SAC river erosion, contract 2
Ended Definitive Contract Awarded Last action
- Contract number
- W9123823C0007
- Awardee
-
San Rafael Rock Quarry, Inc. UEI PH56DGH9LEF3 Part of The Dutra Group
- Awarding agency
-
ENDIST Sacramento
US Army Corps of Engineers, Department of Defense
- Obligated
- $82,302,740
Award facts
- Opportunity
-
- Sacramento River Erosion, Contract 2 - Project Labor Agreements Special Notice · W9123823B0009 · Posted Nov 30, 2022
- Contract value 95% obligated
-
- $82,302,739.81 Current, with exercised options
- $86,286,179.81 Potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Contracting staff
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Set-aside
- No set-aside
- Competition
- 1 offer Sealed Bid
- Pricing
- Firm Fixed Price
- Place of performance
- Sacramento, CA 95814, USA
- Legislative mandates
-
- Davis-Bacon Act FAR subpart 22.4
- Employment Eligibility Verification (E-Verify) FAR subpart 22.18
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Supplemental Agreement for work within scope | $3,268,677 | |
| Change Order | $4,710 | |
| Supplemental Agreement for work within scope | $24,640 | |
| Supplemental Agreement for work within scope | $125,934 | |
| Supplemental Agreement for work within scope | $32,479 | |
| Supplemental Agreement for work within scope | $46,160 | |
| Supplemental Agreement for work within scope | $6,400 | |
| Supplemental Agreement for work within scope | $198,000 | |
| Supplemental Agreement for work within scope | $20,465 | |
| Supplemental Agreement for work within scope | $1,359,790 | |
| Supplemental Agreement for work within scope | $297,000 | |
| Supplemental Agreement for work within scope | $2,660,059 | |
| Supplemental Agreement for work within scope | $12,677 | |
| Supplemental Agreement for work within scope | $242,073 | |
| Other Administrative Action | $0 | |
| Original award | $73,863,110 |
Show all 16
About this award
San Rafael Rock Quarry, Inc., a subsidiary of The Dutra Group, was awarded a $86.3 million firm fixed-price definitive contract by the U.S. Army Corps of Engineers Sacramento District on March 10, 2023, for the Sacramento River Erosion Contract 2 project. The work involves quarry stone removal and placement of rock revetment along approximately 3 miles of the Sacramento River's east levee between river miles 60 and 45 to address erosion and levee failure risk. The contract is not a small business set-aside and was awarded on an unrestricted, full and open competitive basis. Performance is scheduled for completion by October 31, 2025, with work taking place in Sacramento, California. The Dutra Group, through its subsidiary, brings extensive expertise in dredging, marine construction, material placement, and coastal engineering projects, having secured numerous other significant federal contracts totaling hundreds of millions of dollars with the Army Corps of Engineers and Department of the Navy in recent years.
The contract includes a comprehensive subcontractor network supporting project execution across specialized disciplines. Major subcontractors include Brusco Tug & Barge, Inc. for tug and marine support services; Towill, Inc. and Woolpert, Inc. for surveying and geospatial data collection; The Davey Tree Expert Company for tree trimming and removal; Odin Environmental Solutions, LLC for mobilization and site work; and multiple equipment rental providers including Norcal Rental Group, Rasmussen Equipment Holdings, and Poseidon, LLC for barges and specialized marine equipment. Additional support services are provided by environmental monitoring firms (Alluvion Biological Consulting, Youngdahl Consulting Group), fuel suppliers (Yaypen Supply, Ryzhka International), and specialized service providers for archaeological monitoring, electrical work, and erosion control measures, ensuring comprehensive execution of this critical river infrastructure project.
Subawards
| Subcontractor | Amount | Awarded |
|---|---|---|
| The Davey Tree Expert Company | $39,910 | |
| JRM Equipment LLC | $38,250 | |
| Greger Pacific Marine Inc. | $88,500 | |
| Subcontractor not on record | $82,946 | |
| Towill, Inc. | $403,969 | |
| Yaypen Supply, LLC | $895,371 | |
| Billeter Marine LLC | $392,665 | |
| Brusco Tug & Barge, Inc. | $2,463,323 | |
| Subcontractor not on record | $232,653 | |
| Rasmussen Equipment Holdings Company, Inc. | $55,797 | |
| Norcal Rental Group LLC | $220,874 | |
| Woolpert, Inc. | $46,161 | |
| Nick Barbieri Trucking, LLC | $129,427 | |
| Poseidon,Llc | $216,424 | |
| Sitech Norcal, Inc. | $289,357 | |
| Silverado Contractors, Inc. | $237,412 | |
| Selby's Soil Erosion Control Co., Inc. | $329,738 | |
| Kiewit Infrastructure West CO. | $180,000 | |
| Odin Environmental Solutions, LLC | $2,719,482 | |
| Subcontractor not on record | $271,177 | |
| Ryzhka International LLC | $542,809 | |
| Collins Electrical Co Inc. | $58,271 | |
| Alluvion Biological Consulting LLC | $176,340 | |
| Tremaine & Associates, Inc. | $36,337 | |
| Youngdahl Consulting Group, Inc. | $48,760 |
Show all 25
Quick answers
Who was awarded contract W9123823C0007?
W9123823C0007 was awarded to San Rafael Rock Quarry, Inc. by ENDIST Sacramento (US Army Corps of Engineers) on March 10, 2023.
How much is contract W9123823C0007 worth?
The government has obligated $82,302,740 on W9123823C0007. Its potential value, with all options, is $86,286,180.
Was contract W9123823C0007 competed?
The government received 1 offer.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award