Renovation of the Fish Collection Facility on the Toutle River

Closed Pre-Solicitation Posted

Not the latest version. See the latest special notice from .

Solicitation number
PAN26P29638
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Toutle, Washington 98649, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The U.S. Army Corps of Engineers Portland District intends to solicit renovation of the Fish Collection Facility on the Toutle River with a sources-sought response deadline of May 5, 2026 and an estimated construction cost between $100,000 and $1,000,000. This is market research to evaluate contractor availability for brand-name-or-equal component specifications; it is not a Request for Proposal. The procurement carries no set-aside but actively encourages responses from small business, 8(a), HUBZone, WOSB, EDWOSB, SDVOSB, and VOSB firms.

The project scope includes facility renovation to comply with current Biological Opinion requirements as mitigation for a separate Sediment Control Structure project. A new System Acquisition and Control System (SCADA) will be installed, comprising government-developed software and contractor-supplied hardware. The hardware must be capable of executing USACE-developed software to monitor and maintain water levels on a newly constructed fish ladder for fish attraction and collection.

NAICS 237990 applies (Other Heavy and Civil Engineering Construction); PSC is Z2KZ. The Corps anticipates justifying use of brand-name-or-equal descriptions under FAR 6.301(2) unless sources-sought responses demonstrate alternative responsible sources. Formal responses are due before 8:00 a.m. PDT on May 5, 2026. No reimbursement is provided for response costs.

Notice text

2 versions

Update #2 · Latest ·

Notice. Posting has been Amended to reflect the organization's needs. Please review the Sources Sought Notification in its entirety.

General. This is a SOURCES SOUGHT and is for informational/market research purposes only. THIS IS NOT A REQUEST FOR PROPOSAL, QUOTATION OR BID, NOR A SYNOPSIS OF A PROPOSED CONTRACT ACTION UNDER FAR SUBPART 5.2.

PROJECT: Renovation of the Fish Collection Facility on the Toutle River

No reimbursement will be made for any costs associated with providing information in response to this notice or any follow-up information requests.

This is a SOURCES SOUGHT NOTICE for market research ONLY to determine the availability of Brand Name or Equal Items.

In accordance with Section 888(a) of the National Defense Authorization Act for Fiscal Year 2017 (Pub. L. 114-328) as implemented by the Revolutionary FAR Overhaul (RFO) Defense Acquisition Regulation Supplement (DFARS) 206.103-170(c), the justification and approval (J&A) addressed in RFO Federal Acquisition Regulation (FAR) 6.301(2) is required in order to use brand name or equal descriptions in solicitation associated with PAN26P29638 for the renovation of the Fish Collection Facility on the Toutle River.

The United States Army Corps of Engineers, Portland District intends to include the following brand name or equal descriptions in a Request for Proposal under the authority of RFO FAR 6.103-1, “only one responsible source and no other supplies or services will satisfy agency requirements.” This project will include a brand name or equal description, as described below, unless the results of this sources sought notification indicate otherwise.

This notification serves three purposes: (1) to notify potential Offerors of the Government's intent to solicit a brand name or equal component under a the anticipated project; (2) to identify potential sources that can provide the brand name or equal items; (3) notification of USACE’s intent to require the brand name only descriptions if the market is unable to provide equal products.

In the event no equal products exist, the brand name justification and approval will be issued pursuant to RFO FAR 6.103-1 and RFO DFARS 206.103-170(c) and provided at time of solicitation of this project. A subsequent market survey will not be published in support of a brand name justification and approval in the event an equal product is not submitted for consideration. In such instances, the brand name description will be embedded in the project. Only that part of the project requiring a brand name may be sole sourced if no sources are able to provide a Government approved equal product.

Project Details and Background.

This project is to renovate the existing Fish Collection Facility on the Toutle River to meet the current BiOP requirements.  The renovation of the Toutle Fish Collection Facility is a mitigation requirement resulting from the raising of the crest on the Sediment Retention Structure (SRS)

Project Scope.

As part of the renovation, there will be a new System Acquisition and Control System (SCADA) installed consisting of hardware and software. The primary purpose of this control system is to monitor and maintain the proper water levels on the newly constructed fish ladder to attract fish into the facility. Since the software used with the new SCADA system will be developed by USACE electrical engineers, the contractor supplied hardware must be capable of executing this Government generated software. The software currently used by USACE is Allen Bradley Studio 5000.

SUMMARY OF REQUIREMENT: This construction project will require the following Programmable Logic Controller (PLC) equipment that must be compatible with Allen Bradley Studio 5000:

  • Hardware to accept 4-20mA sensor inputs, hence requiring an analog input module.
  • Hardware to accept 0 to 24VDC digital inputs, hence requiring a digital input module.
  • Hardware to control 0 to 24VDC digital outputs, hence requiring a digital output module
  • Hardware to have a module with multiple relay outputs
  • Main controller to operate over Ethernet/IP protocol using CAT6 hardware
  • Hardware to control devices using Ethernet/IP protocol
  • Hardware to include a 15” Human Machine Interface (HMI)
  • Hardware to include variable frequency drives (VFD or ASD) operating motors from 3 hp to 50 hp

Interested parties’ responses to this Sources Sought shall be limited to six (6) pages and shall include the following information:

  • An explanation to include name, make, and model of the equipment that you can provide
  • Provide a list of projects where your equipment has been successfully used
  • Show that your Programmable Logic Controller (PLC) equipment can run Allen Bradley Studio 5000 software:

Interested vendors if submitting equals must show clear and convincing evidence that alternatives to the specified items exist. Interested vendors wishing to be considered by the Government as described above must provide a copy of its brochure and any other capability statements/ data no later than 25 May 2026, 11:00 AM PDT, to Contracting Officer, Justin F. Figueredo at justin.f.figueredo@usace.army.mil and Contract Specialist, David M. Cook, at david.m.cook@usace.army.mil.

This is a market survey and notification of intent only. This is not a request to respond to a solicitation. A determination by the Government to compete this proposed contract based upon responses to this notice is solely within the direction of the Government.

All interested firms must be registered in the System for Award Management (SAM) at https://www.sam.gov to have size status considered. You must remain current for the duration of the source selection process to be eligible for award of a Government contract

Update #1 ·

General. This is a SOURCES SOUGHT and is for informational/market research purposes only. THIS IS NOT A REQUEST FOR PROPOSAL, QUOTATION OR BID, NOR A SYNOPSIS OF A PROPOSED CONTRACT ACTION UNDER FAR SUBPART 5.2.

This Sources Sought is to gain knowledge of the interest, capabilities, and qualifications of industry so the government can make informed business decisions. We are seeking responses from both large and small business members of industry to include: Small Business, Small Disadvantaged Businesses to include 8(a) firms, Historically Underutilized Business Zones (HUBZone), Woman Owned Small Business (WOSB) to include Economically Disadvantaged Women-Owned Small Business (EDWOSB), Service-Disabled Veteran-Owned Small business (SDVOSB) and Veteran Owned Small Business (VOSB). All interested parties are highly encouraged to respond.

The North American Industrial Classification Code (NAICS) for this requirement is:  237990.

The approximate value of the Estimated Construction Cost (ECC) will be from $100,000.00 to $1,000,000.00.

Formal Sources Sought Response Due – before 8:00 am PDT on 5 May 2026.

Project Details and Background.

This project is to renovate the existing Fish Collection Facility on the Toutle River to meet the current BiOP requirements.  The renovation of the Toutle Fish Collection Facility is a mitigation requirement to the raising of the Crest on the Sediment Control Structure

Project Scope.

The project scope would be the renovation of the Facility.  As part of the renovation there will be a new System Acquisition and Control System (SCADA) consisting of hardware and software  The primary purpose of this control system is to monitor and maintain the proper water levels on the newly constructed fish ladder to attract fish into the facility. Since the software used with the new SCADA system will be developed by USACE, electrical engineering department, the contractor supplied hardware must be capable of executing this government generated software. The software used by the government is Allen Bradley Studio 5000.

Anticipated Construction Schedule: CENWP intends to advertise in February 2027 and award in May 2027. Construction Contract with estimated construction completion by the end of calendar year 2027.

Estimated Construction Cost (ECC): The current ECC is between $100,000.00 and $1,000,000.00.

Number and Type of Contracts: NWP contemplates awarding one (1), Firm Fixed-Price contract. The acquisition strategy decision has not yet been determined. Maximum Small business participation is being sought at both the Prime and subcontracting levels.

Anticipated Source Selection Process: The expected method to determine the best value to the government is Invitation for Bid.

Project Details: The following information represents the project objectives:

Hardware to accept 4-20mA sensor inputs, hence requiring an analog input module.

Hardware to accept 0 to 24VDC digital inputs, hence requiring an digital input module.

Hardware to control 0 to 24VDC digital outputs, hence requiring an digital output module

Hardware to have a module with multiple relay outputs

Main controller to operate over Ethernet/IP protocol using CAT6 hardware

Hardware to control devices using Ethernet/IP protocol

Hardware to include a 15” Human Machine Interface (HMI)

Hardware to include variable frequency drives (VFD or ASD) operating motors from 3 hp to 50 hp

Submission Instructions. Formal responses to this Sources Sought notice must be submitted electronically via email with supporting documentation requested here in Section 4 Submission Instructions. Submit your email with SUBJECT: Sources Sought – Toutle Fish collection Facility. Please email to Justin F. Figueredo, Contracting Officer, at justin.f.figueredo@usace.army.mil and David M. Cook Contracting Specialist, at david.m.cook@usace.army.mil, before 8:00 am PDT on 5 May 2026.

Interested parties’ responses to this Sources Sought shall be limited to six (6) pages and shall include the following information:

An explanation of the equipment that you can provide

Provide a list of projects where your equipment has been used

Show that your PLC equipment can run software: Allen Bradley Studio 5000

Disclaimer and Important Notes.

This notice does not obligate the Government to award a contract. No reimbursement will be made for any costs associated with providing information in response to this Sources Sought or any follow up information. The Government reserves the right to use information provided by respondents for any purpose deemed necessary and legally appropriate. Any organization responding to this notice should ensure that its response is complete and sufficiently detailed to allow the Government to determine the organization's capabilities to perform the work. Respondents are advised that the Government is under no obligation to acknowledge receipt of the information received or to provide feedback to respondents with respect to any information submitted.

All interested firms must be registered in the System for Award Management (SAM) at https://www.sam.gov to have size status considered. You must remain current for the duration of the source selection process to be eligible for award of a Government contract.

Notice history

Notice Type Posted
Virtual Industry Day Special Notice: Renovation of the Fish Collection Facility on the Toutle River Latest special notice Special Notice
This notice Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
USCG Station at Cape Disappointment ENDIST Portland No set-aside
Prosser Hatchery Sole Source Presolicitation Notice Prosser, Washington 99350, United States · NAICS 112511 ENDIST Portland No set-aside
Yaquina River Clamshell Dredging 2027 downstream of Toledo, OR. SW Altree Ln Toledo OR 97391 97391 · NAICS 237990 ENDIST Portland No set-aside
Albeni Falls Dam Breakroom Upgrade Albeni Falls Dam Powerhouse 2376 E. Highway 2, Oldtown, ID 83822 83822 · NAICS 237990 ENDIST Seattle No set-aside
FY27 Euclid Creek Fishway Construction Euclid Creek Spillway Cleveland, OH, 44114 44114 · NAICS 237990 ENDIST Buffalo Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors