About this opportunity

This pre-solicitation notice seeks capability statements from contractors interested in replacing the aging intake gate and performing repairs at the Mount St. Helens Spirit Lake headwall in Oregon. The U.S. Army Corps of Engineers Portland District will evaluate statements to determine the ability of respondents to complete a project estimated between $10-20 million. Contractors must demonstrate experience performing mechanical dredging, hydraulic steel structure fabrication, cofferdam design and implementation, and construction in remote, environmentally sensitive areas. Capability statements are due by March 18, 2022 and must include business information, qualifications, intended use of subcontractors, and past projects of similar scope and magnitude.

There is no set-aside designated for this procurement. The proposed NAICS code is 237990 for other heavy and civil engineering construction. Project work includes a 3-mile temporary access road, barge loading facility, dredging from barges or floating platforms, construction behind a cofferdam, and replacement of the inlet gate and slide gate. Respondents must also have experience working in conditions with limited cellular service and inclement weather.

Notice text

6 versions

Update #6 · Latest ·

Mount St. Helens Spirit Lake Intake Headwall

U.S. ARMY CORPS OF ENGINEERS, PORTLAND DISTRICT

ISSUED: 03/08/2021

RESPONSES DUE: 03/22/2021 at 5:00 pm

THIS IS A SOURCES SOUGHT ANNOUNCEMENT ONLY. This notice does not constitute a commitment by the Government.  All information submitted in response to this announcement is voluntary, and the Government will not pay for information requested nor will it compensate any respondent for any cost incurred in developing information provided to the Government.

The proposed NAICS code for this procurement is 237990 - Other Heavy and Civil Engineering Construction.

The US Army Corps of Engineers (USACE) Portland District is searching for Heavy and Civil Engineering Construction Contractors who can provide construction services for Mount St. Helens Spirit Lake Intake Headwall. As part of its market research, USACE Portland District, is issuing this Sources Sought to determine if there exists an adequate number of qualified interested contractors capable of providing the requirement. The Government may use the responses to this Sources Sought for information and planning purposes.

Debris from the 1980 Mount. St. Helens eruption blocked the historic outflow of the lake, and engineers built a tunnel to drain the lake and prevent a catastrophic flood.  A 1.5 mile drainage tunnel was built by the Army Corps of Engineers to drain the lake and prevent a catastrophic flood.  The 35-year-old tunnel needs extensive repairs, and were it to fail, the lake could rise, break through the debris blockage and cause disastrous flooding in the Cowlitz and Toutle valleys.

The multifaceted project focuses primarily on Spirit Lake’s drainage issues.   Re-establishing the road from Windy Ridge to the south shore of the lake would allow access the area to take samples of the debris blockage holding back the lake. It also would make it easier to replace the aging intake gate.  The proposed 3.4-mile access road would be built along an old road used by the U.S. Army Corps of Engineers in the early 1980s that generally tracks along the Truman Trail

The Mount St. Helens Spirit Lake Headwall will include to the following items:

• A 3 mile temporary access road including cut and fill road design.

• A lake-side barge loading facility consisting of an earthen ramp, and a staging area

• Mechanical Dredging from barges or floating work platforms

• Construction of and working behind a cofferdam

• Replacement of inlet gate, design of slide gate, hydraulic steel structures

• Concrete repair to Headwall

The anticipated magnitude for this project will be between $10,000,000 and $20,000,000.

*****UPDATED DATE******

The anticipated Solicitaiton release date for this project will be 13 April 2022

NO AWARD WILL MADE FROM THIS INITIAL NOTICE. THIS IS NOT AN INVITATION FOR BIDS OR REQUEST FOR PROPOSALS.

Submission Instructions:  Please send responses with the subject heading Spirit Lake Intake to Cory Pfenning, email address: cory.r.pfenning@usace.army.mil

CAPABILITY STATEMENT TO SHOW INTEREST AND INTENT:

Respondents interested in performing the proposed project as a prime contractor should submit a capability statement for consideration that include the following: (In A through F).

A. Offerors' name, address, points of contact with telephone numbers and e-mail addresses.

B. DUNS number and CAGE code.

C. Firm's small business category and Business Size: Small Business (SB), Small Disadvantaged (SDB), including 8(a) firms, Historically Underutilized Business Zones (HUBZone), Women-Owned Small Business (WOSB), including Economically Disadvantaged Women-Owned Small Business (EDWOSB), and Service-Disabled Veteran-Owned Small business (SDVOSB).

D. A Statement of Capability (SOC) stating your skills, experience, and knowledge required to perform the specified type of work as described above. This SOC should be a brief description of your company's capabilities. The potential bidders should provide the magnitude and brief references of relevant work they have performed.  Include a statement detailing any special qualifications and certifications, applicable to the scope of this project, held by your firm and/or in-house personnel.  including the following;

•Experience in performing work in remote locations, limited or no cellular service, inclement weather (high winds).

•Experience in performing work in highly sensitive natural environments.

•Experience in mechanical dredging operations

•Hydraulic Steel Structure (HSS) fabricator must be AISC Quality Certified, Category III, Major Steel Bridges with Fracture Critical Rating

•Experience in design and implementation of cofferdam systems

E. Indicate whether your company will perform the work directly or intends to subcontract the work. If subcontracting, identify the percentage of work to be subcontracted. Identify the percentage of work your firm may be capable of directly performing.

F. Any other information that would assist in determining your company's capability in performing the described construction work.

Responses to the Sources Sought will not be returned. Responders are solely responsible for all expenses associated with responding to this Sources Sought. USACE Portland District will not pay for information received in response to this Sources Sought.

Do not submit pricing information in response to this Sources Sought.

All responses must be submitted in either Microsoft Word or Adobe Portable Document Format by no later than 5:00 pm Pacific Time on Monday, 22 March 2021.  Do not include proprietary information in your response.

The Government reserves the right to use information provided by respondents for any purpose deemed necessary and legally appropriate.

Update #5 ·

Mount St. Helens Spirit Lake Intake Headwall

U.S. ARMY CORPS OF ENGINEERS, PORTLAND DISTRICT

ISSUED: 03/08/2021

RESPONSES DUE: 03/22/2021 at 5:00 pm

THIS IS A SOURCES SOUGHT ANNOUNCEMENT ONLY. This notice does not constitute a commitment by the Government.  All information submitted in response to this announcement is voluntary, and the Government will not pay for information requested nor will it compensate any respondent for any cost incurred in developing information provided to the Government.

The proposed NAICS code for this procurement is 237990 - Other Heavy and Civil Engineering Construction.

The US Army Corps of Engineers (USACE) Portland District is searching for Heavy and Civil Engineering Construction Contractors who can provide construction services for Mount St. Helens Spirit Lake Intake Headwall. As part of its market research, USACE Portland District, is issuing this Sources Sought to determine if there exists an adequate number of qualified interested contractors capable of providing the requirement. The Government may use the responses to this Sources Sought for information and planning purposes.

Debris from the 1980 Mount. St. Helens eruption blocked the historic outflow of the lake, and engineers built a tunnel to drain the lake and prevent a catastrophic flood.  A 1.5 mile drainage tunnel was built by the Army Corps of Engineers to drain the lake and prevent a catastrophic flood.  The 35-year-old tunnel needs extensive repairs, and were it to fail, the lake could rise, break through the debris blockage and cause disastrous flooding in the Cowlitz and Toutle valleys.

The multifaceted project focuses primarily on Spirit Lake’s drainage issues.   Re-establishing the road from Windy Ridge to the south shore of the lake would allow access the area to take samples of the debris blockage holding back the lake. It also would make it easier to replace the aging intake gate.  The proposed 3.4-mile access road would be built along an old road used by the U.S. Army Corps of Engineers in the early 1980s that generally tracks along the Truman Trail

The Mount St. Helens Spirit Lake Headwall will include to the following items:

• A 3 mile temporary access road including cut and fill road design.

• A lake-side barge loading facility consisting of an earthen ramp, and a staging area

• Mechanical Dredging from barges or floating work platforms

• Construction of and working behind a cofferdam

• Replacement of inlet gate, design of slide gate, hydraulic steel structures

• Concrete repair to Headwall

The anticipated magnitude for this project will be between $10,000,000 and $20,000,000.

*****UPDATED DATE******

The anticipated Solicitaiton release date for this project will be 13 April 2020

NO AWARD WILL MADE FROM THIS INITIAL NOTICE. THIS IS NOT AN INVITATION FOR BIDS OR REQUEST FOR PROPOSALS.

Submission Instructions:  Please send responses with the subject heading Spirit Lake Intake to Cory Pfenning, email address: cory.r.pfenning@usace.army.mil

CAPABILITY STATEMENT TO SHOW INTEREST AND INTENT:

Respondents interested in performing the proposed project as a prime contractor should submit a capability statement for consideration that include the following: (In A through F).

A. Offerors' name, address, points of contact with telephone numbers and e-mail addresses.

B. DUNS number and CAGE code.

C. Firm's small business category and Business Size: Small Business (SB), Small Disadvantaged (SDB), including 8(a) firms, Historically Underutilized Business Zones (HUBZone), Women-Owned Small Business (WOSB), including Economically Disadvantaged Women-Owned Small Business (EDWOSB), and Service-Disabled Veteran-Owned Small business (SDVOSB).

D. A Statement of Capability (SOC) stating your skills, experience, and knowledge required to perform the specified type of work as described above. This SOC should be a brief description of your company's capabilities. The potential bidders should provide the magnitude and brief references of relevant work they have performed.  Include a statement detailing any special qualifications and certifications, applicable to the scope of this project, held by your firm and/or in-house personnel.  including the following;

•Experience in performing work in remote locations, limited or no cellular service, inclement weather (high winds).

•Experience in performing work in highly sensitive natural environments.

•Experience in mechanical dredging operations

•Hydraulic Steel Structure (HSS) fabricator must be AISC Quality Certified, Category III, Major Steel Bridges with Fracture Critical Rating

•Experience in design and implementation of cofferdam systems

E. Indicate whether your company will perform the work directly or intends to subcontract the work. If subcontracting, identify the percentage of work to be subcontracted. Identify the percentage of work your firm may be capable of directly performing.

F. Any other information that would assist in determining your company's capability in performing the described construction work.

Responses to the Sources Sought will not be returned. Responders are solely responsible for all expenses associated with responding to this Sources Sought. USACE Portland District will not pay for information received in response to this Sources Sought.

Do not submit pricing information in response to this Sources Sought.

All responses must be submitted in either Microsoft Word or Adobe Portable Document Format by no later than 5:00 pm Pacific Time on Monday, 22 March 2021.  Do not include proprietary information in your response.

The Government reserves the right to use information provided by respondents for any purpose deemed necessary and legally appropriate.

Update #4 ·

Mount St. Helens Spirit Lake Intake Headwall

U.S. ARMY CORPS OF ENGINEERS, PORTLAND DISTRICT

ISSUED: 03/08/2021

RESPONSES DUE: 03/22/2021 at 5:00 pm

THIS IS A SOURCES SOUGHT ANNOUNCEMENT ONLY. This notice does not constitute a commitment by the Government.  All information submitted in response to this announcement is voluntary, and the Government will not pay for information requested nor will it compensate any respondent for any cost incurred in developing information provided to the Government.

The proposed NAICS code for this procurement is 237990 - Other Heavy and Civil Engineering Construction.

The US Army Corps of Engineers (USACE) Portland District is searching for Heavy and Civil Engineering Construction Contractors who can provide construction services for Mount St. Helens Spirit Lake Intake Headwall. As part of its market research, USACE Portland District, is issuing this Sources Sought to determine if there exists an adequate number of qualified interested contractors capable of providing the requirement. The Government may use the responses to this Sources Sought for information and planning purposes.

Debris from the 1980 Mount. St. Helens eruption blocked the historic outflow of the lake, and engineers built a tunnel to drain the lake and prevent a catastrophic flood.  A 1.5 mile drainage tunnel was built by the Army Corps of Engineers to drain the lake and prevent a catastrophic flood.  The 35-year-old tunnel needs extensive repairs, and were it to fail, the lake could rise, break through the debris blockage and cause disastrous flooding in the Cowlitz and Toutle valleys.

The multifaceted project focuses primarily on Spirit Lake’s drainage issues.   Re-establishing the road from Windy Ridge to the south shore of the lake would allow access the area to take samples of the debris blockage holding back the lake. It also would make it easier to replace the aging intake gate.  The proposed 3.4-mile access road would be built along an old road used by the U.S. Army Corps of Engineers in the early 1980s that generally tracks along the Truman Trail

The Mount St. Helens Spirit Lake Headwall will include to the following items:

• A 3 mile temporary access road including cut and fill road design.

• A lake-side barge loading facility consisting of an earthen ramp, and a staging area

• Mechanical Dredging from barges or floating work platforms

• Construction of and working behind a cofferdam

• Replacement of inlet gate, design of slide gate, hydraulic steel structures

• Concrete repair to Headwall

The anticipated magnitude for this project will be between $10,000,000 and $20,000,000.

The anticipated Solicitaiton release date for this project will be 5 October 2021

NO AWARD WILL MADE FROM THIS INITIAL NOTICE. THIS IS NOT AN INVITATION FOR BIDS OR REQUEST FOR PROPOSALS.

Submission Instructions:  Please send responses with the subject heading Spirit Lake Intake to Cory Pfenning, email address: cory.r.pfenning@usace.army.mil

CAPABILITY STATEMENT TO SHOW INTEREST AND INTENT:

Respondents interested in performing the proposed project as a prime contractor should submit a capability statement for consideration that include the following: (In A through F).

A. Offerors' name, address, points of contact with telephone numbers and e-mail addresses.

B. DUNS number and CAGE code.

C. Firm's small business category and Business Size: Small Business (SB), Small Disadvantaged (SDB), including 8(a) firms, Historically Underutilized Business Zones (HUBZone), Women-Owned Small Business (WOSB), including Economically Disadvantaged Women-Owned Small Business (EDWOSB), and Service-Disabled Veteran-Owned Small business (SDVOSB).

D. A Statement of Capability (SOC) stating your skills, experience, and knowledge required to perform the specified type of work as described above. This SOC should be a brief description of your company's capabilities. The potential bidders should provide the magnitude and brief references of relevant work they have performed.  Include a statement detailing any special qualifications and certifications, applicable to the scope of this project, held by your firm and/or in-house personnel.  including the following;

•Experience in performing work in remote locations, limited or no cellular service, inclement weather (high winds).

•Experience in performing work in highly sensitive natural environments.

•Experience in mechanical dredging operations

•Hydraulic Steel Structure (HSS) fabricator must be AISC Quality Certified, Category III, Major Steel Bridges with Fracture Critical Rating

•Experience in design and implementation of cofferdam systems

E. Indicate whether your company will perform the work directly or intends to subcontract the work. If subcontracting, identify the percentage of work to be subcontracted. Identify the percentage of work your firm may be capable of directly performing.

F. Any other information that would assist in determining your company's capability in performing the described construction work.

Responses to the Sources Sought will not be returned. Responders are solely responsible for all expenses associated with responding to this Sources Sought. USACE Portland District will not pay for information received in response to this Sources Sought.

Do not submit pricing information in response to this Sources Sought.

All responses must be submitted in either Microsoft Word or Adobe Portable Document Format by no later than 5:00 pm Pacific Time on Monday, 22 March 2021.  Do not include proprietary information in your response.

The Government reserves the right to use information provided by respondents for any purpose deemed necessary and legally appropriate.

Update #3 ·

Mount St. Helens Spirit Lake Intake Headwall

U.S. ARMY CORPS OF ENGINEERS, PORTLAND DISTRICT

ISSUED: 03/08/2021

RESPONSES DUE: 03/22/2021 at 5:00 pm

THIS IS A SOURCES SOUGHT ANNOUNCEMENT ONLY. This notice does not constitute a commitment by the Government.  All information submitted in response to this announcement is voluntary, and the Government will not pay for information requested nor will it compensate any respondent for any cost incurred in developing information provided to the Government.

The proposed NAICS code for this procurement is 237990 - Other Heavy and Civil Engineering Construction.

The US Army Corps of Engineers (USACE) Portland District is searching for Heavy and Civil Engineering Construction Contractors who can provide construction services for Mount St. Helens Spirit Lake Intake Headwall. As part of its market research, USACE Portland District, is issuing this Sources Sought to determine if there exists an adequate number of qualified interested contractors capable of providing the requirement. The Government may use the responses to this Sources Sought for information and planning purposes.

Debris from the 1980 Mount. St. Helens eruption blocked the historic outflow of the lake, and engineers built a tunnel to drain the lake and prevent a catastrophic flood.  A 1.5 mile drainage tunnel was built by the Army Corps of Engineers to drain the lake and prevent a catastrophic flood.  The 35-year-old tunnel needs extensive repairs, and were it to fail, the lake could rise, break through the debris blockage and cause disastrous flooding in the Cowlitz and Toutle valleys.

The multifaceted project focuses primarily on Spirit Lake’s drainage issues.   Re-establishing the road from Windy Ridge to the south shore of the lake would allow access the area to take samples of the debris blockage holding back the lake. It also would make it easier to replace the aging intake gate.  The proposed 3.4-mile access road would be built along an old road used by the U.S. Army Corps of Engineers in the early 1980s that generally tracks along the Truman Trail

The Mount St. Helens Spirit Lake Headwall will include to the following items:

• A 3 mile temporary access road including cut and fill road design.

• A lake-side barge loading facility consisting of an earthen ramp, and a staging area

• Mechanical Dredging from barges or floating work platforms

• Construction of and working behind a cofferdam

• Replacement of inlet gate, design of slide gate, hydraulic steel structures

• Concrete repair to Headwall

The anticipated magnitude for this project will be between $10,000,000 and $20,000,000.

NO AWARD WILL MADE FROM THIS INITIAL NOTICE. THIS IS NOT AN INVITATION FOR BIDS OR REQUEST FOR PROPOSALS.

Submission Instructions:  Please send responses with the subject heading Spirit Lake Intake to Cory Pfenning, email address: cory.r.pfenning@usace.army.mil

CAPABILITY STATEMENT TO SHOW INTEREST AND INTENT:

Respondents interested in performing the proposed project as a prime contractor should submit a capability statement for consideration that include the following: (In A through F).

A. Offerors' name, address, points of contact with telephone numbers and e-mail addresses.

B. DUNS number and CAGE code.

C. Firm's small business category and Business Size: Small Business (SB), Small Disadvantaged (SDB), including 8(a) firms, Historically Underutilized Business Zones (HUBZone), Women-Owned Small Business (WOSB), including Economically Disadvantaged Women-Owned Small Business (EDWOSB), and Service-Disabled Veteran-Owned Small business (SDVOSB).

D. A Statement of Capability (SOC) stating your skills, experience, and knowledge required to perform the specified type of work as described above. This SOC should be a brief description of your company's capabilities. The potential bidders should provide the magnitude and brief references of relevant work they have performed.  Include a statement detailing any special qualifications and certifications, applicable to the scope of this project, held by your firm and/or in-house personnel.  including the following;

•Experience in performing work in remote locations, limited or no cellular service, inclement weather (high winds).

•Experience in performing work in highly sensitive natural environments.

•Experience in mechanical dredging operations

•Hydraulic Steel Structure (HSS) fabricator must be AISC Quality Certified, Category III, Major Steel Bridges with Fracture Critical Rating

•Experience in design and implementation of cofferdam systems

E. Indicate whether your company will perform the work directly or intends to subcontract the work. If subcontracting, identify the percentage of work to be subcontracted. Identify the percentage of work your firm may be capable of directly performing.

F. Any other information that would assist in determining your company's capability in performing the described construction work.

Responses to the Sources Sought will not be returned. Responders are solely responsible for all expenses associated with responding to this Sources Sought. USACE Portland District will not pay for information received in response to this Sources Sought.

Do not submit pricing information in response to this Sources Sought.

All responses must be submitted in either Microsoft Word or Adobe Portable Document Format by no later than 5:00 pm Pacific Time on Monday, 22 March 2021.  Do not include proprietary information in your response.

The Government reserves the right to use information provided by respondents for any purpose deemed necessary and legally appropriate.

Update #2 ·

Mount St. Helens Spirit Lake Intake Headwall

U.S. ARMY CORPS OF ENGINEERS, PORTLAND DISTRICT

ISSUED: 03/08/2021

RESPONSES DUE: 03/22/2021 at 5:00 pm

THIS IS A SOURCES SOUGHT ANNOUNCEMENT ONLY. This notice does not constitute a commitment by the Government.  All information submitted in response to this announcement is voluntary, and the Government will not pay for information requested nor will it compensate any respondent for any cost incurred in developing information provided to the Government.

The proposed NAICS code for this procurement is 237990 - Other Heavy and Civil Engineering Construction.

The US Army Corps of Engineers (USACE) Portland District is searching for Heavy and Civil Engineering Construction Contractors who can provide construction services for Mount St. Helens Spirit Lake Intake Headwall. As part of its market research, USACE Portland District, is issuing this Sources Sought to determine if there exists an adequate number of qualified interested contractors capable of providing the requirement. The Government may use the responses to this Sources Sought for information and planning purposes.

Debris from the 1980 Mount. St. Helens eruption blocked the historic outflow of the lake, and engineers built a tunnel to drain the lake and prevent a catastrophic flood.  A 1.5 mile drainage tunnel was built by the Army Corps of Engineers to drain the lake and prevent a catastrophic flood.  The 35-year-old tunnel needs extensive repairs, and were it to fail, the lake could rise, break through the debris blockage and cause disastrous flooding in the Cowlitz and Toutle valleys.

The multifaceted project focuses primarily on Spirit Lake’s drainage issues.   Re-establishing the road from Windy Ridge to the south shore of the lake would allow access the area to take samples of the debris blockage holding back the lake. It also would make it easier to replace the aging intake gate.  The proposed 3.4-mile access road would be built along an old road used by the U.S. Army Corps of Engineers in the early 1980s that generally tracks along the Truman Trail

The Mount St. Helens Spirit Lake Headwall will include to the following items:

• A 3 mile temporary access road including cut and fill road design.

• A lake-side barge loading facility consisting of an earthen ramp, and a staging area

• Mechanical Dredging from barges or floating work platforms

• Construction of and working behind a cofferdam

• Replacement of inlet gate, design of slide gate, hydraulic steel structures

• Concrete repair to Headwall

The anticipated magnitude for this project will be between $10,000,000 and $20,000,000.

NO AWARD WILL MADE FROM THIS INITIAL NOTICE. THIS IS NOT AN INVITATION FOR BIDS OR REQUEST FOR PROPOSALS.

Submission Instructions:  Please send responses with the subject heading Spirit Lake Intake to Cory Pfenning, email address: cory.r.pfenning@usace.army.mil

CAPABILITY STATEMENT TO SHOW INTEREST AND INTENT:

Respondents interested in performing the proposed project as a prime contractor should submit a capability statement for consideration that include the following: (In A through F).

A. Offerors' name, address, points of contact with telephone numbers and e-mail addresses.

B. DUNS number and CAGE code.

C. Firm's small business category and Business Size: Small Business (SB), Small Disadvantaged (SDB), including 8(a) firms, Historically Underutilized Business Zones (HUBZone), Women-Owned Small Business (WOSB), including Economically Disadvantaged Women-Owned Small Business (EDWOSB), and Service-Disabled Veteran-Owned Small business (SDVOSB).

D. A Statement of Capability (SOC) stating your skills, experience, and knowledge required to perform the specified type of work as described above. This SOC should be a brief description of your company's capabilities. The potential bidders should provide the magnitude and brief references of relevant work they have performed.  Include a statement detailing any special qualifications and certifications, applicable to the scope of this project, held by your firm and/or in-house personnel.  including the following;

•Experience in performing work in remote locations, limited or no cellular service, inclement weather (high winds).

•Experience in performing work in highly sensitive natural environments.

•Experience in mechanical dredging operations

•Hydraulic Steel Structure (HSS) fabricator must be AISC Quality Certified, Category III, Major Steel Bridges with Fracture Critical Rating

•Experience in design and implementation of cofferdam systems

E. Indicate whether your company will perform the work directly or intends to subcontract the work. If subcontracting, identify the percentage of work to be subcontracted. Identify the percentage of work your firm may be capable of directly performing.

F. Any other information that would assist in determining your company's capability in performing the described construction work.

Responses to the Sources Sought will not be returned. Responders are solely responsible for all expenses associated with responding to this Sources Sought. USACE Portland District will not pay for information received in response to this Sources Sought.

Do not submit pricing information in response to this Sources Sought.

All responses must be submitted in either Microsoft Word or Adobe Portable Document Format by no later than 5:00 pm Pacific Time on Monday, 18 March 2021.  Do not include proprietary information in your response.

The Government reserves the right to use information provided by respondents for any purpose deemed necessary and legally appropriate.

Update #1 ·

Mount St. Helens Spirit Lake Intake Headwall

U.S. ARMY CORPS OF ENGINEERS, PORTLAND DISTRICT

ISSUED: 03/08/2021

RESPONSES DUE: 03/22/2021 at 5:00 pm

THIS IS A SOURCES SOUGHT ANNOUNCEMENT ONLY. This notice does not constitute a commitment by the Government.  All information submitted in response to this announcement is voluntary, and the Government will not pay for information requested nor will it compensate any respondent for any cost incurred in developing information provided to the Government.

The proposed NAICS code for this procurement is 237990 - Other Heavy and Civil Engineering Construction.

The US Army Corps of Engineers (USACE) Portland District is searching for Heavy and Civil Engineering Construction Contractors who can provide construction services for Mount St. Helens Spirit Lake Intake Headwall. As part of its market research, USACE Portland District, is issuing this Sources Sought to determine if there exists an adequate number of qualified interested contractors capable of providing the requirement. The Government may use the responses to this Sources Sought for information and planning purposes.

Debris from the 1980 Mount. St. Helens eruption blocked the historic outflow of the lake, and engineers built a tunnel to drain the lake and prevent a catastrophic flood.  A 1.5 mile drainage tunnel was built by the Army Corps of Engineers to drain the lake and prevent a catastrophic flood.  The 35-year-old tunnel needs extensive repairs, and were it to fail, the lake could rise, break through the debris blockage and cause disastrous flooding in the Cowlitz and Toutle valleys.

The multifaceted project focuses primarily on Spirit Lake’s drainage issues.   Re-establishing the road from Windy Ridge to the south shore of the lake would allow access the area to take samples of the debris blockage holding back the lake. It also would make it easier to replace the aging intake gate.  The proposed 3.4-mile access road would be built along an old road used by the U.S. Army Corps of Engineers in the early 1980s that generally tracks along the Truman Trail

The Mount St. Helens Spirit Lake Headwall will include to the following items:

• A 3 mile temporary access road including cut and fill road design.

• A lake-side barge loading facility consisting of an earthen ramp, and a staging area

• Mechanical Dredging from barges or floating work platforms

• Construction of and working behind a cofferdam

• Replacement of inlet gate, design of slide gate, hydraulic steel structures

• Concrete repair to Headwall

The anticipated magnitude for this project will be between $10,000,000 and $20,000,000.

NO AWARD WILL MADE FROM THIS INITIAL NOTICE. THIS IS NOT AN INVITATION FOR BIDS OR REQUEST FOR PROPOSALS.

Submission Instructions:  Please send responses with the subject heading Spirit Lake Intake to Cory Pfenning, email address: cory.r.pfenning@usace.army.mil

CAPABILITY STATEMENT TO SHOW INTEREST AND INTENT:

Respondents interested in performing the proposed project as a prime contractor should submit a capability statement for consideration that include the following: (In A through F).

A. Offerors' name, address, points of contact with telephone numbers and e-mail addresses.

B. DUNS number and CAGE code.

C. Firm's small business category and Business Size: Small Business (SB), Small Disadvantaged (SDB), including 8(a) firms, Historically Underutilized Business Zones (HUBZone), Women-Owned Small Business (WOSB), including Economically Disadvantaged Women-Owned Small Business (EDWOSB), and Service-Disabled Veteran-Owned Small business (SDVOSB).

D. A Statement of Capability (SOC) stating your skills, experience, and knowledge required to perform the specified type of work as described above. This SOC should be a brief description of your company's capabilities. The potential bidders should provide the magnitude and brief references of relevant work they have performed.  Include a statement detailing any special qualifications and certifications, applicable to the scope of this project, held by your firm and/or in-house personnel.  including the following;

•Experience in performing work in remote locations, limited or no cellular service, inclement weather (high winds).

•Experience in performing work in highly sensitive natural environments.

•Experience in mechanical dredging operations

•Hydraulic Steel Structure (HSS) fabricator must be AISC Quality Certified, Category III, Major Steel Bridges with Fracture Critical Rating

•Experience in design and implementation of cofferdam systems

E. Indicate whether your company will perform the work directly or intends to subcontract the work. If subcontracting, identify the percentage of work to be subcontracted. Identify the percentage of work your firm may be capable of directly performing.

F. Any other information that would assist in determining your company's capability in performing the described construction work.

Responses to the Sources Sought will not be returned. Responders are solely responsible for all expenses associated with responding to this Sources Sought. USACE Portland District will not pay for information received in response to this Sources Sought.

Do not submit pricing information in response to this Sources Sought.

All responses must be submitted in either Microsoft Word or Adobe Portable Document Format by no later than 5:00 pm Pacific Time on Monday, 18 March 2020.  Do not include proprietary information in your response.

The Government reserves the right to use information provided by respondents for any purpose deemed necessary and legally appropriate.

Notice history

Notice Type Posted
Mount ST. Helens spirit lake tunnel intake Award Award Notice
Mount ST. Helens spirit lake tunnel intake Latest solicitation Solicitation
Mount ST. Helens spirit lake tunnel intake Pre-Solicitation
This notice Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
USCG Station at Cape Disappointment ENDIST Portland No set-aside
FY26 Willapa Harbor Maintenance Dredging Washington, United States · NAICS 237990 ENDIST Seattle No set-aside
John day DAM navigation lock tainter valve (TV) repairs TV3 and TV4 Location and Access Details. Oregon Side Physical Access, Near Rufus, OR 97050 accessible via I-84, Exit 109. Washington Side (Closest Town), Goldendale, WA 98620 approximately 20 miles north across the river. River Location, Mile 216.6 on the Columbia River, joining Sherman County, Oregon, and Klickitat County, Washington. 98628 · NAICS 237990 ENDIST Portland No set-aside
CA-humboldt BAY NWR-tide gate repair NAICS 236220 — Total Small Business
John day DAM unit 10 packing box replacement John Day Dam, Sherman County, Oregonthe John Day Dam On The Columbia River Between Sherman County, Oregon, And Klickitat County, Washington. Rufus, Oregon 97050, United States · NAICS 237990 ENDIST Portland No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors