OK FLAP 5407(1), Blackgum Landing Road
Closed Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- 6982AF21B000020
- Agency
-
Federal Highway Administration
Department of Transportation
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Roland, Oklahoma 74954, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This pre-solicitation notice seeks offers for the Blackgum Landing Road project located in Oklahoma. The Department of Transportation Federal Highway Administration aims to improve safety and access along the 1.85 mile roadway through full depth reclamation and resurfacing with 3 inches of asphalt concrete pavement. Contractors must have the capability to complete the work within the estimated two month timeframe from June to early August 2022. Key evaluation criteria will include technical approach, past performance, and price. The question deadline is November 17, 2021.
The project is set aside for total small business concerns. Significant quantities of work include 3.0 acres of clearing and grubbing, 5,400 cubic yards of subexcavation, 2,450 tons of roadway aggregate, 4,200 tons of asphalt concrete pavement, and installation of 64 linear feet of 3'x4' concrete box culvert and 8 linear feet of 8'x3' concrete box culvert. The engineer's estimate is between $1,850,000 to $2,550,000 for Schedule A. No right-of-way acquisition is included at this time and single lane closures will be allowed with flaggers or pilot car.
Notice text
PROJECT DESCRIPTION: Blackgum Landing Road provides direct access to Lake Tenkiller, Cato Creek, Chicken Creek, and Sixshooter USACE recreation areas as well as numerous homes with numerous driveways and intersections along Blackgum Landing Road. The purpose of the project is to provide an improved driving surface and improve safety of the roadway and improve access to the USACE recreational areas. This is considered a 3R project and will be completed by performing 6” of full depth reclamation and then placing 3” of asphalt concrete pavement.
The project begins at the intersection of County Road 100 and travels 1.85 miles north. The end terminal of the project is at Ridge Route Road. All portions of the project are included in the base Schedule A. There are no options.
SIGNIFICANT QUANTITIES (Schedule A):
Line Item Unit Estimated Quantity
CLEARING AND GRUBBING ACRE 3.0
ROADWAY EXCAVATION CUYD 260
SUBEXCAVATION CUYD 5400
WASTE CUYD 260
ROADWAY AGGREGATE TON 2450
FULL DEPTH RECLAMATION MILE 1.55
ASPHALT CONCRETE PAVEMENT TON 4200
3’X4’ CONCRETE BOX CULVERT LNFT 64
8’X3’ CONCRETE BOX CULVERT LNFT 8
FURNISHING AND PLACING TOPSOIL ACRE 3.0
SEEDING AND MULCING ACRE 3.0
ENGINEER’S ESTIMATE: Schedule A estimated costs are $1,850,000 to $2,550,000.
CONSTRUCTION DURATION: Construction duration is estimated at approximately 2 months, from June 1st to early August of 2022.
MISCELLANEOUS:
No ROW acquisition work is included at this time.
Single lane closure will be allowed with flaggers or pilot car.
Anticipated advertisement in fall of 2021
Anticipated bid opening in November of 2021
Anticipated Award in December 2021
Anticipated Notice to Proceed in January of 2022
Due to weather restrictions, on-site construction typically cannot occur until June of 2022
Notice history
| Notice | Type | Posted |
|---|---|---|
| OK FLAP 5407(1), Blackgum Landing Road | Award Notice | |
| OK FLAP 5407(1), Blackgum Landing Road | Solicitation | |
| This notice | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| OK FW TSM 10(1) NFH Entrance Road and Parking Improvements | Federal Highway Administration | Total Small Business | |
| Northeast Region Pavement and Bridge Preservation Construction - NP NER PMS BMS FY24(1) | Federal Highway Administration | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity