Water Generator
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- FA2550-18-Q-2023
- Agency
- Air Force Space Command Air Force, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- Contract number
- FA255018P2059 Federal contract award
- NAICS code
- 221310 Water Supply and Irrigation Systems
- PSC
- Not on record
- Place of performance
- 1 Kaena Point Tracking Station Road, Building 10 Waianae, Hawaii 96792, United States
Notice details come from SAM.gov. Updated .
Notice text
5 versions
Update #5 · Latest ·
The purpose of this amendment is to post more questions and answers.
Q1 - The unit as speciied in the solicitation along with the associated water reservoir weighs approximately 6000 LBS. Can you confirm Det 3 will aslso facilitate the offloading of the equipment upon arrival at KPSTS?
A1 - Offloading shall be part of the delivery purchase order. KPSTS will be there during the offloading as an observer.
Q2 - What are the Dimensions for the Water Generator with the integrated built in 2,000 Gallon Water Reservoir Tank Requirements?
A2 - Using 7.48 gallons per cubic feet to convert 2000 gallons capacity of tank reservoir then the water tank reservoir is 267.38 cubic feet. The height, width and length of tank reservoir all depends on the manufacturer and the size of the water generator. As long as there is a 267.38 cubic feet of tank reservoir this will satisfy the 2000 gallons requirement.
All other Terms and Conditioins remain unchanged..
Update #4 ·
The purpose of this amendment is to post more questions and answers.
Q1 - Who will design and build the concrete pad for the AWG?
A1 - Det 3 will design and construct the pad. I will be overall responsible for siting and design. My CE maintenance team will accomplish the site prep and pad construction.
Q2 - Who will supervise the installation of the AWG to include plumbing and electrical?
A2 - Det 3 will be using our in-house plumber and electricians to connect the AWG to an existing potable water pumping station. We are prepared to address the installation and startup with our own resources.
Q3 - Can you be more specific of the exact location of the AWG to be
installed?
A3 - The current proposed location is on the west side of Booster Pump Station (BPS) No. 3, Bldg. 30 (see attached map). Our initial survey indicated that BPS No. 3 has sufficient connectivity to power and water to support the AWG with minimal installation effort and expense from Det 3. There is sufficient space within the security fence to accommodate the unit. The elevation of BPS No. 3 is approximately 1050 feet above sea level. We initially proposed installing the AWG at a higher elevation (1400+ feel above sea level) where humidity levels were higher and closer to our water storage tanks. However, those areas lack an accessible inlet to our water distribution system for the AWG, and the location with possible inlets to our water system lack an adequate power source. Due to the design and function of the AWG, it can be easily moved to various location for improved performance if needed and/or when those area can be modified/upgraded to accept the AWG.
All other terms and conditions remail unchanged.
An extension to the RFQ was made to answer further questions.
All other tems and conditions remain unchanged.
.
Update #3 ·
The purpose of this amendment is to post more questions and answers.
Q1 - Who will design and build the concrete pad for the AWG?
A1 - Det 3 will design and construct the pad. I will be overall responsible for siting and design. My CE maintenance team will accomplish the site prep and pad construction.
Q2 - Who will supervise the installation of the AWG to include plumbing and electrical?
A2 - Det 3 will be using our in-house plumber and electricians to connect the AWG to an existing potable water pumping station. We are prepared to address the installation and startup with our own resources.
Q3 - Can you be more specific of the exact location of the AWG to be
installed?
A3 - The current proposed location is on the west side of Booster Pump Station (BPS) No. 3, Bldg. 30 (see attached map). Our initial survey indicated that BPS No. 3 has sufficient connectivity to power and water to support the AWG with minimal installation effort and expense from Det 3. There is sufficient space within the security fence to accommodate the unit. The elevation of BPS No. 3 is approximately 1050 feet above sea level. We initially proposed installing the AWG at a higher elevation (1400+ feel above sea level) where humidity levels were higher and closer to our water storage tanks. However, those areas lack an accessible inlet to our water distribution system for the AWG, and the location with possible inlets to our water system lack an adequate power source. Due to the design and function of the AWG, it can be easily moved to various location for improved performance if needed and/or when those area can be modified/upgraded to accept the AWG.
All other terms and conditions remail unchanged.
.
Update #2 ·
The purpose of this amendment is to post a question and its answer:
Question: What is the KPSTS distribution system?
Answer: 3-Phase, 4-Wire 208Y/120 V 120 208
All other terms and conditions remain unchanged..
Update #1 ·
Water-Gen's Large Scale AWG or equivalent: purchase and deliver one Water-Gen's Large Scale AWG or equivalent and two maintenance spare filters -- that produce over 5000 liters/1,319.26 gallons of clean fresh water every day to Det 3, 21 SOPS/CE, Kaena Point Satellite Tracking Station (KPSTS). The AWG shall be able to utilize a variety of power sources, including (but not limited to) solar, wind, and traditional power grid. The purchaser shall verify AWG specifications, and determine if there are additional requirements or materials prior to the purchasing of the new AWG and scheduling delivery and coordinate with Det 3, 21 SOPS/CE for the delivery location and provide AWG specification, manual, warranties, and other documentation to the Det 3, 21 SOPS/CE.
Please see attached PWS and COMBO.
Attachments
| File | Type | Posted |
|---|---|---|
| Scope_and_Location_Plan.docx | DOCX document | |
| COMBO.docx | DOCX document |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Water Generator Award Notice | Award Notice | |
| Water Generator | Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity