Sustainment, Restoration, Modernization

Awarded Award Notice Posted

Solicitation number
W911KB-14-R-0011
Agency
ENDIST Alaska US Army Corps of Engineers, Department of Defense
Awarded
to Tanik Construction Company, Inc.
Set-aside
Competitive 8(a)

Opportunity facts

Contract number
W911KB14D0016-0001 Federal contract award
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Not on record
Place of performance
Various Locations in the state of Alaska. Anchorage Alaska Anchorage, Alaska 99506, United States

Notice details come from SAM.gov. Updated .

Notice text

4 versions

Update #4 · Latest ·

Added: Feb 07, 2014 6:22 pm *THE REVISED DUE DATE FOR THIS ACTION IS 27 FEBRUARY 2014.*

*SOURCE SELECTION FOR PARENT , SISTER OR OTHER AFFILIATED COMPANY HAS CHANGED.*

Update #3 ·

Added: Feb 05, 2014 2:35 pm THE NEW DUE DATE FOR PROPOSALS IS 18 FEBRUARY 2014.ELECTRONIC PROPOSAL SUBMISSION IS THE PREFERED METHOD. HOWEVER IF SUBMITTED ELECTRONICALLY IT WILL ONLY BE ACCEPTED IF IT IS RECIEVED BY THE CONTRACTING OFFICER / CONTRACT SPECIALIST BY 2:00PM ALASKA TIME ON THE DUE DATE, NO EXCEPTIONS. ITEM 13A CAN BE IGNORED IF SUBMITTING ELECTRONICALLY. ELECTRONIC SUBMISSIONS MUST BE SENT TO > OLEN.R..NORTHERN@USACE.ARMY.MIL; ALDONE.R.GRAHAM@USACE.ARMY.MIL AND MICHAEL.D.SUPRENANT@USACE.ARMY.MIL.

Update #2 ·

Added: Feb 04, 2014 7:39 pm Amendment: The due date for proposals is 18 February 2014. Offer guarentee is required.

Summary of Changes

1) Section 00 21 00 Deleted 52.204-7 "System for Award Management" from the reference clauses and added same clause as Full Text
2) Section 00 21 00 Deleted 52.215-1 "Instructions to Offerors-Competitive Acquisition" from the reference clauses and added same clause in Full Text
3) Section 00 21 00 clause 52.216-1 changed "IDIQ" to "Indefinite Delivery/Indefinite Quantity"
4) Section 00 21 00 Deleted 52.217-5 "Evaluation of Options" from the reference clauses and added same clause in Full Text
5) Section 00 21 00 Deleted 52,222-5 "Davis-Bacon Act - Secondary Site of the Work" from the reference clauses and added same clause in Full Text
6) Section 00 21 00 Deleted 52.222-35 "Equal Opportunity for Veterans" from the reference clauses and added same clause in Full Text
7) Section 00 21 00 Added full text Clause 52.232-5 "Payment under Fixed-Price Construction Contracts"
8) Section 00 21 00 Added full text Clause 52.232-13 "Notice of Progress Payment"
9) Section 00 21 00 Added full text Clause 52.232-16 "Progress Payments"
10) Section 00 21 00 Added full text Clause 52.232-16 "Progress Payments Alternate I"
11) Section 00 21 00 Added full text Clause 52.232-23 "Assignment of Claims"
12) Section 00 21 00 Added full text Clause 52.232-27 "Prompt Payment for Construction Contracts"
13) Section 00 21 00 Added full text Clause 52.232-33 "Payment by Electronic Funds Transfer - System for award Management"
14) Section 00 21 00 Added full text Clause 52.232-39 "Unenforceability of Unauthorized Obligations"
15) Section 00 21 00 Added full text Clause 52.232-40 "Providing Accelerated Payments to Small Business Subcontractors"
16) Section 00 21 00 Edited Clause 52.236-27 "Site Visit"
17) Section 00 21 00 Deleted 52.236-28 "Preparation of Proposals--Construction" from the reference clauses and added same clause in Full Text
18) Section 00 21 00 Deleted 252.204-7004 Alternate A, "Systems for Award Management" from the reference clauses and added same clause in Full Text
19) Section 00 21 00 Deleted 252.209-7001, "Disclosure of Ownership or Control by the Government of a Terrorist Country" from the reference clauses and added same clause in Full Text
20) Section 00 21 00 Added full text Clause 252.219-7009, "Section 8(A) Direct Award"
21) Section 00 21 00 Added full text Clause 252.219-7010, "Alternate A"
22) Section 00 21 00 Deleted 252.236-7008, "Contract Prices-Bidding Schedule" from the reference clauses and added same clause in Full Text
23) Section 00 22 11 Table of Contents. Updated TOC to match section numbers and titles
24) Section 00 22 11 paragraph 5.1.1.1. Allowed experience of parent, sister, predecessor, subcontractor or other affiliated company
25) Section 00 22 11 paragraph 5.1.2.2. Added evaluation of parent, sister, predecessor, subcontractor or other affiliated company.
26) Section 00 22 11 paragraph 5.1.2.5. Deleted last two sentences
27) Section 00 22 11 paragraph 5.2.2.3. Deleted two sentence starting with, "Past performance of a parent..."
28) Section 00 22 11 paragraph 5.2.2.4 added words "parent, sister, and other affiliated company" and replaced word "Experience" with "Past Performance"
29) Section 00 22 11 paragraph 5.3.2 added sentence, "Provide a ‘Letter of Commitment for Key Personnel' for any key personnel not currently employed by the offeror."
30) Section 00 22 11 paragraph 6.5.1.1 added sentence to require Representations and certifications in accordance with FAR clauses found in 00 45 00.
31) Section 00 22 11 Attachment 3, Deleted reference to personnel not requested in 00 22 11.
32) Section "SRM IDIQ Task Order Proposal Schedule (PS) Form" section 4 (b) deleted words "except temporary heat,"

Update #1 ·

Added: Jan 10, 2014 8:14 pm
                                          8 (a) SET ASIDE
Sustainment Restoration Modernization (SRM) PROJECT. VARIOUS LOCATIONS WITHIN ALASKA. NAICS 236220.The w ork includes providing
support on a Small Construction Contract for the USACE, Alaska District., including services for Design-Build Construction (vertical and
horizontal), Construction Only, Sustainment, Renovation and Modernization of real property projects w ith incidental environmental w ork
including, incidental soil, asbestos and HTRW containment/disposal. Planning, designing and constructing new and/or renovated facilities,
utilities and infrastructure for DoD and civilian customers of the USACE, Alaska District. Typical task requirements issued by the US ACE,
Alaska District include those related to Facility Sustainment, Restoration and Modernization, new construction, repairs, incidental demolition
(including HazMAt testing, removal and disposal), facility and system maintenance and upgrade, infrastructure and site improvements. Efforts
may include, but are not limited to, planning, design, and installation/construction of the follow ing systems: facilities construction/renovation,
HVAC, plumbing, electrical, w aste w ater treatment systems, elevators, building envelope, fire protection, AT/FP, demolition, electronic
security systems. This is set aside for 8(a) business.

Attachments

Files attached to this notice, newest first
File Type Posted
SRM_Amendment_4.docx.pdf PDF
SRM_Amend_03.pdf PDF
SRM_AMEND_2.pdf PDF
SRM_IDIQ_RTA_RFPAMEND1_rev_9.pdf PDF
SRM_IDIQ_RTA_RFP_rev_9.pdf PDF
SRM_IDIQ_RTA_RFP_rev_8.pdf PDF

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity