About this opportunity
The Sacramento River Erosion Contract 2 solicitation seeks placement of approximately 3 miles of rock revetment between river miles 60 and 45 on the Sacramento River east levee by the U.S. Army Corps of Engineers Sacramento District. The purpose is to address erosion and levee failure risk through rock placement by barge-mounted heavy equipment along the levee slope and riparian bench. Improvements also include bank-fill revetment, lower slope quarry stone, slope protection, plantings and in-stream woody material. Interested parties can obtain additional details by visiting the provided website and must submit proposals by January 25, 2023.
There is no set-aside designated for this procurement. The work requires rock placement and slope protection along 3 miles of levee between December 2022 and December 2023. The only offeror was The Dutra Group, who provided the required 20% bid bond. The government estimate was $1 million for the contract. The NAICS code is 237990 and PSC code is R499 for the erosion control and bank stabilization work along the Sacramento River in California.
Notice text
5 versions
Update #5 · Latest ·
**** 1 Feb 2023: This notice provides the bid abstract from the 25 Jan 2023 bid opening ****
AMENDMENT 0002 - Provides updated spec section and an updated wage determination. Sacramento River Erosion Contract 2 will address erosion and levee failure risk to the Sacramento River east levee (SREL) through the placement of approximately 3 miles of rock revetment between the confluence of the American River and the City of Freeport (between river mile 60 and river mile 45). The contract will require rock-placement on the levee by a barge, though heavy equipment may be used (from the barge) along the rock platform to place rock along the levee slope. Heavy equipment is not permitted to be brought in from the crown of the levee. Improvements include bank-fill revetment, riparian bench, lower slope quarry stone and slope protection including plantings and in-stream woody material.
Update #4 ·
AMENDMENT 0002 - Provides updated spec section and an updated wage determination. Sacramento River Erosion Contract 2 will address erosion and levee failure risk to the Sacramento River east levee (SREL) through the placement of approximately 3 miles of rock revetment between the confluence of the American River and the City of Freeport (between river mile 60 and river mile 45). The contract will require rock-placement on the levee by a barge, though heavy equipment may be used (from the barge) along the rock platform to place rock along the levee slope. Heavy equipment is not permitted to be brought in from the crown of the levee. Improvements include bank-fill revetment, riparian bench, lower slope quarry stone and slope protection including plantings and in-stream woody material.
Update #3 ·
AMENDMENT 0001 - Provides updated spec sections, HPMP, updated wage determination and updated price schedule. Please note the new bid due date of 25 January at 9am. Sacramento River Erosion Contract 2 will address erosion and levee failure risk to the Sacramento River east levee (SREL) through the placement of approximately 3 miles of rock revetment between the confluence of the American River and the City of Freeport (between river mile 60 and river mile 45). The contract will require rock-placement on the levee by a barge, though heavy equipment may be used (from the barge) along the rock platform to place rock along the levee slope. Heavy equipment is not permitted to be brought in from the crown of the levee. Improvements include bank-fill revetment, riparian bench, lower slope quarry stone and slope protection including plantings and in-stream woody material.
Update #2 ·
***** 21 Dec 2022: The purpose of this update is to add the attached Site Visit Sign In Sheet from today's site visit *****
Sacramento River Erosion Contract 2 will address erosion and levee failure risk to the Sacramento River east levee (SREL) through the placement of approximately 3 miles of rock revetment between the confluence of the American River and the City of Freeport (between river mile 60 and river mile 45). The contract will require rock-placement on the levee by a barge, though heavy equipment may be used (from the barge) along the rock platform to place rock along the levee slope. Heavy equipment is not permitted to be brought in from the crown of the levee. Improvements include bank-fill revetment, riparian bench, lower slope quarry stone and slope protection including plantings and in-stream woody material. *Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W9123823B0009' to obtain more details.*
Update #1 ·
Sacramento River Erosion Contract 2 will address erosion and levee failure risk to the Sacramento River east levee (SREL) through the placement of approximately 3 miles of rock revetment between the confluence of the American River and the City of Freeport (between river mile 60 and river mile 45). The contract will require rock-placement on the levee by a barge, though heavy equipment may be used (from the barge) along the rock platform to place rock along the levee slope. Heavy equipment is not permitted to be brought in from the crown of the levee. Improvements include bank-fill revetment, riparian bench, lower slope quarry stone and slope protection including plantings and in-stream woody material. *Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W9123823B0009' to obtain more details.*
Files
| File | Type | Posted |
|---|---|---|
| C04 Abstract for Construction W9123823B0009_Signed.pdf | ||
| B07 Site Visit Sign In Sheet.pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Sacramento River Erosion Contract 2 | Award Notice | |
| This notice | Solicitation | |
| Sacramento River Erosion, Contract 2 | Pre-Solicitation | |
| Sacramento River Erosion, Contract 2 - Project Labor Agreements | Special Notice |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| USACE SPK DB Construction - Natomas NPP Named Pumping Plants - Sacramento, CA | ENDIST Sacramento | No set-aside | |
| Grand Island Mitigation Site | ENDIST Sacramento | No set-aside |