About this opportunity

The U.S. Department of Energy's Southwestern Power Administration (SWPA) is seeking bids for a construction project involving the replacement and disposal of switchboard sections at various substations, along with necessary modifications, addition of cables and materials as per drawings. The project, set aside for small businesses, is estimated to cost between $1,000,000 and $5,000,000, with an expected completion date of April 2025. The solicitation package is anticipated to be released in August 2023, with bids due in September 2023.

Services and Products to be provided:

  1. Replacement of switchboard sections at various substations.
  2. Disposal of old switchboard sections.
  3. Modifications at various substations as per drawings.
  4. Addition of cables and materials as required by the drawings.
  5. Disposal of old IFC and RTU cabinets and equipment, and patching of floor openings post removal.

Notice text

The U.S. Department of Energy, Southwestern Power Administration (SWPA) intends to issue a construction Invitation for Bid (IFB) for the following:

Replace four (4) duplex switchboard sections at SWPA’s Water Valley Substation with two (2) duplex switchboard sections. Perform modifications, add cables and materials as required by the drawings. Dispose of the old switchboard sections from Water Valley Substation.

Perform modifications, add cables and materials as required by the drawings at SWPA’s Jonesboro Substation.

Perform modifications, add cables and materials as required by the drawings at AECC’s Glencoe Substation.

Perform modifications, add cables and materials as required by the drawings at Norfork Dam.

Replace five (5) duplex switchboard sections at SWPA’s Idalia Substation with three (3) duplex switchboard sections. Perform modifications, add cables and materials as required by the drawings. Dispose of the old switchboard sections from Idalia Substation.

Perform modifications, add cables and materials as required by the drawings at SWPA’s Sikeston Substation.

Perform modifications, add cables and materials as required by the drawings at M&A’s Asherville Substation.

Perform modifications, add cables and materials as required by the drawings at Tupelo substation. Dispose of the old IFC and RTU cabinets. Patch opening in the floor after cabinet removal.

Perform modifications, add cables and materials as required by the drawings at Van Buren substation. Dispose of the old IFC and RTU cabinets. Patch opening in the floor after cabinet removal.

Perform modifications, add cables and materials as required by the drawings at Ozark Dam switchyard. Dispose of the old IFC and RTU equipment. Patch opening in the floor after cabinet removal.

Perform modifications, add cables and materials as required by the drawings at R.S. Kerr Dam switchyard. Dispose of the old IFC and RTU cabinets. Patch opening in the floor after cabinet removal.

The Contractor shall provide all personnel, facilities, materials, and equipment required to complete the project, unless otherwise notified in the specification.

This acquisition is a 100% small business set aside. The applicable North American Industry Classification System (NAICS) code for this acquisition is 238210 and the small business size standard is $19 million. In accordance with Federal Acquisition Regulation (FAR) 36.204, the magnitude of this project is currently estimated to be between $1,000,000 and $5,000,000. The estimated project completion date is approximately April 2025.

Contractor registration in the Government’s System for Award Management (SAM) is mandatory in order to be eligible for contract award. Registration may be completed and information regarding the registration process may be obtained at http://www.sam.gov.

The anticipated release date of the solicitation package is early August 2023, with bids being due early September 2023.

Once issued, solicitation documents will be available electronically for download at https://www.SAM.GOV. All responsible sources may submit a bid and will be considered by Southwestern.

Notice history

Notice Type Posted
Water valley / idalia RTU replacements Award Award Notice
Water valley/idalia substation protective relay SW Latest solicitation Solicitation
This notice Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Tenkiller 15KV switchgear and station service replacement NAICS 238210 ENDIST Tulsa Total Small Business
Automatic transfer switch for philip north switchi NAICS 335313 Western Area Power Administration Total Small Business
Electrical Substation Maintenance and Repairs Fort Buchanan, Puerto Rico 00934, United States · NAICS 238210 MICC Fort Hood Total Small Business
LLA Navigation Lock Switchgear Pomeroy, Washington 99347, United States · NAICS 238210 ENDIST Walla Walla Total Small Business
Request for Information/Market Intelligence Notice: Repair Electrical Distribution System Switchgear Stations & Addition of Redundancy Cable Use of Progressive Design Build (PDB) with Other Transaction Authority (OTA) Bolling AFB, District of Columbia 20032, United States · NAICS 238210 District Washington No set-aside