About this opportunity

The U.S. Army Corps of Engineers, Kansas City District, issued a Special Notice on August 7, 2026, announcing that it will solicit preconstruction services and construction of Over the Horizon Radar (OTHR) infrastructure in Oregon using Construction Manager at Risk under 10 USC 2808a Other Transaction for Construction, with a Request for White Papers due no later than September 3, 2026.

The project encompasses two interdependent sites located approximately 125 miles apart—a Transmitting site and Receiver site—positioned to monitor the Northwest approach corridor. The Transmitting site requires clearing and grading over 2 square miles for antenna arrays, plus an Operations Facility (10,787 SF), Server Room, Water Treatment Building (1,323 SF), Vehicle Maintenance Shelter (1,600 SF), and Vehicle Storage Shelter (2,450 SF), all pre-engineered buildings on slab with associated utilities, EMI shielding, and support infrastructure. The Receiver site scope was truncated in the source material but is described as similarly configured.

USACE will employ a streamlined two-step competitive selection process. Step 1 requires interested parties to submit a Statement of Qualifications (maximum 10 pages) as white papers; the government intends to down-select up to three companies to proceed to Step 2, pitch meetings. One company will be selected as Construction Agent for preconstruction services award with a modification for construction award. Draft solicitation and white paper documents were released August 30, 2026, ahead of official issuance. Work is classified under NAICS 236220 and PSC Y1BC.

Notice text

2 versions

Update #2 · Latest ·

****20260830 Update - Providing Draft Documents**** This program is moving untypically fast. The current plan is to issue the Request for White Papers NLT 3 September 2026 with short suspenses for providing them as well as Step 2. In acknowledgement of this, we are attached the DRAFT Solicitation document and Request for White Papers. These are DRAFT and the official ones will be issued NLT 3 September 2026.

PROGRAM Notification For Construction Manager at Risk (CM@R) under Other Transaction (OT)Project: Over the Horizon Radar (OTHR) Infrastructure, Oregon. The U.S. Army Corps of Engineers (USACE) is issuing this notice to industry that this requirement will be solicited for preconstruction services and construction of the OTHR infrastructure using Construction Manager at Risk under 10 USC 2808a Other Transaction for Construction. This notice is provided for informational purposes to allow interested parties to be aware of the change in strategy.

Project Overview Project Title: OTHR Infrastructure

Location: Oregon

Agency: USACE, Kansas City District (NWK)

NAICS Code: 236220-Commerical and Industrial Building Construction

Project Description. This OTHR system requires two sites, a Transmitting site and a Receiver site, located approximately 125 miles apart that are interdependent and must be executed concurrently.

Acquisition Strategy (Pre-Award)USACE will use a streamlined competitive selection process: Step 1-White Papers: Interested parties will submit a Statement of Qualifications (max 10 pages). The government intends to down-select up to three Companies to proceed to Step 2. Step 2-Pitches: Selected Companies will participate in pitch meetings. One company will be selected as the Construction Agent for award of the initial preconstruction services with a modification for construction award. AwardThe agreement will be awarded to the most qualified Construction Agent to provide preconstruction services and construction. Post-award Phase 1 of the CM@R includes Pre-construction services and Post-award Phase 2 includes the construction. The agreement will be Firm-Fixed-Price (FFP). The FFP for construction milestones will be agreed to as the design is finalized and funds are available. Key Qualifications that will be used for the a. Demonstrated experience with heavy civil construction in remote locations. (Experience specific to radar arrays, other OTHR systems, and work with Tribal observers will be given more consideration)b. Demonstrated experience in remote locations requiring establishing and maintaining man camps.c. Demonstrated experience with work in remote locations requiring a tight schedule.d. Demonstrated experience with work in remote locations requiring heavy logistical coordination.

Update #1 ·

PROGRAM Notification

For Construction Manager at Risk (CM@R) under Other Transaction (OT)

Project: Over the Horizon Radar (OTHR) Infrastructure, Oregon

The U.S. Army Corps of Engineers (USACE) is issuing this notice to industry that this requirement will be solicited for preconstruction services and construction of the OTHR infrastructure using Construction Manager at Risk under 10 USC 2808a Other Transaction for Construction. This notice is provided for informational purposes to allow interested parties to be aware of the change in strategy.

Project Overview

Project Title: OTHR Infrastructure

Location: Oregon

Agency: USACE, Kansas City District (NWK)

NAICS Code: 236220-Commerical and Industrial Building Construction

Project Description

This OTHR system requires two sites, a Transmitting site and a Receiver site, located approximately 125 miles apart that are interdependent and must be executed concurrently.  The sites are remotely located and positioned to monitor the United States’ Northwest approach corridor.

Transmitting Site Requirements:

Besides clearing and grading a little over 2 square miles for the antenna arrays, the following are also required:

  • Operations Facility, Pre-Engineered Building (PEB) on slab, 10,787 SF
    • Server Room, workshop, office area, restroom, comm room, break room, logistics room, mechanical room, electrical room
    • EMI shielding in comm room, EMI shielding for UPS (located in electrical room)
    • 160 SF UPS Battery Shelter
    • Electric, comm, water, sewer (septic system) utilities
  • Water Treatment Building, PEB on slab, 1,323 SF
    • Fire water storage tank required, commercial off the shelf
    • Potable water storage tank required, commercial off the shelf
    • Connect to water well (well installed by others)
    • Treatment system for potable water
  • Vehicle Maintenance Shelter, PEB on slab, 1,600 SF
    • One 12’x12’ garage door
    • No heating
    • Electric and water utilities
  • Vehicle Storage Shelter, PEB on slab, 2,450 SF
    • Electric utilities only, no heating
    • Drive through Overhead Doors
    • Workbench areas
  • Power Area
    • Gravel area with all equipment and fuel storage on concrete pads
    • Houses transformers, backup generator system (2 generators, government furnished), 14.4KV load bank (government furnished),  80,000 gal generator fuel storage (double walled), switchgear integrated with SCDA, Network, and Metering System.
  • Fueling station (gasoline and diesel dispensing) with minimum 500 gal storage for diesel and 500 gal storage for gasoline
  • Security Building, PEB on slab, 387 SF
    •  Electric gate arm, lighting, fencing
    • Comms

Receiving Site Requirements:

Besides clearing and grading a little over 2 square miles for the antenna arrays, the following are also required:

  • Operations Facility, Pre-Engineered Building (PEB) on slab, 13,288 SF
    • Equipment Room, workshop, 1 office (open classified storage), Secure comms closet, Server room, restrooms, break room, logistics, fire/mechanical room, comm room, and electric room
    • Utilizes Fluid Cooling units on 8’x30’ concrete pad outside of facility
    • Specialized cable entry ports
    • Electric, comm, water, sewer (septic system) utilities
  • Water Treatment Building, PEB on slab, 1,323 SF
    • Fire water storage tank required, commercial off the shelf
    • Potable water storage tank required, commercial off the shelf
    • Connect to water well (well installed by others)
    • Treatment system for potable water
  • Vehicle Maintenance Shelter, PEB on slab, 1,600 SF
    • One 12’x12’ garage door
    • No heating
    • Electric and water utilities
  • Vehicle Storage Shelter, PEB on slab, 2,450 SF
    • Electric utilities only, no heating
    • Drive through Overhead Doors
    • Workbench areas
  • Power Area
    • Gravel area with all equipment and fuel storage on concrete pads
    • Houses transformers, backup generator system (2 generators, government furnished), 14.4KV load bank (government furnished), (4) 60,000 gal generator fuel storage (double walled), switchgear integrated with SCDA, Network, and Metering System.
  • Fueling station (gasoline and diesel dispensing) with minimum 500 gal storage for diesel and 500 gal storage for gasoline
  • Security Building, PEB on slab, 387 SF
    • Electric gate arm, lighting, fencing
  • Substation – serves as electrical utility interconnect and site distribution substation, includes enclosure for control shelter (with heating and cooling), fence, power distribution
  • Helicopter Landing Area, 100’ x 100’, minimal earthwork required

Acquisition Strategy (Pre-Award)

USACE will use a streamlined competitive selection process:

Step 1-White Papers: Interested parties will submit a Statement of Qualifications (max 10 pages). The government intends to down-select up to three Companies to proceed to Step 2.

Step 2-Pitches: Selected Companies will participate in pitch meetings. One company will be selected as the Construction Agent for award of the initial preconstruction services with a modification for construction award.

Award

The agreement will be awarded to the most qualified Construction Agent to provide preconstruction services and construction. Post-award Phase 1 of the CM@R includes Pre-construction services and Post-award Phase 2 includes the construction. The agreement will be Firm-Fixed-Price (FFP). The FFP for construction milestones will be agreed to as the design is finalized and funds are available.

Key Qualifications that will be used for the

Demonstrated experience with heavy civil construction in remote locations. (Experience specific to radar arrays, other OTHR systems, and work with Tribal observers will be given more consideration)

Demonstrated experience in remote locations requiring establishing and maintaining man camps.

Demonstrated experience with work in remote locations requiring a tight schedule.

Demonstrated experience with work in remote locations requiring heavy logistical coordination.

Notice history

Notice Type Posted
Over the Horizon Radar (OTHR) Infrastructure Latest solicitation Solicitation
This notice Original Special Notice

Similar open opportunities

Opportunity Agency Set-aside Responses due
Sources Sought- Sources Sought & Other Transaction Authority (OTA) Construction for Non-Destructive Testing Facility, Red River Army Depot, Texas Texas 75570, United States · NAICS 236220 ENDIST Fort Worth No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity