San Antonio Missions National Historical Park - Re

Award Notice Posted

Solicitation number
140P1320Q0045
Agency
Awarded
to The Tradesmen Group, LLC
Set-aside
No set-aside

Opportunity facts

Contract number
140P1320P0104 Federal contract award
NAICS code
238140 Masonry Contractors
PSC
Z2QA Repair Or Alteration Of Restoration Of Real Property (Public Or Private)

Notice details come from SAM.gov. Updated .

Notice text

San Antonio Missions National Historical Park - Rehabilitation and Stabilization of the Mission Espada North Gate per the scope of work.

Task 1: Assessment of necessary changes to the existing gate in order to straighten the walls and

stabilize the two wall sections.

a. Park Staff will approve design prior to deconstruction of the existing walls.

b. The design should be minimally invasive to the existing Spanish Colonial foundations and other

potential archeological features.

Task 2. Deconstruction of existing walls in such a way as to map location of stones and allow

reconstruction as closely as possible to existing gates as structural stability will allow.

a. Deconstruction should also be done in a way to preserve the stone as much as possible.

b. All ground disturbing activities in deconstruction and reconstruction will be monitored by

professional archeologists.

Task 3. Reconstruction of the two wall sections. This reconstruction should follow the previous design as

closely as possible, allowing for structural stability.

a. Replacement mortar should use the mortar mix identified below.

b. If the footprint for rehabilitation and stabilization goes beyond the 2019 archeological

investigations, further archeological investigations will be required.

c. Removal of any archeological features during the project will only be done after consultation

with the park COR.

d. Reconstruction of the two wall sections should be done in a way to minimize damage to the

Spanish Colonial foundations.

e. Spanish colonial Foundations should be protected from modern footers or construction with

landscape fabric and if necessary, a protective layer of sand or small gravel to protect it.

f. If replacement stone is necessary, it should match the type and style of the existing stone to the

extent possible.

Task 4: Final Documentation

1. Before and after photographs.

2. Design plans and as¿built drawings.

3. Archeological report on monitoring and any excavations that meets SHPO guidelines Awarded contract 140P1320P0104 to TRADESMEN GROUP, INC., THE for 108942 on 2020-09-08.

Notice history

Notice Type Posted
This notice Award Award Notice
SAAN -Rehabilitation and Stabilization of Gate Latest solicitation Solicitation

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors