MSFC Revitalized Pressure & Propellants –Phase 3

Closed Pre-Solicitation Posted

Solicitation number
MSFCPS30-PROC-25002
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Huntsville, Alabama 35812, United States

Notice details come from SAM.gov. Updated .

About this opportunity

NASA's Marshall Space Flight Center is seeking qualified Design-Build contractors for a comprehensive air compressor system replacement project at Facility 4607 on Redstone Arsenal in Huntsville, Alabama. The procurement involves replacing five high-pressure air compressors (3,500 psi, 1,350 SCFM each) and six low-pressure air compressors (125 psi, 2,200 SCFM each), along with associated air dryers, filtration systems, control systems, and electrical components. The agency plans to utilize a Two-Phase Design-Build Selection Process with Phase 1 Request for Qualifications followed by Phase 2 Request for Proposals, evaluated using Best Value Trade-off criteria. Contractors must demonstrate experience with utility plant installations, Design-Build Institute of America best practices implementation, and maintaining operational continuity during complex retrofits. Responses to this Request for Information are due by 12:00 PM CST on August 12, 2025, with an estimated contract award date of January 2026.

This procurement does not utilize any set-aside designation and no incumbent contractors are identified in the notice. The estimated project value ranges from $8-9 million according to the attached government file. The facility must remain operational 24 hours per day, 7 days per week throughout the project duration, requiring a phased implementation approach to accommodate budget constraints. The existing compressors have exceeded their expected service life since the facility's original construction in 1998, and the new systems must deliver a combined maximum flow rate of 6,750 SCFM for high-pressure units and 13,200 SCFM for low-pressure units. Interested firms must submit 10-page electronic responses addressing specific requirements including bonding capacity, technical skills, key personnel qualifications, and feedback on the proposed phased construction approach.

Notice text

RFI MSFCPS30-PROC-25002

MSFC Revitalized Pressure & Propellants –Phase 3

Marshall Space Flight Center (MSFC) is preparing to release a Design Build Request for Qualifications (RFQ) for an upcoming project to be completed at MSFC. The Government’s intent is to utilize Two-Phase Design-Build Selection Procedures (Phase 1 – Request for Qualifications / Phase 2 – RFP) with Best Value Trade-off Source Selection.

This is a request for information and is not to be construed as a commitment by the Government, implied or otherwise to issue a solicitation or ultimately award a contract. An award will not be made on offers received in response to this notice. This notice is not a request for proposal; it is a market research tool being utilized to determine the availability of qualified sources and receive comments on the below scope/description prior to issuing the RFQ and RFP. No questions will be taken at this time. The Government will not pay for effort expended in responding to this request.

Scope/Description:

The National Aeronautics and Space Administration (NASA), Marshall Space Flight Center (MSFC), is seeking information from qualified firms capable of providing Design-Build (D-B) services for the complete design, construction, and phased replacement of central air compressor systems at Facility 4607, located on Redstone Arsenal in Huntsville, Alabama.

Facility 4607 is a critical support asset for MSFC’s research and testing operations and must remain fully operational 24 hours per day, 7 days per week, throughout the duration of the project.
The scope includes the replacement of five (5) high-pressure air compressors, each rated at 3,500 psi with a flow rate of 1,350 standard cubic feet per minute (SCFM), for a combined maximum flow rate of 6,750 SCFM. The scope also includes the replacement of six (6) low-pressure air compressors, each rated at 125 psi with a flow rate of 2,200 SCFM, for a combined maximum flow rate of 13,200 SCFM. The project also involves the installation of air dryers, air filtration systems, control systems, and ancillary equipment such as motor starters, variable frequency drives (VFDs), and necessary electrical components to deliver a complete, integrated, and operable system.
Facility 4607 was originally constructed in 1998 and currently houses high- and low-pressure air compressors, air dryers, pumps, a control room, and restrooms. The compressors included in the project scope have exceeded their expected service life, and the existing controls are reliant on outdated systems that are no longer supported. Due to the facility's essential role, new compressors must be installed and integrated into the existing buildings in a manner that allows operations to remain uninterrupted.
The new compressor systems are expected to meet or exceed the flow capacity of the existing systems. The number of compressors should be the same or fewer than current units, while ensuring that at least two compressors remain operational at all times. Similarly, the new dryers must provide equal or greater flow capacity using the same number of units as the existing configuration. All systems must be compliant with current applicable codes and standards.
This project will be implemented in stages to accommodate budget constraints. The initial stage will include as much of the scope as current funding allows, with the intent to secure additional funding in future fiscal years to complete the remaining compressor replacements. All new compressors must be retrofitted to operate compatibly with the existing equipment until the entire system has been fully replaced.
The required services include full architectural and engineering (A&E) services, pressure system design, and construction services, to be delivered under a single design-build contract. The estimated award date for this potential contract is January 2026.

Files

File Type Posted
RFI RPPP3 7.29.25.pdf PDF

Similar open opportunities

Opportunity Agency Set-aside Responses due
WPAFB 3rd Air Stream/ B18 Wright Patterson AFB, Ohio, United States · NAICS 238220 ENDIST Louisville No set-aside
Recuperator Press Modification Replacement Anniston, Alabama 36201, United States · NAICS 333517 ACC Warren No set-aside
Air Compressor Relocation Washington, District of Columbia 20375, United States · NAICS 238210 Office of Naval Research No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity