W26GLG91677925

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

RECOVERY - DREDGING CHINCOTEAGUE BAY CHANNEL AND CHINCOTEAGUE HARBOR OF REFUGE

1. CONTRACT ID CODE PAGE OF PAGES

J 1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-Jul-2009

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W91236-09-B-0015

X 9B. DATED (SEE ITEM 11)

26-Jun-2009

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Jul-2009

CODE

USA ENGINEER DISTRICT, NORFOLK

CONTRACTING OFFICE

803 FRONT STREET

NORFOLK VA 23510-1096

W91236 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W91236-09-B-0015

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

AMENDMENT 0001

Revised Bid Schedule, Attached.

PART 1 – CHINCOTEAGUE BAY

2. SECTION 00 01 15: Delete the listed drawings in their entirety and substitute therefore the following:

“H-51-26-320(1) TITLE SHEET

H-51-26-320(2) PLANS FOR DREDGING

H-51-26-320(3) PLANS FOR DREDGING

H-51-26-320(4) PLANS FOR DREDGING”.

3. SECTION 01 14 00:

a. Page 5, paragraph 1.4.5, delete the second sentence in its’ entirety and substitute therefore “1.4.5 Not Used.”.

b. Page 8, delete paragraph 1.5.7 in its’ entirety and substitute therefore the following new paragraph:

“Leased and public oyster grounds and tidal wetlands are present in the project dredging area and are depicted on the contract drawings. As part of the Contractor's responsibility to layout the work, the boundaries of the oyster beds in the vicinity of the work areas shall be marked in the field by the licensed Professional Engineer or Surveyor. The boundary points shall be physically located with stakes or pipe and marked with orange flagging prior to dredging operations. These markings shall be maintained during the duration of dredging and placement operations in the vicinity of these areas and removed upon completion of the scheduled work. The locations shown for the oyster grounds are based on information furnished by the Virginia Marine Resources Commission. In order to avoid damage to oyster grounds, the Contractor shall not allow personnel or the operation of plant and attendant vessels across the bounds of the public and private leased oyster and shellfish grounds, except as approved by the Contracting Officer. To the maximum extent practical, the Contractor's work operations over and in the vicinity of the oyster grounds shall be at high tide.”

c. Page 8, paragraph 1.8.1, line 4, delete “and barges/scows” in its’ entirety.

d. Page 9, paragraph 1.11.1, in the second sentence delete “dredged material is placed in the Basin or”.

e. Page 9, paragraph 1.11.2, in the first sentence delete “dredged material is placed in the Basin or”.

4. SECTION 01 45 00: Page 5, in the last sentence of the paragraph change “(757) 441-7723” to “(757)201-7723”.

5. SECTION 01 57 20: Page 6 and 7, delete sub-paragraph 1.7.1j and substitute therefore the following new subparagraph:

“j. An erosion and sediment control plan which identifies the type and location of the erosion and sediment controls to be provided. The plan must include monitoring and reporting requirements to assure that the control measures are in compliance with the erosion and sediment control plan, Federal, State, and local laws and regulations.”

6. SECTION 01 57 30:

a. Page 3, paragraph 3.1.1, delete the last sentence of the paragraph in its’ entirety.

b. Page 3, paragraph 3.1.2, line 5, after “…Report.” delete the remainder of the paragraph in its’ entirety.

7. SECTION 35 20 23:

a. Page 4 and 5, delete paragraph 3.1.2 in its’ entirety and substitute therefore the following new paragraphs:

“3.1.2 Government Furnished Upland Placement Area

“Except as shown otherwise on the drawing, the interior and exterior of the placement area, dikes, spill boxes and associated piping are expected to be adequate for the placement of dredged material. The Contractor is responsible to insure all portions of the placement area, dikes, drainage piping and spill boxes are adequate and in proper working order before commencement of placement operations. The alignment of the dike, along with a typical section view showing existing and required finished horizontal details of the dike construction, are indicated on the drawings. The Contractor shall excavate materials to the maximum extent practical from the interior of the placement area for the finished dike construction.

The required dike shall be constructed to a minimum height as indicated and the entire placement area blade-graded smooth to allow positive drainage to the spill box. Dike height elevations above the indicated elevation are acceptable. Placement area construction shall be conducted in such a manner as to avoid damage to trees and other natural features outside the diked area, with due regard to the safety of employees and others, and in compliance with EM 385-1-1. Backfilling adjacent to spillbox and drainage piping shall be performed such that materials are placed and compacted uniformly in a manner as to prevent wedging action or eccentric loading upon or against the structure. Slopes bounding or within areas to be backfilled shall be stepped or serrated to prevent sliding of the fill. Diversion ditches, dikes, and grading shall be provided and maintained as necessary during construction. Excavated slopes and backfill surfaces shall be protected to prevent erosion and sloughing. Excavation shall be performed so that the site and the area immediately surrounding the site and affecting operations at the site shall be continually and effectively drained. During backfilling operations and in the formation of dikes, equipment that will overload the structure in passing over and compacting these fills shall not be used.

The Contractor shall replace all weir boards (minimum of four for this contract), make corrections to the existing dikes, clear debris from spill box and piping, provide weir boards, and all other work to prepare the placement area for dredged material placement is the Contractor's responsibility and shall be provided as part of the Contractor's mobilization expenses. Any required repairs to the spill box or drainage piping not otherwise specified will be considered a differing site condition and paid for in accordance with the “CHANGES” CLAUSE. All materials repaired or replaced shall be in sizes and type to match existing as approved by the Contracting Officer. All trash and debris shall be removed and disposed in approved landfills at the Contractor's expense. Prior to commencing dredging operations, the weir boards shall be set at a height to assure a minimum ponding depth within the placement area of two feet measured at the spill box. Additionally, for the duration of the contract the Contractor shall be responsible to maintain the placement area dikes and operate the spillbox by keeping spillway weirs at the correct level and free of trash and debris at all times to maintain:

(1) the minimum required ponding level;

(2) specified freeboard; and

(3) specified effluent and other water-quality standards.”

PART 2 – CHINCOTEAGUE HARBOR OF REFUGE

8. SECTION 01 14 00

a. Page 5, paragraph 1.4.5, delete the second sentence in its’ entirety and substitute therefore “1.4.5 Not Used.”.

b. Page 8, paragraph 1.8.1, line 4, delete “and barges/scows” in its’ entirety.

c. Page 9, paragraph 1.11.1, in the second sentence delete “dredged material is placed in the Basin or”.

d. Page 9, paragraph 1.11.2, in the first sentence delete “dredged material is placed in the Basin or”.

9. SECTION 01 45 00: Page 5, paragraph 3.4.3, in the last sentence of the paragraph change “(757) 441- 7723” to “(757)201-7723”.

10. SECTION 01 57 20: Page 6 and 7, delete sub-paragraph 1.7.1 j and substitute therefore the following new subparagraph:

“j. An erosion and sediment control plan which identifies the type and location of the erosion and sediment controls to be provided. The plan must include monitoring and reporting requirements to assure that the control measures are in compliance with the erosion and sediment control plan, Federal, State, and local laws and regulations.”

11. SECTION 01 57 30:

a. Page 3, paragraph 3.1.1, delete the last sentence of the paragraph in its’ entirety.

b. Page 3, paragraph 3.1.2, line 5, after “…Report.” delete the remainder of the paragraph in its’ entirety.

12. SECTION 35 20 23:

a. Page 4 and 5, delete paragraph 3.1.2 in its’ entirety and substitute therefore the following new paragraphs:

“3.1.2 Government Furnished Upland Placement Area

“The interior and exterior of the placement area and dikes are expected to be adequate for the placement of dredged material, except as specified otherwise below. The existing spill box and drainage piping are to be removed and replaced to match existing conditions. The Contractor is responsible to insure all portions of the placement area, dikes, drainage piping and spill boxes are adequate and in proper working order before commencement of placement operations. The alignment of the dike, along with a typical section view showing existing and required finished horizontal details of the dike construction, are indicated on the drawings. The Contractor shall excavate materials to the maximum extent practical from the South cell of the placement area for the finished dike construction. The required dike shall be constructed to a minimum height elevation as indicated and the entire placement area blade-graded smooth to allow positive drainage to the spill box. Dike height elevations above the indicated elevation are acceptable. Placement area construction shall be conducted in such a manner as to avoid damage to trees and other natural features outside the diked area, with due regard to the safety of employees and others, and in compliance with EM 385-1-1. Backfilling adjacent to spillbox and drainage piping shall be performed such that materials are placed and compacted uniformly in a manner as to prevent wedging action or eccentric loading upon or against the structure. Slopes bounding or within areas to be backfilled shall be stepped or serrated to prevent sliding of the fill. Diversion ditches, dikes, and grading shall be provided and maintained as necessary during construction. Excavated slopes and backfill surfaces shall be protected to prevent erosion and sloughing. Excavation shall be performed so that the site and the area immediately surrounding the site and affecting operations at the site shall be continually and effectively drained. During backfilling operations and in the formation of dikes, equipment that will overload the structure in passing over and compacting these fills shall not be used.

“3.1.2.1 SPILLBOX AND ACCESSWAY CONSTRUCTION

“A new spillbox and drainage piping shall be constructed at the same location and to the same shape and material dimensions of the existing. Drainage pipe shall be provided on a level surface in accordance with ASTM A 760, zinc coated of Type I or II pipe with annular or helical corrugations, asphalt coated, 18-inch. The spillbox shall be anchored to a concrete slab sized and dimensioned to match existing. The slab shall be formed and poured on top of a compacted earth foundation with six inches of gravel between the compacted earth and the slab. The concrete slab shall be anchored into the ground with four screw type anchors placed near each corner of the slab, approximately 1 foot from the edge of each adjacent side, and embedded a minimum of 4 inches into the slab after the slab is poured. A minimum of four L-brackets shall be welded to the spillbox and bolted to the slab anchor bolts when the spillbox is set in place. The slab foundation and new spillbox shall be placed so that the drainage pipe invert elevations matches that of the existing spillbox construction, and the top of the spillbox is at +14.0 feet MLLW (NOS). New weir boards shall be installed up to the +12.0 feet MLLW (NOS) elevation. Weir boards shall be treated in accordance with American Wood Preservers Institute Standard (AWPA) C2 with waterborne preservatives listed in AWPA P5 to a retention level recommended for water contact use. The spillbox shall also be further secured to the ground by six cables, each with cable couplings for adjusting cable tension, and six screw type anchors. These cables shall extend from pad eye brackets welded to the top of the spillbox to the anchors installed in the ground at an approximate angle of 45 degrees. The effluent pipeline coming from the spillbox shall be completely covered by a minimum of 2 feet of materials from the spillbox to the placement of materials for the new dike construction. A walkway shall be constructed from the +14.0 feet elevation on the finished dike to the spill box at the location as indicated. The walkway shall be constructed with pressure treated wood or other materials approved by the Contracting Officer in writing. Walkway shall be treated in accordance with American Wood Preservers Institute Standard (AWPA) C2 with waterborne preservatives listed in AWPA P5 to a retention level recommended for water contact use. The walkway shall be framed and braced to provide safe access to the spill box. The walkway shall have a minimum deck width of 4 feet and have well made continuous hand rails on both sides of the walkway deck. At the terminus of the walkway and the spill box a stepladder shall be constructed on both sides from the deck to the ground. The contractor shall be responsible for the design and construction of the walkway, specifically including the framing, bracing, and sufficient footings. All work shall meet the requirements of the Life Safety Code, EM 385-1-1 and OSHA regulations governing location and use. The Contractor shall replace the spill box, including access walkway, new drainage piping and weir boards, make corrections to the existing dikes, clear debris from the disposal area, and all other work required to prepare the placement area for dredged material placement is the Contractor's responsibility and shall be provided as part of the Contractor's mobilization expenses. All materials repaired or replaced shall be in sizes and type to match existing as approved by the Contracting Officer. All trash and debris shall be removed and disposed in approved landfills at the Contractor's expense. Prior to commencing dredging operations, the weir boards shall be set at a height to assure a minimum ponding depth within the placement area of two feet measured at the spill box.

Additionally, for the duration of the contract the Contractor shall be responsible to maintain the placement area dikes and operate the spillbox by keeping spillway weirs at the correct level and free of trash and debris at all times to maintain:

(1) the minimum required ponding level;

(2) specified freeboard; and

(3) specified effluent and other water-quality standards.”

Contracting Point of Contact:

Tracey J. Hughes 803 Front Street Norfolk, VA 23510

FAX: 757-201-7183

Section 00010 - Solicitation Contract Form

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 RECOVERY - CHINCOTEAGUE BAY CHANNEL

Part 1, Begin performance within 15 calendar days and complete all work within 60 calendar days of receipt of Notice To Proceed (NTP). Part 1, consists of maintenance dredging the Chincoteague Bay Channel to a required depth of 6 feet MLLW (NOS) with one foot of allowable over depth. The work shall be performed by a hydraulic dredge and pipeline with all dredged material transported and placed in the designated Government-furnished upland placement area only.

The work involves dredging approximately 17,000 cubic yards of material, including allowable over depth dredging and estimated accretion to September 2009. ---

W26GLG91677926 - PROJECT NO.: 137662

0001 01 Mobilization and Demobilization 1 JOB LS ______________

0001 02 Dredging Chincoteague Bay Channel 17,000 CY ___________ ______________ To a depth of 6 feet with 1 foot of allowable over depth, complete, including all associated work as indicated and specified.

PART 1

TOTAL ESTIMATED AMOUNT OF BID ITEMS (0001 01 through 0001 02) ______________

0002 RECOVERY - CHINCOTEAGUE HARBOR OF REFUGE

Part 2, Begin performance within 15 calendar days and complete all work within 45 calendar days of receipt of Notice To Proceed (NTP). Part 2, consists of maintenance dredging the Chincoteague Harbor of Refuge to a required depth of 9 feet MLLW (NOS) with one foot of allowable over depth dredging. The work shall be performed by a hydraulic dredge and pipeline with all dredged material transported and placed in the designated Government-furnished upland placement area only. The work involves dredging approximately 7,000 cubic yards of material including allowable over depth dredging and estimated accretion to September 2009.--- W26GLG91677925 - PROJECT NO.: 136130

0002 01 Mobilization and Demobilization 1 JOB LS ______________

0002 02 Dredging Chincoteague Harbor of Refuge 7,000 CY ___________ ______________ To a depth of 9 feet with 1 foot of allowable over depth, complete, including all associated work as indicated and specified

PART 2

TOTAL ESTIMATED AMOUNT OF BID ITEMS (0002 01 through 0002 02) ______________

PARTS 1 AND 2

TOTAL ESTIMATED AMOUNT OF BID ITEMS (0001 and 0002) ______________