Stegall Substation Stage 07 Phase 01

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
89503226BWA000075
Agency
Western Area Power Administration Department of Energy
Responses due
Set-aside
Total Small Business

Opportunity facts

NAICS code
237130 Power and Communication Line and Related Structures Construction
PSC
Y1PZ Construction Of Other Non-Building Facilities
Points of contact
More information

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of Energy Western Area Power Administration seeks equipment replacements and upgrades at the Stegall Substation as part of Stage 07 Phase 01, with proposals due August 28. The procurement is a Total Small Business set-aside, restricting competition to firms meeting SBA size standards for NAICS 237130.

The project scope includes replacement of a 1960s-era control building, 30+ disconnect switches, brown glass insulators, main bus reconductor with rating increase, two 115kV oil circuit breakers, and a 1990s vintage GE D20 RTU (replaced by three SEL RTACs), plus installation of a transfer bus dead end structure between 230kV east and west interconnect points. The NAICS code is 237130, Power and Communication Line and Related Structures Construction, with PSC Y1PZ (Construction Of Other Non-Building Facilities). Place of performance is the Stegall Substation. Amendment 0001 posted industry Q&A and extended the bid closing date. Amendment 0002 updated drawings with redline markings, extended the bid closing date again, and changed the bid opening date.

Notice text

3 versions

Update #3 · Latest ·

Amendment (0002) is to update Drawings with redline markings, extend bid closing date, and change the bid opening date as part of the Stegall Substation Stage 07 Phase 01 Project.

Update #2 ·

Amendment (0001) is to post Q/A from industry and extend bid closing date as part of the Stegall Substation Stage 07 Phase 01 Project.

Update #1 ·

The Stegall Substation Stage 07 Phase 01 Project (Equipment Replacements and Upgrades) replaces end of life equipment and installs a new control building. Replaced equipment shall include the 1960’s era control building, 30+ disconnect switches, problematic brown glass insulators, main bus reconductor and rating increase, 2-115kV oil circuit breakers, replace 1990’s vintage GE D20 RTU with three SEL RTACs, and add transfer bus dead end structure between 230kV east and west interconnect.

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Stegall Substation Stage 07 Phase 01 Award Award Notice
Stegall Substation Stage 07 Phase 01 This notice · Latest solicitation Solicitation
Stegall Substation Stage 07 Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity