About this opportunity
The United States Army Corps of Engineers Sacramento District solicits construction of a new pumping plant facility (Pumping Plant 5) in Sacramento, California, with proposals due September 29, 2026. No set-aside applies.
Place of performance is Sacramento, California, specifically along the Sacramento River in Reach B of the Natomas Basin Project near Interstate 5, south of the levee. The existing Pumping Plant 5 will be demolished and a new facility constructed approximately 300 feet up the West Drainage Canal to permit completion of Reach B levee improvements, including seepage berm, adjacent levee reconstruction, and raising discharge pipes above the 200-year water surface elevation. The facility is designed to discharge drainage from the West Drainage Canal to the Sacramento River following significant rainfall.
The project is authorized under the Water Resources Reform Development Act of 2014 and encompasses thirteen contract line items covering site preparation, earthwork, and finishing work including excavation (5,791 cubic yards), levee fill Type 3 (9,558 cubic yards), seepage berm and site fill (23,510 cubic yards Type 2 and 300 cubic yards Type 1), canal excavation and disposal (3,963 cubic yards), structural excavation and backfill, aggregate base installation, HMA paving, and rock vehicle barrier installation (1,487 linear feet). The government estimate totaled $21,401,555. Abstract of Offers documents show five offerors submitted bids ranging from approximately $23.5 million to $27.45 million. Four amendments have been issued; the Abstract of Offers was posted September 30, 2026. NAICS code 237990 applies (Other Heavy and Civil Engineering Construction); PSC is Y1LC. Contact: Antonina Beal, Contract Specialist, Antonina.Beal@usace.army.mil.
Notice text
6 versions
Update #6 · Latest ·
***Abstract of Offers has been posted, see attachments*** *** Amendment 0004 has been issued ****** Amendment 0003 has been issued****** Amendment 0002 has been issued****** Amendment 0001 has been issued ***The United States Army Corps of Engineers (USACE) Sacramento District (SPK) is issuing a solicitation for the requirement to construct a new pumping plant facility in Sacramento, CA. The American River Common Features, Natomas Basin Project was authorized by the Water Resources Reform Development Act of 2014. The Natomas Basin is divided into nine reaches, A through I. Pumping Plant 5 (PP5) is in Reach B, located along the Sacramento River near the landside toe of the levee and south of Interstate 5. PP5 is designed to discharge drainage from the West Drainage Canal to the Sacramento River following any significant amount of rainfall. The existing PP5 is in the path of completing the Reach B levee improvements that includes seepage berm, adjacent levee, and raising discharge pipes above the 200-year water surface elevation. The existing PP5 will be demolished, and a new facility will be constructed about 300 feet up the canal to allow for the levee features to be constructed .Point of Contact: Antonina Beal, Contract Specialist. Email: Antonina.Beal@usace.army.mil. Please refer to the full solicitation document for all detailed instructions, clauses, and submission requirements.
Update #5 ·
*** Amendment 0004 has been issued ****** Amendment 0003 has been issued****** Amendment 0002 has been issued****** Amendment 0001 has been issued ***The United States Army Corps of Engineers (USACE) Sacramento District (SPK) is issuing a solicitation for the requirement to construct a new pumping plant facility in Sacramento, CA. The American River Common Features, Natomas Basin Project was authorized by the Water Resources Reform Development Act of 2014. The Natomas Basin is divided into nine reaches, A through I. Pumping Plant 5 (PP5) is in Reach B, located along the Sacramento River near the landside toe of the levee and south of Interstate 5. PP5 is designed to discharge drainage from the West Drainage Canal to the Sacramento River following any significant amount of rainfall. The existing PP5 is in the path of completing the Reach B levee improvements that includes seepage berm, adjacent levee, and raising discharge pipes above the 200-year water surface elevation. The existing PP5 will be demolished, and a new facility will be constructed about 300 feet up the canal to allow for the levee features to be constructed .Point of Contact: Antonina Beal, Contract Specialist. Email: Antonina.Beal@usace.army.mil. Please refer to the full solicitation document for all detailed instructions, clauses, and submission requirements.
Update #4 ·
*** Amendment 0003 has been issued****** Amendment 0002 has been issued****** Amendment 0001 has been issued ***The United States Army Corps of Engineers (USACE) Sacramento District (SPK) is issuing a solicitation for the requirement to construct a new pumping plant facility in Sacramento, CA. The American River Common Features, Natomas Basin Project was authorized by the Water Resources Reform Development Act of 2014. The Natomas Basin is divided into nine reaches, A through I. Pumping Plant 5 (PP5) is in Reach B, located along the Sacramento River near the landside toe of the levee and south of Interstate 5. PP5 is designed to discharge drainage from the West Drainage Canal to the Sacramento River following any significant amount of rainfall. The existing PP5 is in the path of completing the Reach B levee improvements that includes seepage berm, adjacent levee, and raising discharge pipes above the 200-year water surface elevation. The existing PP5 will be demolished, and a new facility will be constructed about 300 feet up the canal to allow for the levee features to be constructed .Point of Contact: Antonina Beal, Contract Specialist. Email: Antonina.Beal@usace.army.mil. Please refer to the full solicitation document for all detailed instructions, clauses, and submission requirements.
Update #3 ·
*** Amendment 0002 has been issued****** Amendment 0001 has been issued ***The United States Army Corps of Engineers (USACE) Sacramento District (SPK) is issuing a solicitation for the requirement to construct a new pumping plant facility in Sacramento, CA. The American River Common Features, Natomas Basin Project was authorized by the Water Resources Reform Development Act of 2014. The Natomas Basin is divided into nine reaches, A through I. RD-1000 s Pumping Plant 5 (PP5) is in Reach B, located along the Sacramento River near the landside toe of the levee and south of Interstate 5. PP5 is designed to discharge drainage from the West Drainage Canal to the Sacramento River following any significant amount of rainfall. The existing PP5 is in the path of completing the Reach B levee improvements that includes seepage berm, adjacent levee, and raising discharge pipes above the 200-year water surface elevation. The existing PP5 will be demolished, and a new facility will be constructed about 300 feet up the canal to allow for the levee features to be constructed .Point of Contact: Antonina Beal, Contract Specialist. Email: Antonina.Beal@usace.army.mil. Please refer to the full solicitation document for all detailed instructions, clauses, and submission requirements.
Update #2 ·
*** Amendment 0001 has been issued ***
The United States Army Corps of Engineers (USACE) Sacramento District (SPK) is issuing a solicitation for the requirement to construct a new pumping plant facility in Sacramento, CA. The American River Common Features, Natomas Basin Project was authorized by the Water Resources Reform Development Act of 2014. The Natomas Basin is divided into nine reaches, A through I. RD-1000?s Pumping Plant 5 (PP5) is in Reach B, located along the Sacramento River near the landside toe of the levee and south of Interstate 5. PP5 is designed to discharge drainage from the West Drainage Canal to the Sacramento River following any significant amount of rainfall. The existing PP5 is in the path of completing the Reach B levee improvements that includes seepage berm, adjacent levee, and raising discharge pipes above the 200-year water surface elevation. The existing PP5 will be demolished, and a new facility will be constructed about 300 feet up the canal to allow for the levee features to be constructed .Point of Contact: Antonina Beal, Contract Specialist. Email: Antonina.Beal@usace.army.mil. Please refer to the full solicitation document for all detailed instructions, clauses, and submission requirements.
Update #1 ·
The United States Army Corps of Engineers (USACE) Sacramento District (SPK) is issuing a solicitation for the requirement to construct a new pumping plant facility in Sacramento, CA. The American River Common Features, Natomas Basin Project was authorized by the Water Resources Reform Development Act of 2014. The Natomas Basin is divided into nine reaches, A through I. RD-1000?s Pumping Plant 5 (PP5) is in Reach B, located along the Sacramento River near the landside toe of the levee and south of Interstate 5. PP5 is designed to discharge drainage from the West Drainage Canal to the Sacramento River following any significant amount of rainfall. The existing PP5 is in the path of completing the Reach B levee improvements that includes seepage berm, adjacent levee, and raising discharge pipes above the 200-year water surface elevation. The existing PP5 will be demolished, and a new facility will be constructed about 300 feet up the canal to allow for the levee features to be constructed .Point of Contact: Antonina Beal, Contract Specialist. Email: Antonina.Beal@usace.army.mil. Please refer to the full solicitation document for all detailed instructions, clauses, and submission requirements.
Files
Notice history
| Notice | Type | Posted |
|---|---|---|
| This notice | Solicitation | |
| USACE SPK DBB Construction - Natomas PP5, Sacramento, CA | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| USACE SPK DB Construction - Natomas NPP Named Pumping Plants - Sacramento, CA | ENDIST Sacramento | No set-aside | |
| USACE SPK DBB Construction - Sacramento River East Levee Contract 5 (SREL C5), Sacramento, California | ENDIST Sacramento | No set-aside | |
| Grand Island Mitigation Site | ENDIST Sacramento | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity