MRPO Replacement Boiler - Solicitation
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W912EK23Q0029
- Agency
- ENDIST Rock Island US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 332410 Power Boiler and Heat Exchanger Manufacturing
- PSC
- 4410 Industrial Boilers
- Place of performance
- Pleasant Valley, Iowa 52767, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The US Army Corps of Engineers is seeking quotations for the replacement of boilers at the Mississippi River Project Office. The contract includes the supply of two new ultra-high efficiency boilers, with specific characteristics such as a minimum of 800,000 total BTUs, natural gas fuel, and a thermal efficiency of 95% or higher, as well as up to 100 feet of liner piping for boiler venting. The contractor must be able to deliver the boilers no later than 15 weeks after the award date, which is set for July 24, 2023.
Products and Services to be provided:
- Two new ultra-high efficiency boilers with specific characteristics.
- Up to 100 feet of liner piping for boiler venting.
- Delivery of the boilers to the specified location within 15 weeks of contract award.
- Warranty service for the supplied boilers.
- Invoicing and payment processing services.
Notice text
3 versions
Update #3 · Latest ·
Update 7/28/2023: Amendment 0001 is hereby issued. This amendment clarifies the number of BTUs per boiler unit and updates the schedule of prices. To be considered for award, interested vendors need to complete/have completed the solicitation (if already bid), and complete and sign the amendment and submit bid and/or revised bid by the new closing date of 8/2/2023.
Solicitation and Amendment 0001 are in attachments/links section below.
Update 7/20/2023: Questions were submitted this week via email. The questions asked and provided answers are posted here:
Q1: Do you prefer water of fire boiler tube?
A1: Water boiler tube is preferred.
Q2: What System Fluid Type? 100% Water or Propylene Glycol? Please specify percentage.
A2: The system fluid type is Glycol with a range of 200 to 300 gallons.
Q3: What is the Main Piping Size?
A3: It starts out a 2 inch for a foot then increases to a 2 ½ inch for ten feet then back down to 2 inch.
Q4: What is the main System GPM Flow?
A4: It is a 25 GPM Pump is a Bell & Gossett Model #FVB56T17D5598D P
Q5: What are the Existing Expansion Tank Size/Dimensions and type: Ceiling Compression Bladder/Diaphragm?
A5: It’s a Bladder Tank / Amtrol Tank Size ST30VC.
******************************************************************
The United States Army Corps of Engineers (USACE) hereby issues solicitation W912EK23Q0029 for the purchase of two new ultra-high efficiency, condensing boilers to be delivered to the Mississippi River Project Office (MRPO) in Pleasant Valley, Iowa. Solicitation and all instructions to complete and submit bids are in attachments/links section below.
Update #2 ·
Update 7/20/2023: Questions were submitted this week via email. The questions asked and provided answers are posted here:
Q1: Do you prefer water of fire boiler tube?
A1: Water boiler tube is preferred.
Q2: What System Fluid Type? 100% Water or Propylene Glycol? Please specify percentage.
A2: The system fluid type is Glycol with a range of 200 to 300 gallons.
Q3: What is the Main Piping Size?
A3: It starts out a 2 inch for a foot then increases to a 2 ½ inch for ten feet then back down to 2 inch.
Q4: What is the main System GPM Flow?
A4: It is a 25 GPM Pump is a Bell & Gossett Model #FVB56T17D5598D P
Q5: What are the Existing Expansion Tank Size/Dimensions and type: Ceiling Compression Bladder/Diaphragm?
A5: It’s a Bladder Tank / Amtrol Tank Size ST30VC.
*****************************************************************************************************************************
The United States Army Corps of Engineers (USACE) hereby issues solicitation W912EK23Q0029 for the purchase of two new ultra-high efficiency, condensing boilers to be delivered to the Mississippi River Project Office (MRPO) in Pleasant Valley, Iowa. Solicitation and all instructions to complete and submit bids are in attachments/links section below.
Update #1 ·
The United States Army Corps of Engineers (USACE) hereby issues solicitation W912EK23Q0029 for the purchase of two new ultra-high efficiency, condensing boilers to be delivered to the Mississippi River Project Office (MRPO) in Pleasant Valley, Iowa. Solicitation and all instructions to complete and submit bids are in attachments/links section below.
Attachments
| File | Type | Posted |
|---|---|---|
| A22 - W912EK23Q0029 00001 MRPO Boiler Replacement Amendment.pdf | ||
| A22 - W912EK23Q0029 MRPO Boiler Replacement Solicitation.pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| MRPO Replacement Boiler | Award Notice | |
| MRPO Replacement Boiler - Solicitation | Solicitation | |
| MRPO Replacement Boiler | Pre-Solicitation | |
| Miss. River Proj. Office - Upgrade Boiler System Controls | Special Notice |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity