Old Hickory Turbine Generator Rehabilitation
Closed Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- W912P522R0003
- Agency
-
ENDIST Nashville
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Place of performance
- Hendersonville, Tennessee 37075, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This Pre-Solicitation Notice is seeking fixed-price construction proposals for the rehabilitation of turbine generator units at the Old Hickory Power Plant in Hendersonville, Tennessee, owned by the U.S. Army Corps of Engineers Nashville District. The scope of work includes rewinding the stators and replacing the turbine runners on Units 1, 2, and 3 to increase maximum output to 45 megawatts, as well as upgrading various mechanical and electrical systems to support the increased load. A site visit is scheduled for April 7, 2022, and interested offerors must submit security forms by the stated deadlines. Questions regarding this procurement must be submitted in writing to the identified point of contact by the deadline of June 3, 2022.
The estimated value of this contract is between $25-100 million. There is no set-aside designation. The anticipated NAICS code is 237990 for other heavy and civil engineering construction, with a small business size standard of $39.5 million. The scope of work will be performed over an estimated two year period and includes rewinding the generators, replacing turbine runners, and upgrading mechanical support systems for Units 1-3 at the Old Hickory Power Plant to increase maximum output to 45 megawatts.
Notice text
3 versions
Update #3 · Latest ·
The Nashville District U.S. Army Corps of Engineers (USACE) is soliciting for a firm fixed-price construction contract to rehabilitate turbine generator units at Old Hickory Power Plant, Hendersonville, TN. The estimated magnitude of this project is between $25,000,000 and $100,000,000.
Summary of work for the Old Hickory Turbine Generator Rehab Project:
The overall goal of this project is to increase generator maximum output to 45 MW. This will be accomplished by rewinding units 1, 2, and 3 and replacing turbines runner for the same units. Unit 4’s generator was rewound in 2021, but the turbine runner was not replaced. All the mechanical system to support this new load will have to be assessed and refurbished. While the units are down for rehabilitation there will be some efforts to upgrade or replace systems associated with the turbine generators.
General Project: The term of the project is estimated at two (2) years of model testing, design, and fabrication for the first unit. Followed by an additional eighteen (18) months of installation per base unit.
Electrical Work: The primary electrical scope of work is to accomplish the rewind and restack of the generator stators on Units 1, 2, and 3 to 45,000 kVA, with a 0.9 power factor at 13.8 kV. The electrical work includes, but is not limited to replacing the stator winding, replacing core laminations, reinsulating rotor poles, and model verification. Other major electrical scope items for Units 1, 2 and 3 include but are not limited to the installation of a machine condition monitoring system, refurbishment of rotor field poles and field leads, replacement of cable, wiring, relays, and RTDs, and furnishing and installing new high resistance grounding systems. The scope of work for each unit will culminate with testing and commissioning.
Turbine Work: The primary mechanical scope of work is the replacement of the Kaplan turbine runners of Units 1, 2, and 3 to an increased rated output of 61,600 hp at 54 feet of net head, along with replacement of the wicket gates. Turbine runner and wicket gate replacement for Unit 4 will be at the option of the Government. The existing turbine runners are 264-in diameter, 5-bladed Kaplan runners rated at 35,000 hp at a net head of 45 feet. Other turbine work will be focused around stay ring, bottom ring, headcovers, turbine shaft, bearings, operating ring, servomotors, and facing plates. A special item in this contract will be producing a display from the existing runner. Old Hickory’s powerhouse has experienced historical movement that has rendered the stator core eccentric to the discharge ring by as much as one-quarter inch on some units. Refurbishment of the discharge rings by machining and weld overlay is a feature of work that shall accomplish cavitation repair and the re-establishment of concentric unit alignment.
Mechanical Work: During the rehab all the mechanical support systems will be inspected, refurbished, or upgraded. This will include but not limited to brake ring, brake cylinders, thrust bearing coolers, float switches, digital relays, turbine guide bearing lubrication system, high pressure lift system addition, vacuum breakers, and wicket gate lubrication system, and rotating exciter will be removed.
The contractor will be required to provide all plant, labor and materials to construct these features.
The anticipated NAICS code is 237990, Other Heavy and Civil Engineering Construction, with a small business size standard of $39.5 million.
An organized site visit is scheduled for Thursday, April 7, 2022 at 9:00 a.m. Central Time. See FAR 52.236-27 Site Visit (Construction) (FEB 1995) – Alternate I for additional details. Vendors interested in attending the site visit MUST fill out the site visit request forms (FN Pre-bid or Site Visit Request Form or US Citizen Pre-bid or Site Visit Request Form provided as separate attachments to this notice) and submit them to Kristal Jones via e-mail at Kristal.R.Jones@usace.army.mil. Site visit request forms must be submitted for each individual company representative who will be in attendance at the site visit.
Foreign nationals submitting a site visit request form must have the form and its associated documentation sent to Kristal Jones at the aforementioned e-mail address at least 2 weeks prior to the site visit.
U.S. citizens submitting a site visit request form must have the form sent to Kristal Jones at the aforementioned e-mail address at least 5 business days prior to the site visit.
Failure to submit the site visit request forms in a timely manner will result in interested participants not being able to gain access to the areas that will be shown during the site visit.
Questions regarding this project must be submitted in writing via e-mail to Kristal Jones at Kristal.R.Jones@usace.army.mil. Please include the solicitation number and project name in the subject line of the e-mail.
--28 March 2022: This pre-solicitation notice is being amended to change the date of the site visit from Thursday, April 7, 2022 at 9:00 a.m. Central Time to Thursday, April 21, 2022 at 9:00 a.m. Central Time.
--13 April 2022: This pre-solicitation notice is being amended to change the date of the site visit from Thursday, April 21, 2022 at 9:00 a.m. Central Time to Thursday, April 28, 2022 at 9:00 a.m. Central Time.
Update #2 ·
The Nashville District U.S. Army Corps of Engineers (USACE) is soliciting for a firm fixed-price construction contract to rehabilitate turbine generator units at Old Hickory Power Plant, Hendersonville, TN. The estimated magnitude of this project is between $25,000,000 and $100,000,000.
Summary of work for the Old Hickory Turbine Generator Rehab Project:
The overall goal of this project is to increase generator maximum output to 45 MW. This will be accomplished by rewinding units 1, 2, and 3 and replacing turbines runner for the same units. Unit 4’s generator was rewound in 2021, but the turbine runner was not replaced. All the mechanical system to support this new load will have to be assessed and refurbished. While the units are down for rehabilitation there will be some efforts to upgrade or replace systems associated with the turbine generators.
General Project: The term of the project is estimated at two (2) years of model testing, design, and fabrication for the first unit. Followed by an additional eighteen (18) months of installation per base unit.
Electrical Work: The primary electrical scope of work is to accomplish the rewind and restack of the generator stators on Units 1, 2, and 3 to 45,000 kVA, with a 0.9 power factor at 13.8 kV. The electrical work includes, but is not limited to replacing the stator winding, replacing core laminations, reinsulating rotor poles, and model verification. Other major electrical scope items for Units 1, 2 and 3 include but are not limited to the installation of a machine condition monitoring system, refurbishment of rotor field poles and field leads, replacement of cable, wiring, relays, and RTDs, and furnishing and installing new high resistance grounding systems. The scope of work for each unit will culminate with testing and commissioning.
Turbine Work: The primary mechanical scope of work is the replacement of the Kaplan turbine runners of Units 1, 2, and 3 to an increased rated output of 61,600 hp at 54 feet of net head, along with replacement of the wicket gates. Turbine runner and wicket gate replacement for Unit 4 will be at the option of the Government. The existing turbine runners are 264-in diameter, 5-bladed Kaplan runners rated at 35,000 hp at a net head of 45 feet. Other turbine work will be focused around stay ring, bottom ring, headcovers, turbine shaft, bearings, operating ring, servomotors, and facing plates. A special item in this contract will be producing a display from the existing runner. Old Hickory’s powerhouse has experienced historical movement that has rendered the stator core eccentric to the discharge ring by as much as one-quarter inch on some units. Refurbishment of the discharge rings by machining and weld overlay is a feature of work that shall accomplish cavitation repair and the re-establishment of concentric unit alignment.
Mechanical Work: During the rehab all the mechanical support systems will be inspected, refurbished, or upgraded. This will include but not limited to brake ring, brake cylinders, thrust bearing coolers, float switches, digital relays, turbine guide bearing lubrication system, high pressure lift system addition, vacuum breakers, and wicket gate lubrication system, and rotating exciter will be removed.
The contractor will be required to provide all plant, labor and materials to construct these features.
The anticipated NAICS code is 237990, Other Heavy and Civil Engineering Construction, with a small business size standard of $39.5 million.
An organized site visit is scheduled for Thursday, April 7, 2022 at 9:00 a.m. Central Time. See FAR 52.236-27 Site Visit (Construction) (FEB 1995) – Alternate I for additional details. Vendors interested in attending the site visit MUST fill out the site visit request forms (FN Pre-bid or Site Visit Request Form or US Citizen Pre-bid or Site Visit Request Form provided as separate attachments to this notice) and submit them to Kristal Jones via e-mail at Kristal.R.Jones@usace.army.mil. Site visit request forms must be submitted for each individual company representative who will be in attendance at the site visit.
Foreign nationals submitting a site visit request form must have the form and its associated documentation sent to Kristal Jones at the aforementioned e-mail address at least 2 weeks prior to the site visit.
U.S. citizens submitting a site visit request form must have the form sent to Kristal Jones at the aforementioned e-mail address at least 5 business days prior to the site visit.
Failure to submit the site visit request forms in a timely manner will result in interested participants not being able to gain access to the areas that will be shown during the site visit.
Questions regarding this project must be submitted in writing via e-mail to Kristal Jones at Kristal.R.Jones@usace.army.mil. Please include the solicitation number and project name in the subject line of the e-mail.
28 March 2022: This pre-solicitation notice is being amended to chnage the date of the site visit from Thursday, April 7, 2022 at 9:00 a.m. Central Time to Thursday, April 21, 2022 at 9:00 a.m. Central Time.
Update #1 ·
The Nashville District U.S. Army Corps of Engineers (USACE) is soliciting for a firm fixed-price construction contract to rehabilitate turbine generator units at Old Hickory Power Plant, Hendersonville, TN. The estimated magnitude of this project is between $25,000,000 and $100,000,000.
Summary of work for the Old Hickory Turbine Generator Rehab Project:
The overall goal of this project is to increase generator maximum output to 45 MW. This will be accomplished by rewinding units 1, 2, and 3 and replacing turbines runner for the same units. Unit 4’s generator was rewound in 2021, but the turbine runner was not replaced. All the mechanical system to support this new load will have to be assessed and refurbished. While the units are down for rehabilitation there will be some efforts to upgrade or replace systems associated with the turbine generators.
General Project: The term of the project is estimated at two (2) years of model testing, design, and fabrication for the first unit. Followed by an additional eighteen (18) months of installation per base unit.
Electrical Work: The primary electrical scope of work is to accomplish the rewind and restack of the generator stators on Units 1, 2, and 3 to 45,000 kVA, with a 0.9 power factor at 13.8 kV. The electrical work includes, but is not limited to replacing the stator winding, replacing core laminations, reinsulating rotor poles, and model verification. Other major electrical scope items for Units 1, 2 and 3 include but are not limited to the installation of a machine condition monitoring system, refurbishment of rotor field poles and field leads, replacement of cable, wiring, relays, and RTDs, and furnishing and installing new high resistance grounding systems. The scope of work for each unit will culminate with testing and commissioning.
Turbine Work: The primary mechanical scope of work is the replacement of the Kaplan turbine runners of Units 1, 2, and 3 to an increased rated output of 61,600 hp at 54 feet of net head, along with replacement of the wicket gates. Turbine runner and wicket gate replacement for Unit 4 will be at the option of the Government. The existing turbine runners are 264-in diameter, 5-bladed Kaplan runners rated at 35,000 hp at a net head of 45 feet. Other turbine work will be focused around stay ring, bottom ring, headcovers, turbine shaft, bearings, operating ring, servomotors, and facing plates. A special item in this contract will be producing a display from the existing runner. Old Hickory’s powerhouse has experienced historical movement that has rendered the stator core eccentric to the discharge ring by as much as one-quarter inch on some units. Refurbishment of the discharge rings by machining and weld overlay is a feature of work that shall accomplish cavitation repair and the re-establishment of concentric unit alignment.
Mechanical Work: During the rehab all the mechanical support systems will be inspected, refurbished, or upgraded. This will include but not limited to brake ring, brake cylinders, thrust bearing coolers, float switches, digital relays, turbine guide bearing lubrication system, high pressure lift system addition, vacuum breakers, and wicket gate lubrication system, and rotating exciter will be removed.
The contractor will be required to provide all plant, labor and materials to construct these features.
The anticipated NAICS code is 237990, Other Heavy and Civil Engineering Construction, with a small business size standard of $39.5 million.
An organized site visit is scheduled for Thursday, April 7, 2022 at 9:00 a.m. Central Time. See FAR 52.236-27 Site Visit (Construction) (FEB 1995) – Alternate I for additional details. Vendors interested in attending the site visit MUST fill out the site visit request forms (FN Pre-bid or Site Visit Request Form or US Citizen Pre-bid or Site Visit Request Form provided as separate attachments to this notice) and submit them to Kristal Jones via e-mail at Kristal.R.Jones@usace.army.mil. Site visit request forms must be submitted for each individual company representative who will be in attendance at the site visit.
Foreign nationals submitting a site visit request form must have the form and its associated documentation sent to Kristal Jones at the aforementioned e-mail address at least 2 weeks prior to the site visit.
U.S. citizens submitting a site visit request form must have the form sent to Kristal Jones at the aforementioned e-mail address at least 5 business days prior to the site visit.
Failure to submit the site visit request forms in a timely manner will result in interested participants not being able to gain access to the areas that will be shown during the site visit.
Questions regarding this project must be submitted in writing via e-mail to Kristal Jones at Kristal.R.Jones@usace.army.mil. Please include the solicitation number and project name in the subject line of the e-mail.
Files
| File | Type | Posted |
|---|---|---|
| FN Pre_Bid or Site Visit Form JAN 2019.pdf | ||
| US Citizen Pre_Bid or Site Visit Form JAN 2019.pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Old Hickory Turbine Generator Rehabilitation | Award Notice | |
| Old Hickory Turbine Generator Rehabilitation | Solicitation | |
| This notice | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Tenkiller Hydropower Excitation System Replacement | ENDIST Tulsa | No set-aside | |
| Eufaula Powerhouse Hydroelectric Generator Rewind | ENDIST Tulsa | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity