Oahe Project Pier 10 Bridge Rocker Bearing Modification

Closed Pre-Solicitation Posted

This opportunity was awarded. See the award notice from , or the latest solicitation from .

Solicitation number
W9128F22B0015
Agency
ENDIST Omaha US Army Corps of Engineers, Department of Defense
Responses due
Set-aside
Total Small Business

Opportunity facts

NAICS code
238110 Poured Concrete Foundation and Structure Contractors
PSC
Z2LB Repair Or Alteration Of Highways/Roads/Streets/Bridges/Railways
Place of performance
Pierre, South Dakota 57501, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This pre-solicitation notice is seeking contractors to modify the rocker bearings at Pier 10 of the Oahe Project bridge. The U.S. Army Corps of Engineers Engineering District Omaha requires contractors capable of repairing portions of the bridge located above the waterline using heavy machinery. Contractors must have the ability to place elevated concrete using pumping systems or chutes, install scaffolding above water for work, install adhesive anchors with qualified inspectors, and mechanically scarify and core drill through four feet of existing concrete. Pressure grouting equipment and methods to scan for existing reinforcement are also needed. The solicitation for this total small business set-aside will be posted on August 18th, 2022 with proposals due by September 20th, 2022.

This project is a 100% total small business set-aside, with the primary NAICS code 237990 (Other Heavy and Civil Engineering Construction) and PSC code R499 (Construction of Structures and Facilities). As an ongoing maintenance project for an existing structure, there is no identified incumbent and the award value will depend on the modification needs identified but is estimated to be under $5 million. The work must be completed efficiently while the bridge remains in service.

Notice text

PRESOLICITATION ANNOUNCEMENT - W9128F22B0015 - Oahe Project Pier 10 Bridge Rocker Bearing Modification

Oahe Project, Pier 10 Bridge Rocker Bearing Mod. The rocker bearings at Pier 10 have been moving gradually over time since the bridge was originally constructed. The bearings have been reset multiple times and are now at the edge of the pier.  The pier needs to be modified so that the rocker bearing can be reset as needed as the bridge piers continue to move. 

To effectively repair the bridge, the project will require contractors capable of repairing bridge portions located above the waterline, the usage of heavy machinery, and qualified staff to inspect the quality of the job being performed. The following conditions must be met to successfully complete the task: A system for placing elevated concrete, such as a pumping system or chutes that descend from the bridge's surface. Scaffolding is placed above the water so workers can do the job (bar placement, formwork placement, tensioning and a bar-tensioning jack. An installation team for the adhesive anchors, as well as qualified test inspectors.
Tools for mechanically scarifying the existing concrete surfaces and core drills that can drill through four feet of existing concrete are required for this project, pressure grouting equipment and a method of scanning for existing reinforcement in order to find it before digging.

This will be an IFB Procuement with the Solicitation being Posted on or about 18 August 2022
 

Notice history

Notices posted for this opportunity, newest first
Notice Type Posted
Oahe Project Pier 10 Bridge Rocker Bearing Modification Award Award Notice
Oahe Project Pier 10 Bridge Rocker Bearing Modification Latest solicitation Solicitation
Oahe Project Pier 10 Bridge Rocker Bearing Modification This notice · Original Pre-Solicitation

On GovTribe

Work this opportunity on GovTribe

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity