening date

Update #2 ·

Amendment (0002) to add Clause RFO 52.211-12, Liquidated Damages - Construction, and upload Solicitation, Amendment 0001 and 0002.

Update #1 ·

Western Area Power Administration (WAPA), Rocky Mountain Region (RMR) has a requirement for the construction of the Weld Substation Stage 05 for the removal and installation of a 230/115-13.8-KV, 150MVA, transformer KV1A, removal and installation of associated 230/115KV take-off structure, KV1A tertiary station service feed, installation of a new station service, removal of the existing station service, and installation of new KV2A tertiary station service feed, associated foundations, structures, associated electrical equipment, removal of control building single-phase AC panels, installation of control building 3-phase AC panels, and site development for Weld Substation, Stage 05

Notice history

Notice Type Posted
Weld Substation Stage 05 Award Award Notice
This notice Latest solicitation Solicitation
Weld Substation Stage 05 Original Pre-Solicitation