OK-deep fork NWR-levee gravel supply, delivery, an

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
140FS226Q0149
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of the Interior Fish and Wildlife Service seeks supply, delivery, and stockpiling of approximately 900 tons of limestone gravel to Deep Fork National Wildlife Refuge in Okmulgee, Oklahoma, with quotes due August 7 and delivery required by October 9, 2026. This is a Total Small Business set-aside, firm-fixed price procurement.

Place of performance is 21680 HWY 75, Okmulgee, OK 74447. The material specification comprises 600 tons of 1.5" limestone crusher run and 300 tons of No. 57-2" limestone clean aggregate, both conforming to State Department of Transportation Standard Specifications for Road and Bridge Construction. Material must be free of clay, organic matter, debris, asphalt, brick, concrete, and other deleterious substances. Contractor activities are limited to refuge operating hours (7:00 a.m. to 3:30 p.m., Monday through Friday) and must comply with OSHA Safety and Health Standards. Delivery must occur within 10 calendar days of requested date, with at least 14 calendar days written notice required beforehand. The contractor must provide price per ton including all labor, equipment, materials, weighing, testing, transportation, overhead, profit, and taxes. Material weighing on certified scales is mandatory, with weight tickets accompanying each load. Rejected material must be removed and replaced within five calendar days at no additional cost.

Contract period runs August 13 through October 9, 2026. NAICS code 212312 (Crushed and Broken Limestone Mining and Quarrying); PSC 5610 (Mineral Construction Materials, Bulk). Evaluation uses a Best Value trade-off approach: technical acceptability (pass/fail, requiring supplier commitment verification), past performance (three similar-work examples), and price. Technical acceptability and past performance are significantly more important than price for determining acceptability; price becomes the determining factor once acceptable proposals are identified. Offerors must submit supplier commitment letters certifying availability of 900 tons and specification compliance, product data sheets, and daily load capacity with lead time estimates.

Notice text

OK-DEEP FORK NWR-LEVEE GRAVEL SUPPLY, DELIVERY, AND STOCKPILING

Files

File Type Posted
Sol_140FS226Q0149.pdf PDF
B06_Supplier_commitment_Verification_Form.pdf PDF
A04_Map_GravelDropOffLocation.pdf PDF
A04_RFQ_SOW_Gravel.pdf PDF

Notice history

Notice Type Posted
OK-deep fork NWR-levee gravel supply, delivery, an Award Award Notice
This notice Latest solicitation Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Champion Creek Pit Rock Crushing Supply Idaho 83338, United States · NAICS 212321 Forest Service Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors