Recovery - chincoteague BAY channel, accomack county, virginia and maintenance dredging, chincoteague harbor of refuge, chincoteague, virginia
Award Notice Posted
- Solicitation number
- W91236-09-B-0015
- Agency
-
ENDIST Norfolk
US Army Corps of Engineers, Department of Defense
- Awarded
- to J.n.d. Thomas Company, Inc.
- Set-aside
- Total Small Business
Opportunity facts
- Contract number
- W9123609C0068 Federal contract award
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Not on record
- Place of performance
- Accomack County, Virginia And Chincoteague, Virginia, Virginia, United States
Notice details come from SAM.gov. Updated .
Notice text
PRESOLICITATION NOTICE TIMEFRAME SHORTENED
SOLICITATION AVAILABLE 26 JUNE 2009
BID OPENINGING DATE: 27 JULY 2009
Project Description - The entire work for this contract consists of dredging two locations as part of the American Recovery and Reinvestment Act (ARRA). All ARRA funds must be expended by 30 September 2010. The first location of work, Part 1, consists of maintenance dredging the Chincoteague Bay Channel to a required depth of 6 feet MLLW (NOS) with one foot of allowable overdepth. The work shall be performed by a hydraulic dredge and pipeline with all dredged material transported and placed in the designated Government-furnished upland placement area only. The work involves dredging approximately 17,000 cubic yards of material, including allowable overdepth dredging and estimated accretion to September 2009. The second location of work, Part 2, consists of maintenance dredging the Chincoteague Harbor of Refuge to a required depth of 9 feet MLLW (NOS) with one foot of allowable overdepth dredging. The work shall be performed by a hydraulic dredge and pipeline with all dredged material transported and placed in the designated Government-furnished upland placement area only. The work involves dredging approximately 7,000 cubic yards of material including allowable overdepth dredging and estimated accretion to September 2009.
CLIN 0001 - Part 1, Maintenance Dredging Chincoteague Bay Channel - Begin performance within 15 calendar days and complete all work within 60 calendar days of receipt of Notice To Proceed (NTP).
CLIN 0002 - Part 2, Maintenance Dredging Chincoteague Harbor of Refuge - Begin performance within 15 calendar days and complete all work within 45 calendar days of receipt of Notice To Proceed (NTP)
LIQUIDATED DAMAGES: $400.00
MAGNITUDE OF CONSTRUCTION: $250,000.00 - $400,000.00
Files
| File | Type | Posted |
|---|---|---|
| ABSTRACT.pdf | ||
| W09B0015_0001.pdf | ||
| W91236-09-B-0015.pdf | ||
| W09B0015 PLANS TO CONTRACTS.zip | ZIP file |