Market intelligence notice / request for information (RFI)

Open Pre-Solicitation Posted

Solicitation number
W912HV27ZOTA1
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

PSC
Not on record
Place of performance
Multiple Military Bases Okinawa Japan

Notice details come from SAM.gov. Updated .

About this opportunity

The U.S. Army Corps of Engineers Japan District Contracting Division anticipates soliciting five Marine Corps microgrid and power generation projects in Japan under one or more Other Transaction Authority agreements, using a Construction Manager at Risk model, with responses to this market intelligence RFI due December 17, 2026 at 1400 JST. No solicitation is currently available. The OTA vehicle, authorized under 10 U.S.C. 2808a, is exempt from the FAR and the Small Business Act, and the notice uses No Set-Aside. The Marine Corps ERCIP program sponsors the projects, which are sited at Camp Fuji, Shizuoka Prefecture; Marine Corps Air Station Iwakuni, Yamaguchi Prefecture; and Camp Foster, Camp Courtney, and Camp Hansen, Okinawa.

Each site involves a resilient microgrid with natural gas and diesel generators, solar photovoltaic systems, battery energy storage, utility interconnection, microgrid controls, commissioning, and cybersecurity measures. Site ranges are Camp Fuji $30 million to $50 million, Iwakuni $100 million to $150 million, Foster $100 million to $150 million, Courtney $50 million to $100 million, and Hansen $100 million to $150 million, for a combined portfolio of $380 million to $600 million. Projected awards are May 2028 for Camp Fuji and February 2029 for Iwakuni and Foster; Hansen and Courtney award dates are to be determined. Design runs 2028 to 2032, construction runs 2029 to 2034, and construction at the five sites overlaps.

CMMC Level 1 compliance is anticipated as a contract requirement, and the RFI asks for recommendations on obtaining RMF Authority to Operate. Camp Fuji operates at 50 Hz while the other sites operate at 60 Hz. The planned process uses a two-step qualification: Step 1 requests roughly 10-page statements of qualifications with three finalists selected, and Step 2 holds pitch presentations, selecting the most highly qualified firm without price discussion. Phase 2 construction pricing is set through a Guaranteed Maximum Price at 95 to 100 percent design completion, and the Government may solicit construction competitively if GMP negotiations fail.

The RFI questionnaire covers ten topics, including bonding capacity, subcontractor teaming, and portfolio packaging (single portfolio, two regional packages, or five agreements). Responses go by email to Christine Allen (heather.c.allen@usace.army.mil) and Erica Stiner (erica.j.stiner@usace.army.mil). Participation is voluntary, the Government will not reimburse preparation costs, and responding does not affect eligibility for future proposals.

Notice text

USACE Japan District

Contracting Division POCs:

  • H. Christine Allen (email: heather.c.allen@usace.army.mil)
  • Erica J. Stiner (email: erica.j.stiner@usace.army.mil)

Notice: This is a Market Intelligence Notice/ Request for Information (RFI) and is for informational purposes only. This announcement does not constitute a Solicitation or a Request for Proposal (RFP), and no solicitation is currently available. Participation in this RFI is strictly voluntary. The Government will not be obligated to award any agreement or contract because of this RFI, nor will it reimburse respondents for any costs associated with the preparation or submission of information. Submitting a response will not affect a firm’s ability to submit a proposal should a formal solicitation be issued in the future.

Acquisition Approach & Delivery Method: The Government anticipates soliciting these requirements under one or more Other Transaction Authority (OTA) agreements pursuant to 10 U.S.C. § 2808a, utilizing a Construction Manager at Risk (CM@R) delivery model. Under this collaborative framework, the Government intends to engage a construction manager early during preconstruction (Phase 1) to actively influence the design alongside the Architect-Engineer Firm by providing constructability reviews, value engineering, schedule optimization, and open-book cost modeling prior to negotiating price for construction execution (Phase 2).

Cybersecurity Maturity Model Certification: CMMC Level 1 Anticipated

NAICS Code: 236220 – Commercial and Institutional Building Construction

(Note: While Other Transaction Authority is not subject to FAR-based small business regulations, this NAICS code is provided for market research to help the Government understand the size and demographics of the interested industrial base.)

______________________________________________________________________

Project Overview: The U.S. Army Corps of Engineers (USACE), in partnership with the United States Marine Corps (USMC), is conducting market research to formulate an acquisition strategy for a five-project portfolio under the Energy Resilience and Conservation Investment Program (ERCIP). These projects establish islanded, cybersecure microgrids and decentralized power generation to guarantee 14+ days of continuous mission operations without commercial grid power across key operational hubs in Japan.

Total Estimated Acquisition Magnitude: Between $380,000,000 - $600,000,000.

_______________________________________________________________________

Anticipated Project Profiles:

1. Project P-904: Microgrid and Backup Power -- CATC Camp Fuji (Shizuoka Prefecture)

Target Budget: $30M to $50M

Key Generation & Storage Assets:

  • 400 kW Solar Photovoltaic (PV) System
  • 800 kW Electric Peaker Plant (Gas Peaker / BESS)
  • 400 kW Standby Diesel Generator Plant

Key Supporting Works: Install onsite generation including storage equipment from a solar photovoltaic system, peaker generation plant and/or battery storage assets, and diesel-fired standby generator. This work includes all required electrical, mechanical, plumbing, and controls work associated with each install. A microgrid controller will be installed, and generation assets will be connected to the microgrid. The controls and microgrid will be cyber-secured. The system will be commissioned.

Mission Mandate: Support III Marine Expeditionary Force (III MEF) combined arms live-fire training. Removes vulnerability as the end-of-the-line consumer on the commercial utility.

2. Project P-1016: Power Generation and Microgrid -- MCAS Iwakuni (Yamaguchi Prefecture)

Target Budget: $100M to $150M

Key Generation & Storage Assets:

  • 12,500 kW Diesel Power Plant
  • 6,000 kW Solar Photovoltaic (PV) System
  • 2.4 MW Battery Energy Storage System (BESS)

Key Supporting Works: Construct a resilient microgrid with diverse energy sources to include natural gas and diesel generators to maximize resilience, PV system, and a BESS. Work to include utility interconnects, microgrid and other controls, commissioning, and cybersecurity.

Mission Mandate: Maintain continuous flightline and mission operations for Carrier Air Wing Five (CVW-5) and Marine Aircraft Group 12 (MAG-12), with a goal of zero downtime for Pacific Air Mobility and tactical air sorties.

3. Project P-312: Power Generation and Microgrid -- Camp Foster (Okinawa)

Target Budget: $100M to $150M

Key Generation & Storage Assets:

  • 3,000 kW Gas Turbine Power Plant
  • 4,500 kW Diesel Power Plant
  • 2,100 kW Solar Photovoltaic (PV) System
  • 979 kW Battery Energy Storage System (BESS)

Key Supporting Works: A PV system, onsite gas and diesel generation to maximize resilience, and a BESS. This project will also include utility interconnections, microgrid and other controls, commissioning, and cybersecurity.

Mission Mandate: Support Major Subordinate Command headquarters (MCIPAC, 1st Marine Aircraft Wing and the U.S. Naval Hospital Okinawa. Goal is 14+ days of islanded operations.

4. Project P-625: Microgrid and Backup Power -- Camp Hansen (Okinawa)

Target Budget: $100M to $150M

Key Generation & Storage Assets:

  • 10,000 kW Standby Diesel Generator Plant
  • 1,148 kW Solar Photovoltaic (PV) System
  • 2,400 kW (4-Hour) Battery Energy Storage System (BESS)

Key Supporting Works: Install centralized diesel generation, ground/roof solar PV arrays, and a 4-hour BESS to support microgrid stability and contingency operations. Electrical scope includes medium-voltage switchgear, generator interconnections, and integration of all generation and storage assets into a centralized, cybersecure microgrid controller. Supporting scope includes civil site preparation and grading, utility interconnection modernization, communications network enhancements, full system commissioning, and RMF cybersecurity authorization.

Mission Mandate: Support the III MEF Information Group (MIG) and the 31st Marine Expeditionary Unit (31st MEU) across critical facilities. Eliminates points of failure and fuel logistics constraints to deliver 100% critical load capability in island mode for 14+ days.

5. Project P-406: Microgrid and Backup Power -- Camp Courtney (Okinawa)

Target Budget: $50M to $100M

Key Generation & Storage Assets:

  • 5,000 kW Standby Diesel Electric Power Plant (two generator sets)
  • 1,685 kW Solar Photovoltaic (PV) System
  • 2,400 kW (4-Hour) Battery Energy Storage System (BESS)
  • 4,000 SF Standby Generator Enclosure/Facility

Key Supporting Works: Construct a 4,000 SF facility to house the standby generator sets and install solar PV alongside a 4-hour BESS for microgrid stability and ride-through capability. Work includes medium-voltage distribution integration, site civil grading and paving, utility interconnection upgrades, communications improvements, mechanical work for solar racking, full functional commissioning, and Risk Management Framework (RMF) cybersecurity accreditation.

Mission Mandate: Support III Marine Expeditionary Force (III MEF), 3rd Marine Division, and 3D Marine Expeditionary Brigade (MEB) Headquarters across mission-critical facilities. Ensures continuous command and control capabilities with a goal of 14+ days of islanded operations during commercial grid disruptions and severe weather events.

Industry Questionnaire

Submission Instructions: Please see the attached Market Intelligence Questionnaire document and email your response to Christine Allen (heather.c.allen@usace.army.mil) and Erica Stiner (erica.j.stiner@usace.army.mil) by 17 December 2026 at 14:00 Japan Standard Time.

Purpose: The Government is seeking industry insight to identify potential delivery methods, evaluate commercial capabilities, understand host-nation supply chain dynamics, and determine whether these requirements should be executed via standard Federal Acquisition Regulation (FAR) contracts or through Other Transaction Authority (OTA) under 10 U.S.C. § 2808a using Construction Manager at Risk (CM@R).

Planned Acquisition Strategy: Other Transaction Authority (OTA) with Construction Manager at Risk (CM@R)

USACE Japan District is conducting market intelligence to assess industry capability and interest in supporting this effort utilizing an Other Transaction (OT) Agreement under the authority of 10 U.S.C. § 2808a, Facility Construction or Repair: Transactions Other Than Contracts and Grants. This authority is distinct from the Department of Defense prototype OT authorities commonly associated with 10 U.S.C. § 4021 and 4022. This authority is intended for military construction projects that involve testing and experimentation associated with new and emergent construction technologies to achieve potential benefits such as enhanced mission resilience, improved installation support, or cost and schedule reduction.

  • Phase 1: Pre-Construction Services - The OT Awardee shall assist the Government collaboratively in achieving its goals with respect to the project’s scope, constructability, budget, quality, schedule, and in coordination with the Designer of Record.
  • Phase 2: Final Design and Construction - Upon reaching an agreed-upon level of design (e.g., 95 to 100%), the Awardee will propose a Guaranteed Maximum Price (GMP). If the GMP is accepted, the Government will exercise construction execution. If a GMP cannot be agreed upon, the Government retains the right to "off-ramp" the contractor in order to complete the construction of the facility via alternative methods.

Files

Similar open opportunities

Opportunity Agency Set-aside Responses due
FY2026 - FY2027 Projections Japan ENDIST Japan No set-aside
FY2027 Projections ENDIST Japan No set-aside
DLA DWCF B1907 Backup Power Generator, Yokosuka, Japan Japan · NAICS 237130 ENDIST Japan No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors