NUWC, B1258, Collaborative Workspace Enhancement
Awarded Award Notice Posted
- Solicitation number
- N4008516R4623
- Agency
- Naval Facilities Engineering Command Department of the Navy, Department of Defense
- Awarded
- to The Nutmeg Companies, Inc.
- Set-aside
- Total Small Business
Opportunity facts
- Contract number
- N4008514D52490008 Federal contract award
- NAICS code
- 541330 Engineering Services
- PSC
- Not on record
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
Added: Apr 06, 2016 3:25 pm
Modified: Jun 29, 2016 3:31 pmTrack Changes
Project shall add 1,780 sf additional work space to an existing 111,233 sf building. The addition is
proposed for the west side of the building, north of the main entrance. [Note: The entrance on the west
side provides grade-level access to the second floor of the building; the first floor is below grade. The
new workspace will consist of a single-story addition to the second floor of the building at grade level.]
Update #1 ·
Added: Apr 06, 2016 3:25 pm
This Project is Set Aside For NAVFAC Mid-Atlanticâs Small Business (SB) Multiple Award Construction Contract (MACC), For Design Build (DB) And Design Bid Build (DBB) Projects In The Northeast Area Of Responsibility (AOR); Contract Numbers: N40085-14-D-5245, N40085-14-D-5250, N40085-14-D-5249, N40085-14-D-5247, N40085-14-D-5248, AND N40085-14-D-5246.
The Contractor shall provide a construction schedule in sufficient detail to show all salient features of
work. As a minimum, the schedule shall include all submittals and administrative items required by the
contract, outages, delivery of materials, quality control activities (i.e. preparatory and initial phase
meetings), detailed work activities, inspections, punch list, etc.
No work may commence until the
baseline Network Analysis Schedule (NAS) is approved.
Include design and permit activities with the necessary conferences and follow-up actions and design
package submission dates. Include the design schedule in the project schedule, showing the sequence
of events involved in carrying out the project design tasks within the specific contract period. This shall
be at a detailed level of scheduling sufficient to identify all major design tasks, including those that
control the flow of work. The schedule shall include review and correction periods associated with each
item.
Attachments
| File | Type | Posted |
|---|---|---|
| RFI_Responses_to_RFIs_N40085-16-R-4623.docx | DOCX document | |
| Attachment 4 Specifications.compressed.pdf | ||
| Attachment_1_N40085-16-R-4623_Bid_Schedule.docx | DOCX document | |
| RFP_N40085-16-R-4623_Collaboration_Workspace_Bldg_1258.docx | DOCX document |