About this opportunity
The Western Area Power Administration (WAPA), a Power Marketing Agency under the Department of Energy, is conducting market research to determine the capabilities of potential contractors to perform design-build work for the end-of-lifecycle replacement of four 525-kV series capacitor banks within the California Oregon Transmission Project. The contractor would be responsible for engineering, procurement, and construction to remove and replace the existing series capacitor banks with new in-kind equipment, as well as integrate the new banks into WAPA's existing substation. The applicable NAICS code is 237130 - Power and Communication Line and Related Structures Construction, with a size standard of $45.0M. The estimated construction price range for this project is between $75,000,000 and $125,000,000. Interested parties are encouraged to provide feedback by November 18, 2024, including information on their firm, bonding capability, and past performance on similar design-build projects.
This opportunity is not set aside, and no incumbent contractors are named. The Government anticipates issuing the solicitation within the next 10-14 months, with a targeted completion date of June 30, 2033. Interested firms must be able to demonstrate sufficient bonding capacity within the estimated construction range.
Notice text
This is a Sources Sought/Request for Information only. This is not a Solicitation Announcement, nor is it a Request for Proposal. This request does not obligate the Government in any contract award. Western Area Power Administration (WAPA), a Power Marketing Agency, under Department of Energy, is conducting research to determine the market capabilities of potential contractors to perform the work described herein. No reimbursement will be made for any costs associated with providing information to this RFI or any follow-up information requests.
The contemplated action is a fixed-price Design-Build contract for the design and construction required for end-of-lifecyle replacement of four (4) banks of 525-kV series capacitors installed within the California Oregon Transmission Project (COTP), which consists of the Tracy-Olinda and Olinda-Captain Jack 525-kV transmission lines. Performance would begin at time of award, with completion no later than June 30th, 2033. The Contractor would engineer, procure and construct (EPC) by removing and replacing the existing series capacitor banks with new and in-kind series capacitor banks (no changes to series capacitor size, rating, segmentation, and line compensation level). The Contractor shall perform engineering design for full integration of new series capacitor banks into WAPA’s existing substation; as well as procure, install, test and commission all equipment.
The applicable North American Industry Classification System (NAICS) code is 237130, Power and Communication Line and Related Structures Construction, with a size standard of $45.0M. The estimated construction price range for this project is between $75,000,000 and $125,000,000. The Government anticipates that the solicitation will be issued in 10-14 months.
Interested parties having ability to meet this requirement are encouraged to provide feedback via email to Angela Xavier at xavier@WAPA.GOV by 11/18/2024, 10:30 am Pacific Time. Phone calls will not be accepted. Interested firms should submit the following information:
- Name & Address of your firm
- Point of Contact (Name/Phone/E-mail)
- Current SAM.gov registered UEI and CAGE codes
- Business Size, to include designation such as HUBZone, 8(a), Service-Disabled Veteran Owned Small Business, Small Disadvantaged Business, Woman-Owned Business, and Large Business.
- Evidence of Bonding capability (construction bonding level per contract and aggregate construction bonding level, both expressed in dollars). Interested Firms should be able to demonstrate bonding capacity within the estimated construction range listed above.
- Past performance of similar Design-Build projects in the past 10 years. Be sure to include:
- Project name and description of the key/salient features of the project
- Completion date
- Total contract construction value
- Description of the Design-Build team, to include name and role of each firm (for example…Architect-Engineer, Geotechnical, Construction, Equipment Manufacturer/Supplier).
- Description of how the Design-Build team coordinated efforts to deliver quality work on time and in accordance with the Contract.
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| COTP Series Capacitor Two-Phase Design Build | Department of Energy | No set-aside | |
| CSSC Utility Feed Transformer Replacement | ENDIST Chicago | No set-aside |