Pre-solicitation - FY25 Brunswick Inner Harbor Maintenance Dredging Project
Closed Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- W912HN25B5007
- Agency
- ENDIST Savannah US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Z1KF Maintenance Of Dredging Facilities
- Place of performance
- Brunswick, Georgia, United States
- Points of contact
-
- Glenda Canty glenda.a.canty@usace.army.mil (912) 652-5030
- Rohan Bryan rohan.a.bryan@usace.army.mil (912) 652-5619
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of the Army Corps of Engineers Engineering District Savannah is seeking a small business contractor for the FY25 Brunswick Inner Harbor Maintenance Dredging Project. The contract will provide construction services for maintenance dredging in Brunswick Harbor, Georgia, including personnel, transportation, mobilization, equipment, and materials. Services will involve removing approximately 835,000 cubic yards of material from various river sections including the East River, South Brunswick River, Brunswick River, and Lower Turtle River using a hydraulic cutterhead dredge. The project is expected to take 120 days from notice to proceed, with dredged materials to be placed in the Andrews Island Dredged Material Containment Area. While specific evaluation criteria are not detailed in the pre-solicitation notice, the contract will be awarded as a Firm Fixed Price contract with responses due by May 21, 2025.
The opportunity is designated as a 100% Small Business Set Aside with a contract value between $1,000,000 and $5,000,000. The project involves dredging multiple river sections to maintain a 36-foot navigation depth, with approximately 700,000 cubic yards anticipated from the East River, 50,000 cubic yards from the South Brunswick River, 40,000 cubic yards from the Brunswick River, and 10,000 cubic yards from the Lower Turtle River. Environmental restrictions include a Least Tern nesting window that prohibits material placement in the disposal area between mid-April and mid-August. The dredging is traditionally performed in late summer or fall, with the work focused on maintaining navigational channels in Brunswick Harbor, located 70 statute miles south of Savannah Harbor and 25 statute miles north of Fernandina Harbor, Florida.
Notice text
This synopsis is for the FY25 Brunswick Inner Harbor Maintenance Dredging. This acquisition is being offered as a 100% Small Business Set Aside and will result in a Firm Fixed Price Contract Award. The magnitude of this requirement per FAR 36.204 is between $1,000,000.00 and $5,000,000.00.
The Brunswick Inner Harbor Dredging Contract provides construction services, including furnishing personnel, transportation, mobilization and demobilization, equipment and materials required in connection with maintenance dredging. This contract is traditionally performed with a hydraulic cutterhead dredge, and the duration is expected to be 120 days from notice to proceed. Up to 835 thousand cubic yards of maintenance material is expected to be removed from the inner harbor.
The work is located in Brunswick Harbor Georgia deep draft navigation project. Brunswick Harbor is located in Glynn County, Georgia, 70 statute miles south of the Savannah Harbor, Georgia, and 25 statute miles north of Fernandina Harbor, Florida. Brunswick Harbor Inner Harbor channel is 36 ft. deep MLLW and 400 ft. wide through St. Simon Sound, Brunswick River, Turtle River, South Brunswick River, and East River.
Brunswick Harbor Inner Harbor is generally dredged in late summer or fall. The dredging in the Brunswick Inner Harbor primarily takes place in the East River (station 0+000 to 12+000) which includes the East River Turning Basin and the Transition Areas leading up to the turning basin and immediately upriver of the basin. The South Brunswick River (station 0+000 to 7+000) in the Brunswick Inner Harbor is the other area that generally requires dredging and is primarily dredged when shoaling become problematic to navigation but is constantly monitored monthly. The Lower Turtle River (station 34+000 to 43+000) and Brunswick River (station 22+000 to 26+000) in the Brunswick Inner Harbor are other areas that may require dredging and are primarily dredged when shoaling become problematic to navigation, but are constantly monitored monthly. Approximately 700,000 cubic yards of material is anticipated to be removed from the East River, approximately 50,000 cubic yards of material is anticipated to be removed from the South Brunswick River, approximately 40,000 cubic yards of material is anticipated to be removed from the Brunswick River and approximately 10,000 cubic yards of material is anticipated to be removed from the Lower Turtle River this dredging cycle.
The maintenance material removed from the Brunswick Inner Harbor is placed in the Andrews Island Dredged Material Containment Area located adjacent to both the East River and the South Brunswick River. Andrews Island is the only confined upland containment area in the Brunswick Inner Harbor.
Advanced maintenance depths and locations for Brunswick Inner Harbor is as follows:
East River, 0+000 to 2+500 project depth is 36’ with 1’ of advanced maintenance
East River, 2+500 to 4+500 project depth is 36’ with 5’ of advanced maintenance
East River, 4+500 to 6+250 project depth is 36’ with 1’ of advanced maintenance
East River, Turning Basin project depth is 36’ with 1’ of advanced maintenance
South Brunswick River, 0+000 to 7+000 project depth is 36’ with no advanced maintenance
Brunswick River, 22+000 to 26+000 project depth is 36’ with no advanced maintenance
Lower Turtle River, 34+000 to 43+000, project depth is 36’ with no advanced maintenance
Environmental windows limit the timing of dredging in the Brunswick Inner Harbors. Environmental restrictions on the Brunswick Inner Harbor include a Least Tern nesting window to where dredged material must not be placed in the Andrews Island confined upland disposal area between the middle of April through the middle of August.
Notice history
| Notice | Type | Posted |
|---|---|---|
| W912HN25C5005 - Award Notice - FY25 Brunswick Inner Harbor Maintenance Dredging Project | Award Notice | |
| Solicitation - FY25 Brunswick Inner Harbor Maintenance Dredging Project | Solicitation | |
| Pre-solicitation - FY25 Brunswick Inner Harbor Maintenance Dredging Project | Pre-Solicitation | |
| Sources Sought - FY25 Brunswick Inner Harbor Maintenance Dredging | Pre-Solicitation | |
| Solicitation Hartwell O AND M Project | Solicitation | |
| DRAFT Solicitation Hartwell O&M Project | Special Notice | |
| W912HN24R5003 -Maintenance, Repair, Minor Construction, and Operations of the Hartwell Project -Savannah District | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity