Shoshone NF - Warm Springs Bridge #4
Awarded Award Notice Posted
- Solicitation number
- AG-82X9-S-10-0103
- Agency
- Region 2 - Rocky Mountain Region Forest Service, Department of Agriculture
- Awarded
- to C C & G, Inc.
- Set-aside
- Total Small Business
Opportunity facts
- Contract number
- AG-82X9-C-10-0152 Federal contract award
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- PSC
- Not on record
- Place of performance
- The bridge is located approximately 15 miles northwest of Dubois, Wyoming in the Shoshone National Forest. Dubois, Wyoming 82513, United States
Notice details come from SAM.gov. Updated .
Notice text
Added: Jul 15, 2010 10:09 am
• Remove trees and clear and grub as required.
• Construct the temporary detour.
• Establish the traffic control signing and temporary barriers as required for detour.
• Excavate for footings.
• Construct the footings.
• Construct the abutments and wingwalls to the elevation shown on the plans.
• Backfill the abutments to just below the beam seat elevation.
• Grade portions of the channel banks under the new bridge.
• Install riprap adjacent to the new structure.
• Erect the timber superstructure.
• Construct the remaining abutment and wingwall concrete.
• Construct the remaining backfill and approach embankment.
• Install the approach and bridge rails.
• Install the aggregate surface course
• Shift traffic to the new bridge.
• Remove the detour.
• Install the final traffic control devices as shown on the plans.
• Complete the grading at the location of the detour.
• Complete the riprap installation along the stream.
• Salvage and transport the existing bridge timber stringers.
Attachments
| File | Type | Posted |
|---|---|---|
| WarmSpringsHydroReport.pdf | ||
| AG-82X9-S-10-0103 a 1.pdf | ||
| AG-82X9-S-10-0103.pdf |