This solicitation from the Department of the Army Corps of Engineers Engineering District Japan seeks to renovate Bechtel Elementary School at Camp McTureous in Okinawa, Japan. The scope of work includes demolishing portions of existing buildings, constructing a new two-story addition of approximately 7,525 square meters, and renovating around 6,550 square meters of existing school facilities. The project must meet Department of Defense and Department of Defense Education Activity standards for high performance and sustainable buildings and incorporate anti-terrorism/force protection features. Proposals are due by February 22, 2023.

There is no set-aside designation. The contract is intended solely for local sources physically located and licensed to conduct business in Japan. The projected value is between 2.5 to 10 billion Japanese Yen. All work will be performed in Okinawa, Japan. Key details include demolishing around 4,200 square meters of existing structures, constructing a new addition of approximately 81,000 square feet, and renovating approximately 70,493 square feet of existing school buildings to provide functional areas for a fully functioning elementary school.

Notice text

5 versions

Update #5 · Latest ·

The purpose of this Amendment is to provide Government Responses to Contractor Requests for Information (RFI) and to release amended specifications. The proposal due date and time of 11:00AM local time on 23 February 2023 remains unchanged. See SF30 Bechtel AM-0002, Bechtel ES_AM-0002_CLIN Schedule, Bechtel ES_AM-0002_Specifications.

Update #4 ·

The purpose of this Amendment is to provide Government Responses to Contractor Requests for Information (RFI) and to release amended specifications and drawings. The proposal due date and time of 11:00AM local time on 23 February 2023 remains unchanged.

Update #3 ·

***** For Information Only (FIO):  The Bechtel Elementary School site-visit attendance sheet is attached. *****

Update #2 ·

***** For Information Only (FIO):  The Bechtel Elementary School site-visit slides are attached. *****

Renovate Bechtel Elementary School, Camp McTureous, Okinawa, JapanThis project will construct, through renovation and new addition of a multi-story elementary school with functional areas containing neighborhood instructional spaces, special education spaces, staff collaboration spaces, commons area, multipurpose room, information center, physical education, art room, music room, administration suite, health suite, guidance counseling suite, special education suite, food service, janitorial workroom, maintenance support, school supply/storage area, technology service center, and other required areas for a fully functioning elementary school. Typical construction for new building addition is to consist of special deep foundation systems, reinforced concrete and structural steel framing and reinforced concrete bearing and shear walls. Interior construction will consist of reinforced concrete interior bearing and shear-walls, gypsum wallboard partitions, and operable / movable partition walls. The project is to renovate approximately 6550 square meters of the existing school facilities and construct a new addition of approximately 7525 square meters. The project will require demolition of approximately 4200 square meters of existing facilities. Department of Defense (DoD) and Department of Defense Education Activity (DoDEA) principles for high performance and sustainable building requirements will be included in the design and construction of the project in accordance with federal laws and Executive Orders. Low Impact Development will be included in the design and construction of this project as appropriate.This project will provide Anti-Terrorism/Force Protection (AT/FP) features, including design for progressive collapse and blast-rated windows and doors, and comply with AT/FP regulations, and physical security mitigation in accordance with DoD Minimum Anti-Terrorism Standards for Buildings. Project includes the construction within the school building of Designated Seismic Systems (DSS). DSS are those systems identified in the plans and specifications that must remain operable following a design earthquake. DSS have special requirements for certification(s) of the installed equipment of the DSS as well as Special Inspection requirements during construction. Project also includes other construction that requires Special Inspection of structural, architectural, electrical, and fire protection systems. Special Inspections are in addition to the standard Quality Control inspections required by the contract. Facilities will be designed to provide cyber security engineering and validation as specified in DoD Unified Facilities Criteria. Special foundation features are required due to poor near-surface subgrade soils capacity. The project includes related infrastructure such as water, sewer, electrical, telephone, local area network, community access television systems, and provisions for interior and campus wireless access. The project includes site improvements such as site preparation, signage, fencing, paving, sidewalks, landscaping, exterior lighting, retaining walls, pedestrian bridges, canopies, covered walkways, play lots, play areas, outdoor learning, storm water, low impact development, and external AT/FP. Reconfigured parking area to include: staff and visitor parking areas, parent drop off lane, emergency/service access lanes, and loading/delivery areas. The project will require hazardous material mitigation for all buildings to be demolished or renovated. U.S. Federal and Japan Environmental Laws and Regulations shall be followed. Asbestos containing materials and lead based paint are present in the existing facilities. The site is a known radon risk. Radon mitigation will be required.This contract will be performed in its entirety in the country of Japan, and any solicitation posted will be intended for local sources only. Local sources are those sources physically located and licensed to conduct business in Japan. See local source information within this notice. *Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W912HV22R0013' to obtain more details.*

Update #1 ·

Renovate Bechtel Elementary School, Camp McTureous, Okinawa, JapanThis project will construct, through renovation and new addition of a multi-story elementary school with functional areas containing neighborhood instructional spaces, special education spaces, staff collaboration spaces, commons area, multipurpose room, information center, physical education, art room, music room, administration suite, health suite, guidance counseling suite, special education suite, food service, janitorial workroom, maintenance support, school supply/storage area, technology service center, and other required areas for a fully functioning elementary school. Typical construction for new building addition is to consist of special deep foundation systems, reinforced concrete and structural steel framing and reinforced concrete bearing and shear walls. Interior construction will consist of reinforced concrete interior bearing and shear-walls, gypsum wallboard partitions, and operable / movable partition walls. The project is to renovate approximately 6550 square meters of the existing school facilities and construct a new addition of approximately 7525 square meters. The project will require demolition of approximately 4200 square meters of existing facilities. Department of Defense (DoD) and Department of Defense Education Activity (DoDEA) principles for high performance and sustainable building requirements will be included in the design and construction of the project in accordance with federal laws and Executive Orders. Low Impact Development will be included in the design and construction of this project as appropriate.This project will provide Anti-Terrorism/Force Protection (AT/FP) features, including design for progressive collapse and blast-rated windows and doors, and comply with AT/FP regulations, and physical security mitigation in accordance with DoD Minimum Anti-Terrorism Standards for Buildings. Project includes the construction within the school building of Designated Seismic Systems (DSS). DSS are those systems identified in the plans and specifications that must remain operable following a design earthquake. DSS have special requirements for certification(s) of the installed equipment of the DSS as well as Special Inspection requirements during construction. Project also includes other construction that requires Special Inspection of structural, architectural, electrical, and fire protection systems. Special Inspections are in addition to the standard Quality Control inspections required by the contract. Facilities will be designed to provide cyber security engineering and validation as specified in DoD Unified Facilities Criteria. Special foundation features are required due to poor near-surface subgrade soils capacity. The project includes related infrastructure such as water, sewer, electrical, telephone, local area network, community access television systems, and provisions for interior and campus wireless access. The project includes site improvements such as site preparation, signage, fencing, paving, sidewalks, landscaping, exterior lighting, retaining walls, pedestrian bridges, canopies, covered walkways, play lots, play areas, outdoor learning, storm water, low impact development, and external AT/FP. Reconfigured parking area to include: staff and visitor parking areas, parent drop off lane, emergency/service access lanes, and loading/delivery areas. The project will require hazardous material mitigation for all buildings to be demolished or renovated. U.S. Federal and Japan Environmental Laws and Regulations shall be followed. Asbestos containing materials and lead based paint are present in the existing facilities. The site is a known radon risk. Radon mitigation will be required.This contract will be performed in its entirety in the country of Japan, and any solicitation posted will be intended for local sources only. Local sources are those sources physically located and licensed to conduct business in Japan. See local source information within this notice. *Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W912HV22R0013' to obtain more details.*

Files

Notice history

Notice Type Posted
RENOVATE BECHTEL ELEMENTARY SCHOOL, Camp McTureous, Okinawa, Japan Award Award Notice
This notice Latest solicitation Solicitation
Renovate Bechtel Elementary School, Camp McTureous, Okinawa, Japan Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
FY26 MCN P309, School Age Care Centers Replacement, Camp Foster and McTureous, Okinawa, Japan NAICS 236220 ENDIST Japan No set-aside
Renovate military family housing tower 4511, camp courtney Camp Courtney, Okinawa, Japan · NAICS 236118 ENDIST Japan No set-aside
Vehicle Maintenance Shop, Kadena Air Base, Okinawa, Japan Kadena Air Base, Okinawa, Japan · NAICS 236220 ENDIST Japan No set-aside
AFHC Repair Quarters 82 and 86, Camp Zama, Japan Camp Zama, Japan · NAICS 236118 ENDIST Japan No set-aside
FY2026 - FY2027 Projections Japan ENDIST Japan No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors