This document is an overview of Other Transactional Authority (OTA) procurement mechanisms and Construction Manager at Risk (CM@R) processes for five proposed U.S. Marine Corps resilient microgrid and power generation projects located at military installations in Japan.
The five proposed projects are: (1) FY25 P904 at Camp Fuji, Shizuoka, projected award May 2028; (2) FY26 P1016 at Marine Corps Air Station Iwakuni, Yamaguchi, projected award February 2029; (3) FY30 P312 at Camp Foster, Okinawa, projected award February 2029; (4) FYTBD P-625 at Camp Hansen, Okinawa, award date to be determined; and (5) FYTBD P406 at Camp Courtney, Okinawa, award date to be determined. Each project involves construction of resilient microgrids incorporating natural gas and diesel generators, solar photovoltaic systems, battery energy storage systems, utility interconnections, microgrid controls, commissioning, and cybersecurity measures. All projects are sponsored by the Marine Corps Energy Resilient Construction Improvement Program (ERCIP). The procuring agency is USACE (U.S. Army Corps of Engineers).
The OTA procurement process, authorized under 10 U.S.C. § 2808a, is exempt from Federal Acquisition Regulations (FAR), Cost Accounting Standards, Truth in Negotiations Act, Competition in Contracting Act, Small Business Act, and Project Labor Agreements, though it remains subject to Fiscal Law, Miller Act payment and performance bonds, Buy American, cybersecurity requirements, environmental compliance, and procurement integrity laws. The CM@R approach comprises two award phases: Phase 1 Preconstruction Services and Phase 2 Construction. The solicitation uses a two-step qualification process—Step 1 requests approximately 10-page Statements of Qualifications (white papers), with the Government selecting three finalists; Step 2 consists of interactive pitch presentations where the Government selects the most highly qualified firm without price discussion. Phase 1 negotiations cover agreement terms, scope of services, payment schedule, and profit. Phase 2 involves development of a Guaranteed Maximum Price (GMP) through open book estimating at 95-100% design completion, with the Government retaining the right to off-ramp and solicit construction competitively if GMP negotiations fail. Benefits include early contractor collaboration during design and long-lead item procurement authorization prior to 100% design completion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Industry Questions OTA_CMatR Japan ERCIP Microgrids.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
� � �Overview: Other Transactional Authority (OTA) and Construction Manager at Risk (CM@R)
Overview:
Other Transactional Authority (OTA) and Construction Manager at Risk (CM@R)
Proposed Upcoming Projects Using OTA with CM@R Install Power Generation and Microgrids at the following locations:
1. Combined Arms Training Center Camp Fuji, Shizuoka
2. Marine Corps Air Station Iwakuni, Yamaguchi
3. Camp Foster, Okinawa
4. Camp Hansen, Okinawa
5. Camp Courtney, Okinawa
What is Other Transaction Authority (OTA)?
What is Other Transaction Authority (OTA)?
• A legal authority to enter into transactions other than standard contracts, grants, or cooperative agreements. It provides the flexibility to adopt commercial industry standards and best practices.
- Primarily were used for research and prototyping, but new authority has expanded its use for construction under 10 U.S.C. § 2808a.
• OTAs are not subject to the Federal Acquisition Regulations (FAR). This can attract non-traditional partners and encourages flexible, collaborative, and commercial arrangements.
→ OTAs are awarded by Agreements Officers (AO), similar to the Contracting Officer (KO) on a project.
→ Administrative Agreements Officers (AAO), similar to the Administrative Contracting Officer (ACO), may be assigned for post-award construction administration.
→ Agreements Officer Representatives (AOR), similar to a Contracting Officer’s Representatives (COR), may be assigned.
Laws Applicable to OTAs
Laws Applicable to OTAs
*Contract Disputes Act – Agreements issued under an agency under its other transactional authority are not procurement contracts. Instead, the agreements are the sort of “new type of contractual relationship” established by Congress “with the specific intent” that agreements are not considered contracts under CDA. Procedures for resolving disputes between the agency and the OTA recipient are addressed in the OTA. OTA recipients must seek to resolve any disputes with the agency according to the procedures set forth in the OTA.
What Applies: What Does Not Apply:
Fiscal Law (Funding) Federal Acquisition Regulation
Miller Act Payment & Performance Bonds (Construction) Cost Accounting Standards (CAS)
Buy American Truth in Negotiations Act (TINA)
Cybersecurity- CMMC Requirements (if applicable to the project) Competition in Contracting Act (CICA)
Security, Export Control, DPAS Ratings Small Business Act
Procurement Integrity, False Claims Act, Conflicts of Interest, Bribery, Kickbacks
Project Labor Agreements (PLA)
Environmental Compliance (NEPA, UFC, Installation), OSHA Selection of Architects and Engineers
Law: 10 U.S.C. § 2808a
Regulations. Though FAR does not apply, there are regulations/laws the Government must follow:
�What is the OTA with Construction Manager at Risk (CM@R) Process
What is the OTA with Construction Manager at Risk (CM@R) Process
• Design. USACE retains a design firm to complete plans and specifications. The construction contractor is then brought on through the OTA with CM@R process to collaborate during the design phase.
• Solicitation. The solicitation process is conducted through full and open competition over a multiple step process.
- The most highly qualified firm is selected.
- All terms are negotiated to provide flexibility in the agreement.
- The agreement award is broken into two areas; preconstruction services and construction
Preconstruction Services. The construction contractor (builder) is brought on early to provide construction expertise and collaborates during the design phase to improve constructability, cost, schedule, and any phasing requirements.
Construction. The construction contractor then proposes a Guaranteed Maximum Price (GMP) for the construction of the project. This will serve as a firm-fixed-price ceiling for the construction.
Aka: White Papers
Contractor Collaborates w/ Design Firm
Process Overview
Process Overview
Construction Manager at Risk (CM@R) Process
Construction Manager at Risk (CM@R) Process
Solicitation. The RFP will be issued in two major steps:
Step1: Request for Qualifications/White Papers. The Government will provide all necessary project information for interested parties to submit an approximately 10-page Statements of Qualifications (SOQ)/White Papers. The submission will focus on identifying the most qualified teams based on qualifications such as team composition, past relevant experience, or other factors as identified.
→ The Government will evaluate and select a target of three (3) most highly qualified firms to move to Step 2.
Step 2. Pitch Presentations. The firms selected in Phase 1 will be invited to an interactive pitch presentation.
The presentation will include the company’s pitch for collaboration with the design firm, problem solving, any innovative solutions, and a Question-and-Answer session. Price is not discussed.
→ Upon conclusion of the pitch presentations, the Government Evaluation Team will come to a consensus on the most highly qualified company for award.
“White Papers”
Construction Manager at Risk (CM@R) Process Continued
Construction Manager at Risk (CM@R) Process Continued
Award. Award of the agreement will occur in two phases- Preconstruction Services and Construction Agreements:
• Phase 1 Preconstruction Services. The Government team will then negotiate the price of Agreement for Phase 1 for Preconstruction Services with the selected firm. Negotiations will include:
- Articles (Terms) of the Agreement
- Scope of Services
- Payment Schedule
- Profit
“White Papers”
Construction Manager at Risk (CM@R) Process Continued
Construction Manager at Risk (CM@R) Process Continued
• Phase 2 Construction. Once the design is mature, generally between 95% to 100%, the Phase 2 Construction negotiations will begin. Contractors will develop a Guaranteed Maximum Price (GMP) through Open Book (transparent) estimating. Transition from Phase 1 to Phase 2 is contingent upon the Government’s formal acceptance of the GMP construction price.
→ If the contractor and Government cannot reach an agreement, the Government reserves the right to off-ramp and solicit the construction competitively.
Upon execution of the Phase 2 Agreement, the project will move into the construction phase. This phase will operate similarly to a standard construction project. OTA with CM@R benefits include:
- Long Lead Item Procurement can begin prior to 100% design with AO approval
- Enables an earlier start to construction
�Proposed Projects- Japan ERCIP Microgrid Portfolio (Projects 1–3)
Proposed Projects- Japan ERCIP Microgrid Portfolio (Projects 1–3)
3. FY30 P312 Power Generation and Microgrid Who: Marine Corps ERCIP What: Resilient Microgrid Where: Camp Foster When: Projected Award by Feb 2029 Why: Camp Foster requires the ability to provide energy availability to the warfighter in the event of power disruption.
Summary of Work: The project constructs a microgrid to involve natural gas and diesel generators to maximize resilience, a solar photovoltaic system and a battery storage system. Construction for this project includes onsite gas and diesel generation to maximize resilience, a solar photovoltaic (PV) system, and a battery energy storage system (BESS). This project will also include utility interconnections, microgrid and other controls, commissioning, and cybersecurity.
1. FY25 P904 Power Generation and Microgrid Who: Marine Corps ERCIP What: Resilient Microgrid Where: Camp Fuji When: Projected Award by May 2028 Why: Improve operational capabilities by ensuring Camp Fuji does not solely rely on commercial power to support operations.
Summary of Work: Construct a resilient microgrid with diverse energy sources to include natural gas and diesel generators to maximize resilience, PV system, and a BESS. Work to include utility interconnects, microgrid and other controls, commissioning, and cybersecurity.
2. FY26 P1016 Power Generation and Microgrid Who: Marine Corps ERCIP What: Resilient Microgrid Where: MCAS Iwakuni When: Projected Award by Feb 2029 Why: MCAS Iwakuni requires the capability to adequately provide energy availability to the warfighter in the event of power disruption.
Summary of Work: Construction for this project includes onsite gas and diesel generation to maximize resilience, a solar photovoltaic (PV) system, and a battery energy storage system (BESS). This project will also include utility interconnections, microgrid and other controls, commissioning, and cybersecurity.
�Proposed Projects- Japan ERCIP Microgrid Portfolio (Projects 4–5)
Proposed Projects- Japan ERCIP Microgrid Portfolio (Projects 4–5)
4. FYTBD P-625: Microgrid and Backup Power, Camp Hansen (Okinawa) Who: Marine Corps ERCIP What: Resilient Microgrid Where: Camp Hansen When: Projected Award TBD Why: Improve operational capabilities by ensuring Camp Hansen can continue to support command control operations for the warfighter to Marines in the even of extended power disruptions.
Summary of Work: Proposed construction includes installation of a diesel electric power plant consisting of two standby generator sets and construction of a generator facility to house and support the units.
A solar photovoltaic system will be installed along with a battery energy storage system to support microgrid stability and ride through capability. Microgrid and control systems will be provided to integrate all new generation and storage assets and coordinate operation with the installation’s medium voltage electrical distribution system.
Commissioning will include full functional testing, simulations, operator training, and system validation.
5. FYTBD P406 Microgrid and Backup Power, Camp Courtney (Okinawa) Who: Marine Corps ERCIP What: Resilient Microgrid Where: Camp Courtney When: Projected Award TBD Why: This project will ensure adequate backup power system is in place for the warfighter to Marines, Sailors, and their families stationed on Camp Courtney.
Summary of Work: Proposed construction includes installation of diesel fired standby generator units, a solar photovoltaic system, and a battery energy storage system to support microgrid stability and contingency operations. Electrical work provides medium voltage switchgear, generator interconnection, and integration of all generation and storage assets into a cyber secure microgrid.
Mechanical work includes installation of solar racking and related components to meet installation requirements. The entire system will be commissioned
| Overview: �Other Transactional Authority (OTA) �and �Construction Manager at Risk (CM@R) |
| What is Other Transaction Authority (OTA)? |
| Laws Applicable to OTAs |
| What is the OTA with Construction Manager �at Risk (CM@R) Process |
| Process Overview |
| Construction Manager at Risk (CM@R) Process |
| Construction Manager at Risk (CM@R) Process Continued |
| Construction Manager at Risk (CM@R) Process Continued |
| Proposed Projects- Japan ERCIP Microgrid Portfolio (Projects 1–3)� |
| Proposed Projects- Japan ERCIP Microgrid Portfolio (Projects 4–5)� |