RECOVERY--Y--Recovery--Lock and Dam 3 Lower Embankment Improvements-Request for Qualifications

Award Notice Posted

Solicitation number
W912ES-09-R-0026
Agency
Awarded
to Edward Kraemer & Sons, Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
W912ES10C0011 Federal contract award
PSC
Not on record
Place of performance
US Army Engineer District, St. Paul Contracting Division Cemvp-CT, 190 East Fifth Street St. Paul MN 55101 US

Notice details come from SAM.gov. Updated .

Notice text

9 versions

Update #9 · Latest ·

PHASE II OF THIS DESIGN-BUILD ACQUISITION IS NOW UNDERWAY.  The RFP has been issued to the Offerors selected in Phase I.  The posted RFP is for informational purposes only and does not contain attachments. 

Update #8 ·

Four Questions were received and answered in the PDF file attached today.

Update #7 ·

Amendment 0003 is now on www.fbo.gov.  Amendment 0003 changes Sections 00 12 00 of the Request for Qualifications.

Update #6 ·

Amendment 0002 is now on www.fbo.gov.  This amendment incorporates the General Reevaluation Report (GRR) Apendices A through M.

Update #5 ·

For your convenience, a Word version of the Data Sheet and Questionnaires has been posted.

Update #4 ·

RECOVERY--This project is for the design and construction (Two-Step Design-Build) of embankment improvements at Lock and Dam 3 on the Mississippi River near Diamond Bluff in Pierce County, Wisconsin. Contractors shall be capable of providing all technical expertise, equipment, materials and labor to design and construct embankment improvements at Lock and Dam 3. These improvements may include: 1) construction of a series of embankments and spillways totaling up to several thousand linear feet, and 2) construction of associated control structures and any associated improvements.
The Design-Build process will have two distinct phases. Phase-I will be the pre-qualification process, where the Government may select a designated number of Design-Build Contractors on the basis of qualifications to perform the work.
Only the selected Design-Build Contractors will then qualify for the Phase-II of the process. In the Phase-II of the procurement procedure, offerors will be given the opportunity to submit their preliminary design and price proposals. Price, along with other non-pricing factors, will determine the best value to the Government. No stipend will be paid to any unsuccessful Phase I or Phase II offerors that submit proposals.
This will be a firm-fixed price contract and award will be based on best value to the Government. THIS PROCUREMENT IS ISSUED UNRESTRICTED UNDER THE SMALL BUSINESS COMPETITIVENESS DEMONSTRATION PROGRAM (PUBLIC LAW 100-656). The estimated price range for this requirement is between $10,000,000 and $25,000,000. The North American Industry Classification System (NAICS) code is 237990 with a small business size standard of $33.5 million. This Request for Proposal (RFP) is being issued on an unrestricted basis.
The solicitation for the Request for Qualifications will be posted with specifications on www.fbo.gov on or around July 17, 2009 for a period of not less than 30 days. The solicitation for the Request for Proposals will be posted with the specification and plans on or around September 8, 2009 for a period of not less than 45 days. Please check this website for any changes.


RECOVERY--The Request for Qualifications is now on www.fbo.gov for Lock and Dam 3 Lower Embankment Inprovments. Along with it are attachments.


RECOVERY--In the description of '09-R-0026 Lock 3 Final RFQ Lower Embank.pdf (567.96KB)', the description should read 'Request for Qualifications' not Request for Quotation.


 Amendment 0001 is now on www.fbo.gov. 


 

Update #3 ·

RECOVERY--In the description of '09-R-0026 Lock 3 Final RFQ Lower Embank.pdf (567.96KB)', the description should read 'Request for Qualifications' not Request for Quotation.

Update #2 ·

RECOVERY--The Request for Qualifications is now on www.fbo.gov for Lock and Dam 3 Lower Embankment Inprovments. Along with it are attachments.

Update #1 ·

RECOVERY--This project is for the design and construction (Two-Step Design-Build) of embankment improvements at Lock and Dam 3 on the Mississippi River near Diamond Bluff in Pierce County, Wisconsin. Contractors shall be capable of providing all technical expertise, equipment, materials and labor to design and construct embankment improvements at Lock and Dam 3. These improvements may include: 1) construction of a series of embankments and spillways totaling up to several thousand linear feet, and 2) construction of associated control structures and any associated improvements.
The Design-Build process will have two distinct phases. Phase-I will be the pre-qualification process, where the Government may select a designated number of Design-Build Contractors on the basis of qualifications to perform the work.
Only the selected Design-Build Contractors will then qualify for the Phase-II of the process. In the Phase-II of the procurement procedure, offerors will be given the opportunity to submit their preliminary design and price proposals. Price, along with other non-pricing factors, will determine the best value to the Government. No stipend will be paid to any unsuccessful Phase I or Phase II offerors that submit proposals.
This will be a firm-fixed price contract and award will be based on best value to the Government. THIS PROCUREMENT IS ISSUED UNRESTRICTED UNDER THE SMALL BUSINESS COMPETITIVENESS DEMONSTRATION PROGRAM (PUBLIC LAW 100-656). The estimated price range for this requirement is between $10,000,000 and $25,000,000. The North American Industry Classification System (NAICS) code is 237990 with a small business size standard of $33.5 million. This Request for Proposal (RFP) is being issued on an unrestricted basis.
The solicitation for the Request for Qualifications will be posted with specifications on www.fbo.gov on or around July 17, 2009 for a period of not less than 30 days. The solicitation for the Request for Proposals will be posted with the specification and plans on or around September 8, 2009 for a period of not less than 45 days. Please check this website for any changes.

Files

File Type Posted
0026 RFP Amendment 0004.pdf PDF
M-L3-40_3 —
M-P3-52_001.pdf PDF
M-P3-52_002.pdf PDF
Attachment 7 LE Cover.pdf PDF
M-L3-52_12.pdf PDF
M-P3-61_1.1 —
M-P3-52_003.pdf PDF
M-P3-61_2 —
M-L3-40_1 —
M-P3-61_3.1 —
Anticipated Conditions - LD3 WDNR Permit and Water Quality Certification.doc DOC document
0026 RFP Amendment 0003.pdf PDF
0026 RFP Amendment 0002.pdf PDF
LD3 Lower Emb 0026 RFP Amend 0001.pdf PDF
Attachment 2.4_LE GRR appendices.pdf PDF
Attachment 1 LE conceptual drawings.pdf PDF
LD3 Lower Embankment RFP FINAL 9.11.09.pdf PDF
Question for W912ES-09-R-0026.pdf PDF
Amendment 0003.pdf PDF
Amendment 0002.pdf PDF
Data Sheet and Evaluation Questionnaires 9-R-26.docx DOCX document
Amendment 0001.pdf PDF
Attachment 1 Conceptual Drawings Lower Embankments.pdf PDF
Attachment 2.1_Part 2_ LE GRR Real Estate drawings.pdf PDF
Attachment 3 draft RFP Lower Embankments.pdf PDF
Attachment 2.1_Part 1_06Nov16Final GRR EIS.pdf PDF
Attachment 2.2 LE Hist Nav Season Info.pdf PDF
Attachment 2.1_Part 3_ LE GRR drawings.pdf PDF
Attachment 2.3 LE Hydrographs cover.pdf PDF
Attachment 4 LE draft Wage Rates.pdf PDF
09-R-0026 Lock 3 Final RFQ Lower Embank.pdf PDF
Show all 32

Notice history

Notice Type Posted
RECOVERY--PROJECT NUMBER 153882, Lock & Dam 3, Lower Embankment Improvements Latest Award Notice
This notice Original Award Notice

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors