About this opportunity

The Department of Energy is seeking information to develop one or more carbon-free energy generation facilities at the Savannah River Site in South Carolina by 2030 to fully offset the site's annual electricity consumption of approximately 360,000 megawatt hours. Interested offerors must have experience siting, designing, permitting, constructing, interconnecting, licensing, operating and maintaining such facilities. Responses are due by January 2, 2024 and must demonstrate the offeror's capabilities, experience complying with applicable regulations, and preferred contract length.

There is no set-aside designation. The NAICS code is 221114 for solar electric power generation. Key details include four potentially suitable tracts of land totaling over 8,000 acres that could accommodate various carbon-free technologies. The contract is anticipated to have a long-term lease structure under which the selected offeror would generate energy attribute certificates to offset the site's consumption over the lease period while retaining ownership of any excess certificates.

Notice text

4 versions

Update #4 · Latest ·

Introduction:

THIS IS A REQUEST FOR INFORMATION (RFI).  This RFI is issued solely for information and planning 

purposes and does not constitute a solicitation.

The Department of Energy (DOE) is working toward the goal of using 100% carbon-free energy (CFE) at 

all DOE sites by the year 2030.  The Savannah River Site (SRS) is one of the largest consumers of 

electricity within the DOE complex.  The Site is located on 310 square miles (approximately 200,000 

acres) of DOE owned and largely forested land in western South Carolina along the Savannah River 

near the town of Jackson, SC.

SRS will focus on offsetting the annual electricity consumption by generating an equivalent amount 

of electricity using any CFE technology, e.g., solar, small modular reactors, geothermal, and wind, 

that can deliver carbon-free energy in the form of electricity to the electric grid.  To fully 

offset the typical amount of electricity consumed, it is estimated that SRS would need to offset 

approximately 180,000 MWh annually by 2030 and 360,000 MWh annually by 2032.

Savannah River Site would also like to consider opportunities for energy storage in addition to CFE 

generation.  Ultimately, SRS would like to generate as much of carbon-free energy as SRS resources 

can support without impacting the site’s primary mission. The Federal Acquisition Regulation (FAR) 

and Department of Energy Acquisition Regulation (DEAR) will be used for this acquisition along with 

NAICS code 221114 Solar Electric Power Generation.

Due Date for Responses:  12:00pm on Tuesday, January 2, 2024

Point of Contact: Jeff Hynds (jeff.hynds@srs.gov)

Project Description:

Four tracts of land have been initially identified as potential locations for CFE power generation. 

These four tracts are indicated on the included map.  Each tract is 2000+ acres of reasonably flat 

ground.  Each tract could be developed with access to the site from a public road.  The four tracts 

that have been identified may not necessarily be the optimum locations for some CFE technologies.  

Other tracts of land more suitable to different CFE technologies can be considered as required.  

DOE may decide to lease part or all the available land, or award leases to one or multiple entities.

In exchange for favorable lease terms and a waiver of property taxes, the selected firm would 

provide the U. S. Government with the number of Energy Attribute Certificates (EACs) commonly referred to as Renewable Energy Certificates (RECs) required to fully offset the typical annual power consumption of approximately 360,000 MWh, to the extent permitted by law.  Disposition of any additional Renewable energy credits created by CFE generation at SRS beyond the number required to offset SRS consumption would be solely at the discretion of the CFE installation owner.

A long-term lease agreement is anticipated.  The Department of Energy is anticipating a turnkey 

agreement with the selected firm managing and financing all tasks related siting, designing, 

environmental permitting, including NEPA, construction, interconnection, licensing, operation, and 

maintenance of the CFE facility or facilities on land leased from DOE.  At the end of its useful 

life, the selected firm shall be responsible for removal and proper dispositioning of all equipment 

and restoration of the site.  The selected firm will be required to set aside funding during the 

period of the lease, such that there are sufficient funds available to restore the land at the end 

of the lease period.

It is anticipated that the selected firm will own and operate the finished CFE facility upon 

completion of construction. The selected firm will produce EACs by operating the CFE facility and 

will provide the required number of EACs to SRS each year of the lease agreement between SRS and 

the firm.

It is the responsibility of the selected firm to negotiate and establish agreements with the off- 

taking utility.  Interconnection to the off-taking utility’s power grid and any associated costs 

are the responsibility of the selected firm.  The CFE facility will not supply power directly to 

the SRS onsite grid.  If the CFE facility power generation is not isolated from the SRS onsite 

power grid, then the selected firm may be responsible for the additional maintenance and operations 

to ensure the CFE facility does not interfere with the SRS mission.

All the currently identified tracts of land can be accessed directly from an existing State or 

Federal highway without passing through an SRS barricade.  The selected firm will construct a fence 

around the entire CFE facility and maintain controlled access to the facility.

The facility will be located within the state of South Carolina and must meet all applicable state 

and federal regulations.  It is anticipated that the selected firm will have experience in 

compliance with state and federal regulatory reviews and permitting projects on federal land, the 

National Environmental Policy Act, National Historic Preservation Act, and Endangered Species Act.

The electricity market in South Carolina is a “regulated monopoly” managed by the South Carolina 

Public Service Commission (https://www.psc.sc.gov).  The region where SRS is located is assigned to 

Dominion Energy South Carolina (https://www.dominionenergy.com/south-carolina), formerly South 

Carolina Electric and Gas Company. The Southeast Energy Exchange Market (https://southeastenergymarket.com) provides 

opportunities for 15-minute energy trading in this area.

Capability Statement:

The following request is designed to provide information to the Department of Energy of any 

prospective developer of CFE power generation facilities with capabilities to execute the 

requirements as described above.

Please provide in your response to the following:

1.   Offeror's Name, Address, Point of Contact, Phone Number, and E-Mail Address.

2.   Offeror's interest in bidding on the solicitation when it is issued.

3.   Offeror's business size certified status, number of years in business, and your DUNS number.

4.   Offeror's capability statement demonstrating the Offeror's ability to perform comparable work. 

The statement should include a brief description of the three (3) most recently completed and 

comparable projects.  For each project include the customer’s name, offeror’s scope within the 

project, project duration, size of the CFE facility, location of the facility and whether the 

offeror retained ownership of the operating CFE facility.

5.   Offeror’s experience in compliance with state and federal regulatory reviews and permitting 

projects on federal land, the National Environmental Policy Act, National Historic Preservation 

Act, and Endangered Species Act, to address such elements as ecological, environmental, and 

cultural considerations associated with ground-disturbing and visual-affecting activities. 

Information in this item can be consolidated with item #4 above if applicable.

6.   What is the preferred contract/lease length for this type of contractual arrangement?

7.   Do you have any other suggestions or comments to improve future solicitations?

Disclaimer:

This RFI is issued solely for information and planning purposes and does not constitute a 

solicitation. Responses to this notice are not offers and cannot be accepted by the Government to 

form a binding contract.  SRS is not seeking proposals through this RFI and will not accept 

unsolicited proposals. Respondents are solely responsible for all expenses associated with 

responding to this RFI.  Not responding to this RFI does not preclude participation in any future 

procurement, if conducted.  No proprietary information should be included in any submittal.

How to Respond:

ALL interested Offerors should notify in writing via e-mail by 12:00pm EST on Tuesday, January 2, 

2024. Submit your response and information by e-mail to: Jeff.Hynds@srs.gov with the subject line 

“SRS CFE RFI Response”. Responses are limited to 10 pages (11-point font, 1-inch margins). Please 

include contact name(s), address, phone, and e-mail. Any questions regarding the RFI should be 

included in the RFI response. These questions will be addressed after the

RFI response due date with a FAQ document to everyone submitting a response.

Update #3 ·

Introduction:

THIS IS A REQUEST FOR INFORMATION (RFI).  This RFI is issued solely for information and planning 

purposes and does not constitute a solicitation.

The Department of Energy (DOE) is working toward the goal of using 100% carbon-free energy (CFE) at 

all DOE sites by the year 2030.  The Savannah River Site (SRS) is one of the largest consumers of 

electricity within the DOE complex.  The Site is located on 310 square miles (approximately 200,000 

acres) of DOE owned and largely forested land in western South Carolina along the Savannah River 

near the town of Jackson, SC.

SRS will focus on offsetting the annual electricity consumption by generating an equivalent amount 

of electricity using any CFE technology, e.g., solar, small modular reactors, geothermal, and wind, 

that can deliver carbon-free energy in the form of electricity to the electric grid.  To fully 

offset the typical amount of electricity consumed, it is estimated that SRS would need to offset 

approximately 180,000 MWh annually by 2030 and 360,000 MWh annually by 2032.

Savannah River Site would also like to consider opportunities for energy storage in addition to CFE 

generation.  Ultimately, SRS would like to generate as much of carbon-free energy as SRS resources 

can support without impacting the site’s primary mission. The Federal Acquisition Regulation (FAR) 

and Department of Energy Acquisition Regulation (DEAR) will be used for this acquisition along with 

NAICS code 221114 Solar Electric Power Generation.

Due Date for Responses:  12:00pm on Friday, November 17, 2023

Point of Contact: Jeff Hynds (jeff.hynds@srs.gov)

Project Description:

Four tracts of land have been initially identified as potential locations for CFE power generation. 

These four tracts are indicated on the included map.  Each tract is 2000+ acres of reasonably flat 

ground.  Each tract could be developed with access to the site from a public road.  The four tracts 

that have been identified may not necessarily be the optimum locations for some CFE technologies.  

Other tracts of land more suitable to different CFE technologies can be considered as required.  

DOE may decide to lease part or all the available land, or award leases to one or multiple entities.

In exchange for favorable lease terms and a waiver of property taxes, the selected firm would 

provide the U. S. Government with the number of Energy Attribute Certificates (EACs) commonly referred to as Renewable Energy Certificates (RECs) required to fully offset the typical annual power consumption of approximately 360,000 MWh, to the extent permitted by law.  Disposition of any additional Renewable energy credits created by CFE generation at SRS beyond the number required to offset SRS consumption would be solely at the discretion of the CFE installation owner.

A long-term lease agreement is anticipated.  The Department of Energy is anticipating a turnkey 

agreement with the selected firm managing and financing all tasks related siting, designing, 

environmental permitting, including NEPA, construction, interconnection, licensing, operation, and 

maintenance of the CFE facility or facilities on land leased from DOE.  At the end of its useful 

life, the selected firm shall be responsible for removal and proper dispositioning of all equipment 

and restoration of the site.  The selected firm will be required to set aside funding during the 

period of the lease, such that there are sufficient funds available to restore the land at the end 

of the lease period.

It is anticipated that the selected firm will own and operate the finished CFE facility upon 

completion of construction. The selected firm will produce EACs by operating the CFE facility and 

will provide the required number of EACs to SRS each year of the lease agreement between SRS and 

the firm.

It is the responsibility of the selected firm to negotiate and establish agreements with the off- 

taking utility.  Interconnection to the off-taking utility’s power grid and any associated costs 

are the responsibility of the selected firm.  The CFE facility will not supply power directly to 

the SRS onsite grid.  If the CFE facility power generation is not isolated from the SRS onsite 

power grid, then the selected firm may be responsible for the additional maintenance and operations 

to ensure the CFE facility does not interfere with the SRS mission.

All the currently identified tracts of land can be accessed directly from an existing State or 

Federal highway without passing through an SRS barricade.  The selected firm will construct a fence 

around the entire CFE facility and maintain controlled access to the facility.

The facility will be located within the state of South Carolina and must meet all applicable state 

and federal regulations.  It is anticipated that the selected firm will have experience in 

compliance with state and federal regulatory reviews and permitting projects on federal land, the 

National Environmental Policy Act, National Historic Preservation Act, and Endangered Species Act.

The electricity market in South Carolina is a “regulated monopoly” managed by the South Carolina 

Public Service Commission (https://www.psc.sc.gov).  The region where SRS is located is assigned to 

Dominion Energy South Carolina (https://www.dominionenergy.com/south-carolina), formerly South 

Carolina Electric and Gas Company. The Southeast Energy Exchange Market (https://southeastenergymarket.com) provides 

opportunities for 15-minute energy trading in this area.

Capability Statement:

The following request is designed to provide information to the Department of Energy of any 

prospective developer of CFE power generation facilities with capabilities to execute the 

requirements as described above.

Please provide in your response to the following:

1.   Offeror's Name, Address, Point of Contact, Phone Number, and E-Mail Address.

2.   Offeror's interest in bidding on the solicitation when it is issued.

3.   Offeror's business size certified status, number of years in business, and your DUNS number.

4.   Offeror's capability statement demonstrating the Offeror's ability to perform comparable work. 

The statement should include a brief description of the three (3) most recently completed and 

comparable projects.  For each project include the customer’s name, offeror’s scope within the 

project, project duration, size of the CFE facility, location of the facility and whether the 

offeror retained ownership of the operating CFE facility.

5.   Offeror’s experience in compliance with state and federal regulatory reviews and permitting 

projects on federal land, the National Environmental Policy Act, National Historic Preservation 

Act, and Endangered Species Act, to address such elements as ecological, environmental, and 

cultural considerations associated with ground-disturbing and visual-affecting activities. 

Information in this item can be consolidated with item #4 above if applicable.

6.   What is the preferred contract/lease length for this type of contractual arrangement?

7.   Do you have any other suggestions or comments to improve future solicitations?

Disclaimer:

This RFI is issued solely for information and planning purposes and does not constitute a 

solicitation. Responses to this notice are not offers and cannot be accepted by the Government to 

form a binding contract.  SRS is not seeking proposals through this RFI and will not accept 

unsolicited proposals. Respondents are solely responsible for all expenses associated with 

responding to this RFI.  Not responding to this RFI does not preclude participation in any future 

procurement, if conducted.  No proprietary information should be included in any submittal.

How to Respond:

ALL interested Offerors should notify in writing via e-mail by 12:00pm EST on Tuesday, January 2, 

2024. Submit your response and information by e-mail to: Jeff.Hynds@srs.gov with the subject line 

“SRS CFE RFI Response”. Responses are limited to 10 pages (11-point font, 1-inch margins). Please 

include contact name(s), address, phone, and e-mail. Any questions regarding the RFI should be 

included in the RFI response. These questions will be addressed after the

RFI response due date with a FAQ document to everyone submitting a response.

Update #2 ·

Introduction:

THIS IS A REQUEST FOR INFORMATION (RFI).  This RFI is issued solely for information and planning 

purposes and does not constitute a solicitation.

The Department of Energy (DOE) is working toward the goal of using 100% carbon-free energy (CFE) at 

all DOE sites by the year 2030.  The Savannah River Site (SRS) is one of the largest consumers of 

electricity within the DOE complex.  The Site is located on 310 square miles (approximately 200,000 

acres) of DOE owned and largely forested land in western South Carolina along the Savannah River 

near the town of Jackson, SC.

SRS will focus on offsetting the annual electricity consumption by generating an equivalent amount 

of electricity using any CFE technology, e.g., solar, small modular reactors, geothermal, and wind, 

that can deliver carbon-free energy in the form of electricity to the electric grid.  To fully 

offset the typical amount of electricity consumed, it is estimated that SRS would need to offset 

approximately 180,000 MWh annually by 2030 and 360,000 MWh annually by 2032.

Savannah River Site would also like to consider opportunities for energy storage in addition to CFE 

generation.  Ultimately, SRS would like to generate as much of carbon-free energy as SRS resources 

can support without impacting the site’s primary mission. The Federal Acquisition Regulation (FAR) 

and Department of Energy Acquisition Regulation (DEAR) will be used for this acquisition along with 

NAICS code 221114 Solar Electric Power Generation.

Due Date for Responses:  12:00pm on Friday, November 17, 2023

Point of Contact: Jeff Hynds (jeff.hynds@srs.gov)

Project Description:

Four tracts of land have been initially identified as potential locations for CFE power generation. 

These four tracts are indicated on the included map.  Each tract is 2000+ acres of reasonably flat 

ground.  Each tract could be developed with access to the site from a public road.  The four tracts 

that have been identified may not necessarily be the optimum locations for some CFE technologies.  

Other tracts of land more suitable to different CFE technologies can be considered as required.  

DOE may decide to lease part or all the available land, or award leases to one or multiple entities.

In exchange for favorable lease terms and a waiver of property taxes, the selected firm would 

provide the U. S. Government with the number of Energy Attribute Certificates (EACs) commonly referred to as Renewable Energy Certificates (RECs) required to fully offset the typical annual power consumption of approximately 360,000 MWh, to the extent permitted by law.  Disposition of any additional Renewable energy credits created by CFE generation at SRS beyond the number required to offset SRS consumption would be solely at the discretion of the CFE installation owner.

A long-term lease agreement is anticipated.  The Department of Energy is anticipating a turnkey 

agreement with the selected firm managing and financing all tasks related siting, designing, 

environmental permitting, including NEPA, construction, interconnection, licensing, operation, and 

maintenance of the CFE facility or facilities on land leased from DOE.  At the end of its useful 

life, the selected firm shall be responsible for removal and proper dispositioning of all equipment 

and restoration of the site.  The selected firm will be required to set aside funding during the 

period of the lease, such that there are sufficient funds available to restore the land at the end 

of the lease period.

It is anticipated that the selected firm will own and operate the finished CFE facility upon 

completion of construction. The selected firm will produce EACs by operating the CFE facility and 

will provide the required number of EACs to SRS each year of the lease agreement between SRS and 

the firm.

It is the responsibility of the selected firm to negotiate and establish agreements with the off- 

taking utility.  Interconnection to the off-taking utility’s power grid and any associated costs 

are the responsibility of the selected firm.  The CFE facility will not supply power directly to 

the SRS onsite grid.  If the CFE facility power generation is not isolated from the SRS onsite 

power grid, then the selected firm may be responsible for the additional maintenance and operations 

to ensure the CFE facility does not interfere with the SRS mission.

All the currently identified tracts of land can be accessed directly from an existing State or 

Federal highway without passing through an SRS barricade.  The selected firm will construct a fence 

around the entire CFE facility and maintain controlled access to the facility.

The facility will be located within the state of South Carolina and must meet all applicable state 

and federal regulations.  It is anticipated that the selected firm will have experience in 

compliance with state and federal regulatory reviews and permitting projects on federal land, the 

National Environmental Policy Act, National Historic Preservation Act, and Endangered Species Act.

The electricity market in South Carolina is a “regulated monopoly” managed by the South Carolina 

Public Service Commission (https://www.psc.sc.gov).  The region where SRS is located is assigned to 

Dominion Energy South Carolina (https://www.dominionenergy.com/south-carolina), formerly South 

Carolina Electric and Gas Company. The Southeast Energy Exchange Market (https://southeastenergymarket.com) provides 

opportunities for 15-minute energy trading in this area.

Capability Statement:

The following request is designed to provide information to the Department of Energy of any 

prospective developer of CFE power generation facilities with capabilities to execute the 

requirements as described above.

Please provide in your response to the following:

1.   Offeror's Name, Address, Point of Contact, Phone Number, and E-Mail Address.

2.   Offeror's interest in bidding on the solicitation when it is issued.

3.   Offeror's business size certified status, number of years in business, and your DUNS number.

4.   Offeror's capability statement demonstrating the Offeror's ability to perform comparable work. 

The statement should include a brief description of the three (3) most recently completed and 

comparable projects.  For each project include the customer’s name, offeror’s scope within the 

project, project duration, size of the CFE facility, location of the facility and whether the 

offeror retained ownership of the operating CFE facility.

5.   Offeror’s experience in compliance with state and federal regulatory reviews and permitting 

projects on federal land, the National Environmental Policy Act, National Historic Preservation 

Act, and Endangered Species Act, to address such elements as ecological, environmental, and 

cultural considerations associated with ground-disturbing and visual-affecting activities. 

Information in this item can be consolidated with item #4 above if applicable.

6.   What is the preferred contract/lease length for this type of contractual arrangement?

7.   Do you have any other suggestions or comments to improve future solicitations?

Disclaimer:

This RFI is issued solely for information and planning purposes and does not constitute a 

solicitation. Responses to this notice are not offers and cannot be accepted by the Government to 

form a binding contract.  SRS is not seeking proposals through this RFI and will not accept 

unsolicited proposals. Respondents are solely responsible for all expenses associated with 

responding to this RFI.  Not responding to this RFI does not preclude participation in any future 

procurement, if conducted.  No proprietary information should be included in any submittal.

How to Respond:

ALL interested Offerors should notify in writing via e-mail by 12:00pm EST on Friday, November 17, 

2023. Submit your response and information by e-mail to: Jeff.Hynds@srs.gov with the subject line 

“SRS CFE RFI Response”. Responses are limited to 10 pages (11-point font, 1-inch margins). Please 

include contact name(s), address, phone, and e-mail. Any questions regarding the RFI should be 

included in the RFI response. These questions will be addressed after the

RFI response due date with a FAQ document to everyone submitting a response.

Update #1 ·

Introduction:
THIS IS A REQUEST FOR INFORMATION (RFI).  This RFI is issued solely for information and planning 
purposes and does not constitute a solicitation.

The Department of Energy (DOE) is working toward the goal of using 100% carbon-free energy (CFE) at 
all DOE sites by the year 2030.  The Savannah River Site (SRS) is one of the largest consumers of 
electricity within the DOE complex.  The Site is located on 310 square miles (approximately 200,000 
acres) of DOE owned and largely forested land in eastern South Carolina along the Savannah River 
near the town of Jackson, SC.

SRS will focus on offsetting the annual electricity consumption by generating an equivalent amount 
of electricity using any CFE technology, e.g., solar, small modular reactors, geothermal, and wind, 
that can deliver carbon-free energy in the form of electricity to the electric grid.  To fully 
offset the typical amount of electricity consumed, it is estimated that SRS would need to offset 
approximately 180,000 MWh annually by 2030 and 360,000 MWh annually by 2032.

Savannah River Site would also like to consider opportunities for energy storage in addition to CFE 
generation.  Ultimately, SRS would like to generate as much of carbon-free energy as SRS resources 
can support without impacting the site’s primary mission. The Federal Acquisition Regulation (FAR) 
and Department of Energy Acquisition Regulation (DEAR) will be used for this acquisition along with 
NAICS code 221114 Solar Electric Power Generation.

Due Date for Responses:  12:00pm on Friday, November 17, 2023

Point of Contact: Jeff Hynds (jeff.hynds@srs.gov)


Project Description:

Four tracts of land have been initially identified as potential locations for CFE power generation. 
These four tracts are indicated on the included map.  Each tract is 2000+ acres of reasonably flat 
ground.  Each tract could be developed with access to the site from a public road.  The four tracts 
that have been identified may not necessarily be the optimum locations for some CFE technologies.  
Other tracts of land more suitable to different CFE technologies can be considered as required.  
DOE may decide to lease part or all the available land, or award leases
to one or multiple entities.

In exchange for favorable lease terms and a waiver of property taxes, the selected firm would 
provide SRS with the number of Environmental Attribute Certificates (EACs) commonly referred to as 
Renewable Energy Credits (RECs) required to fully offset the typical annual power consumption of 
approximately 360,000 MWh.  Disposition of any additional Renewable energy credits created by CFE 
generation at SRS beyond the number required to offset SRS consumption would be solely at the 
discretion of the CFE installation owner.

A long-term lease agreement is anticipated.  The Department of Energy is anticipating a turnkey 
agreement with the selected firm managing and financing all tasks related siting, designing, 
environmental permitting, including NEPA, construction, interconnection, licensing, operation, and 
maintenance of the CFE facility or facilities on land leased from DOE.  At the end of its useful 
life, the selected firm shall be responsible for removal and proper dispositioning of all equipment 
and restoration of the site.  The selected firm will be required to set aside funding during the 
period of the lease, such that there are sufficient funds available to restore the land at the end 
of the lease period.

It is anticipated that the selected firm will own and operate the finished CFE facility upon 
completion of construction. The selected firm will produce EACs by operating the CFE facility and 
will provide the required number of EACs to SRS each year of the lease agreement between SRS and 
the firm.

It is the responsibility of the selected firm to negotiate and establish agreements with the off- 
taking utility.  Interconnection to the off-taking utility’s power grid and any associated costs 
are the responsibility of the selected firm.  The CFE facility will not supply power directly to 
the SRS onsite grid.  If the CFE facility power generation is not isolated from the SRS onsite 
power grid, then the selected firm may be responsible for the additional maintenance and operations 
to ensure the CFE facility does not interfere with the SRS mission.

All the currently identified tracts of land can be accessed directly from an existing State or 
Federal highway without passing through an SRS barricade.  The selected firm will construct a fence 
around the entire CFE facility and maintain controlled access to the facility.

The facility will be located within the state of South Carolina and must meet all applicable state 
and federal regulations.  It is anticipated that the selected firm will have experience in 
compliance with state and federal regulatory reviews and permitting projects on federal land, the 
National Environmental Policy Act, National Historic Preservation Act, and Endangered Species Act.

The electricity market in South Carolina is a “regulated monopoly” managed by the South Carolina 
Public Service Commission (https://www.psc.sc.gov).  The region where SRS is located is assigned to 
Dominion Energy South Carolina (https://www.dominionenergy.com/south-carolina), formerly South 
Carolina Electric and Gas Company. The Southeast Energy Exchange Market (https://southeastenergymarket.com) provides 
opportunities for 15-minute energy trading in this area.

Capability Statement:

The following request is designed to provide information to the Department of Energy of any 
prospective developer of CFE power generation facilities with capabilities to execute the 
requirements as described above.


Please provide in your response to the following:
1.   Offeror's Name, Address, Point of Contact, Phone Number, and E-Mail Address.
2.   Offeror's interest in bidding on the solicitation when it is issued.
3.   Offeror's business size certified status, number of years in business, and your DUNS number.
4.   Offeror's capability statement demonstrating the Offeror's ability to perform comparable work. 

The statement should include a brief description of the three (3) most recently completed and 
comparable projects.  For each project include the customer’s name, offeror’s scope within the 
project, project duration, size of the CFE facility, location of the facility and whether the 
offeror retained ownership of the operating CFE facility.
5.   Offeror’s experience in compliance with state and federal regulatory reviews and permitting 
projects on federal land, the National Environmental Policy Act, National Historic Preservation 
Act, and Endangered Species Act, to address such elements as ecological, environmental, and 
cultural considerations associated with ground-disturbing and visual-affecting activities. 
Information in this item can be consolidated with item #4 above if applicable.
6.   What is the preferred contract/lease length for this type of contractual arrangement?
7.   Do you have any other suggestions or comments to improve future solicitations?

Disclaimer:
This RFI is issued solely for information and planning purposes and does not constitute a 
solicitation. Responses to this notice are not offers and cannot be accepted by the Government to 
form a binding contract.  SRS is not seeking proposals through this RFI and will not accept 
unsolicited proposals. Respondents are solely responsible for all expenses associated with 
responding to this RFI.  Not responding to this RFI does not preclude participation in any future 
procurement, if conducted.  No proprietary information should be included in any submittal.


How to Respond:
ALL interested Offerors should notify in writing via e-mail by 12:00pm EST on Friday, November 17, 
2023. Submit your response and information by e-mail to: Jeff.Hynds@srs.gov with the subject line 
“SRS CFE RFI Response”. Responses are limited to 10 pages (11-point font, 1-inch margins). Please 
include contact name(s), address, phone, and e-mail. Any questions regarding the RFI should be 
included in the RFI response. These questions will be addressed after the
RFI response due date with a FAQ document to everyone submitting a response.
 

Files

Notice history

Similar open opportunities

Opportunity Agency Set-aside Responses due
Advanced manufacturing, critical materials, and computing development request for offer Richland, Washington 99352, United States · NAICS 53 Office of Environmental Management No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors