Norfolk Harbor Southern Branch Maintenance Dredging
Closed Pre-Solicitation Posted
A newer solicitation was posted. See the latest solicitation from .
- Solicitation number
- W9123625BA005
- Agency
- ENDIST Norfolk US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Z1KF Maintenance Of Dredging Facilities
- Place of performance
- Portsmouth, Virginia, United States
- Points of contact
-
- Luke Hedlund luke.d.hedlund@usace.army.mil (757) 201-7298
- Stormie Wicks stormie.b.wicks@usace.army.mil (757) 675-4428
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Army Corps of Engineers (USACE) Norfolk District plans to issue an Invitation for Bid (IFB) for maintenance dredging in the Southern Branch of the Elizabeth River in Hampton Roads, Virginia. The procurement will follow FAR Part 14 and result in a firm-fixed-price contract for mechanical dredging services. The project requires a contractor to perform dredging to specific depth levels (-41 and -36 feet MLLW), transport approximately 100,000 cubic yards of material by barge to the Craney Island Dredged Material Management Area (CIDMMA), and discharge material via direct pump-out method. Definitive Responsibility Criteria will be used to assess bidder qualifications, specifically requiring documented experience in mechanical dredging of at least 50,000 cubic yards in bay and coastal environments. The solicitation will be posted electronically on SAM.gov, with a current pre-solicitation notice date of March 19, 2025, and a response deadline of June 2, 2025.
The contract is designated as unrestricted and does not have a specific set-aside classification, with a project value estimated between $1,000,000 and $5,000,000 under NAICS code 237990 for Other Heavy and Civil Engineering Construction. The anticipated period of performance is 90 calendar days from the Notice to Proceed, with potential work restrictions between May 1 and August 31 due to nesting bird species at the CIDMMA. Bidders must be registered in SAM and maintain registration through contract performance and final payment. The project includes additional requirements such as maintaining spillways, ensuring water quality standards, and coordinating with maritime users to minimize operational impacts. Contractors should be prepared for potential site access limitations and operational constraints related to protected bird species in the project area.
Notice text
W9123625BA005
Norfolk Harbor Southern Branch Maintenance Dredging
Hampton Roads, VA
This is a pre-solicitation notice. This is NOT a solicitation. Do NOT submit proposals or questions in response to this notice.
The U.S. Army Corps of Engineers (USACE) Norfolk District (NAO) intends to issue an Invitation for Bid (IFB) acquisition for the Norfolk Harbor Southern Branch Maintenance Dredging in Hampton Roads, Virginia. This procurement will be conducted in accordance with FAR Part 14, Invitation for Bid (IFB).
The Government intends to award a firm-fixed-price (FFP) contract. The requirement will be solicited as unrestricted. The applicable NAICS code is 237990, Other Heavy and Civil Engineering Construction, with a Business Standard of $37M and Product Service Code of Z1KF - Maintenance of Dredging Facilities.
In accordance with FAR 36.204(f), the magnitude of construction for this project is between $1,000,000.00 and $5,000,000.00.
Project Description: Provide labor, material, and equipment to perform the following:
Required work includes maintenance dredging by mechanical dredge in the Southern Branch of the Elizabeth River, part of the Norfolk Harbor Federal Navigation Project. The segments are being dredged to required depth of -41 feet and -36 feet MLLW. One foot of allowable overdepth dredging will be included as part of the contract dredging pay prism. Dredged material generated by the project is expected to be transported by barge or scow and placed directly into the cell(s) at the Craney Island Dredged Material Management Area (CIDMMA). Dredging is estimated to generate approximately 100,000 cubic yards of pay volume.
The Contractor shall be responsible for the following: dredging within the designated areas to the proposed required and allowable pay depths, transporting the dredged material to the CIDMMA, discharging the material by direct pump-out method into the designated Government-furnished placement site, properly operating and maintaining the spillways within the CIDMMA, ensuring effluent water leaving the CIDMMA meets State water quality requirements, and communicating with the Port of Hampton Roads maritime users to minimize impacts to vessel traffic, adjacent utilities, and other dredging operations.
Period of performance to complete the work is anticipated to be 90 calendar days from Notice to Proceed.
*The CIDMMA is a known nesting area for Federal and State protected bird species. The Contractor can expect potential restrictions for use of certain areas within the CIDMMA between May 1 and August 31 due to nesting bird species. The area restrictions are not anticipated to significantly delay work progress. Examples of restrictions that may occur include relocation of discharge inflow point, restricted access in closure areas to vehicles and people, and limited vehicular access to spill boxes.
Definitive Responsibility Criteria:
This requirement will use Definitive Responsibility Criteria (DRC) which are specific and objective standards established to inform the Contracting Officer. In accordance with FAR 9.104-2. These criteria will be used to assess whether the apparent low bidder can demonstrate the expertise and specialized facilities needed for adequate contract performance. The inability of a contractor otherwise eligible for award to demonstrate minimally acceptable experience as measured by the DRC may result in the Contracting Officer determining the contractor is not responsible. The Definitive Responsibility Criteria will assess the following work items:
Dredging:
The apparent low bidder shall provide documented contract experience in performing a mechanical dredging job in bay and coastal environments of a minimum of 50,000 cubic yards (CY).
Placement at Craney Island Dredged Material Management Area (CIDMMA):
The apparent low bidder shall provide documented contract experience of mechanically dredging a minimum of 50,00 CY with the placement of dredged material via hydraulic pump-out from a barge/scow to a confined upland placement area.
The IFB and accompanying documents will be issued electronically and will be uploaded to SAM.gov.
Prospective bidders are responsible for monitoring SAM.gov to respond to the solicitation and any amendments or other information regarding this acquisition. Prospective bidders are required to be registered in SAM when submitting an offer and shall continue to be registered until time of award, during performance, and through final payment of any contract.
Notice history
| Notice | Type | Posted |
|---|---|---|
| Norfolk Harbor Southern Branch Maintenance Dredging | Solicitation | |
| Norfolk Harbor Southern Branch Maintenance Dredging | Pre-Solicitation | |
| Norfolk Harbor Southern Branch Maintenance Dredging | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities