Market Intelligence Notice – Hangar Construction (Hybrid Conventional and Tension Fabric Structures)

Closed Special Notice Posted

Solicitation number
W912HN26MITSF
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Savannah, Georgia, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The U.S. Army Corps of Engineers, Savannah District, issued a Request for Information on hangar construction using tension fabric structures and hybrid industrialized construction approaches, with responses due October 23, 2026. This RFI is for market intelligence and planning purposes only and does not constitute a commitment to issue a future solicitation; the Government will not reimburse respondents for information or administrative costs.

USACE seeks to identify industry capabilities relevant to modern industrialized construction solutions intended to improve schedule, cost, and lifecycle outcomes for large-span mission support facilities. The Government will use responses to understand available market participants, solution types, and industry interest, and to inform future industry engagements and acquisition planning, including potential use of 10 U.S.C. 2808a for facility construction or repair transactions outside the standard contract process.

Two forecasted projects are identified: a Maintenance Hangar at Hunter Army Airfield, Georgia (approximately 193,513 square feet), designed as a 10-module aircraft maintenance complex with integrated operations and support spaces; and a six-bay hangar with squadron operations facility at Moody Air Force Base, Georgia (approximately 105,000 square feet) for aircraft repair, inspection, and maintenance in a climate-controlled environment.

Respondents must submit a completed online survey and a capability statement in PDF format (single-spaced, 11-point font minimum) addressing corporate overview, commercial best practices, specialized systems integration, supply chain and logistics, materials and durability, and experience with collaborative delivery models such as Design-Build or Construction Manager at Risk. Capability statements should detail tension fabric structure design and construction experience, subcontractor qualifications, and how team involvement improved design quality, schedule, and cost on previous projects. Submit capability statements via email to Jennifer.L.Murphy@usace.army.mil and Sabrina.Bastine@usace.army.mil by October 23, 2026, at 5:00 PM. Clearly mark proprietary information on each page.

Notice text

Market Intelligence Notice – Hangar Construction (Hybrid Conventional and Tension Fabric Structures)

Disclaimer: This RFI is issued solely for information and planning purposes. It does not constitute a solicitation or a commitment to issue a solicitation in the future. The Government will not pay for any information or administrative costs incurred in response to this RFI.

1.0 Objective

The U.S. Army Corps of Engineers (USACE), Savannah District (SAS) is seeking market intelligence to identify and assess industry capabilities relevant to Tension Fabric Structures (TFS) and hybrid industrialized construction solutions for hangar facilities and similar large-span mission support applications. The Government is pursuing modern industrialized construction approaches intended to improve schedule, cost, and lifecycle outcomes for this facility type.

Information provided by respondents will be used to help the Government understand available market participants, solution types, and industry interest, and will inform future industry engagements, acquisition planning, and assessment of potential use of 10 U.S.C. § 2808a, Facility Construction or Repair: Transactions Other Than Contracts and Grants.

2.0 Forecasted Projects - Overview

 The following projects are currently projected for potential TFS or hybrid industrialized construction applications. USACE, SAS requires a highly resilient, energy-efficient operational hangar facility that can be rapidly constructed, scaled, and reconfigured as a tension-fabric structure. Solutions may be scaled for additional hangar facilities identified later.

  1. Maintenance Hangar, Hunter Army Airfield (HAAF), GA (approximately 193,513 square footage (SF)). Construction of a Large (10 Module) Standard Design Aircraft Maintenance Hangar Complex with integrated aviation maintenance operations, maintenance support, company operations, flight planning, flight operations spaces, Ground Support Equipment (GSE) covered storage, Associated Support Items of Equipment (ASIOE) covered storage, Petroleum, Oil, and Lubricants (POL) and Hazardous Material (HAZMAT) storage, hangar access and wash aprons. Project also includes fire protection and alarm systems, information systems, Intrusion Detection System (IDS) installation, closed circuit television connection, cybersecurity measures, and Energy Monitoring Control Systems (EMCS) connection. Supporting facilities include site development, utilities and connections, exterior lighting, paving, POV parking, walks, storm drainage, information systems, landscaping and signage. Heating and air conditioning will be provided by self-contained system.
  2. Moody Air Force Base, GA (approximately 105,000 SF). Construction of an adequately sized six-bay hangar and squadron operations facility.  The squadron operations section of the facility shall incorporate mission planning, life support, and squadron admin space. The aircraft maintenance section shall be designed to optimize maintenance administration for the squadron. The hangar bays will provide space to support aircraft repair and inspection, engine changes, and other activities that must be accomplished in a secure, climate-controlled environment.  The hangar space must be sized to accommodate movement and placement of maintenance equipment around the aircraft and systems supporting the aircraft.

 3.0 Requested Information & Market Intelligence Questionnaire

Section - General Information

Provide responses to the survey linked herein.  https://forms.osi.apps.mil/r/8B5GPKqrMh

Section - Capabilities

Respondents are asked to structure Capability Statements to include the following elements:

  1. Corporate Overview - A brief summary of your firm's core capabilities, relevant experience, and capacity to perform the type of work contemplated under this RFI.   
  2. Commercial Best Practices. To the extent available, provide information regarding commercial best practices applicable to the contemplated construction delivery method, including:
  • Typical pricing/payment structures
  • Geographic coverage
  • Typical project schedule timelines, long lead items, and key decision points
  • Key considerations and risk associated with  permitting, logistics, staffing/labor availability, and construction execution.
  • Specialized Systems Integration: Describe your experience integrating specialized hangar systems, such as high-capacity cranes, fall protection systems, and high-expansion foam fire suppression systems, within a tension fabric structure.
  • Supply Chain and Logistics: Describe your supply chain for key components of the tension fabric structure.  What are your typical lead times for material and fabrication?
  • Materials and Durability: What specific materials, coatings, and structural frame materials do you typically use for facilities of this type and in a coastal environment?  What is the expected design life and warranty period for these components?

        3. Survey Responses – Please provide detailed responses to Survey Questions 10 through 12 (listed below and on the survey form). Respondents are asked to integrate these responses directly into their capability statements; separate or stand-alone survey responses are not required. Additional Information – Respondents may include other information that demonstrates their relevant capabilities, experience, and capacity. Examples include:

  • Photos of TFS projects ;
  • Smart Building Technologies (e.g., automated controls, sensors, energy management systems, fire protection and alarm systems, information systems, Intrusion Detection System (IDS) installation, closed circuit television connection, cybersecurity measures, and Energy Monitoring Control Systems (EMCS) connection.)
  • Advanced HVAC Systems (e.g., high-efficiency climate control, specialized filtration)

Survey Questions 10-12

10.   Describe your experience or capability in designing and constructing tension-fabric structures that could innovate and accelerate construction.

11.  Describe your firm’s practical experience with collaborative delivery models, such as Design-Build, Progressive Design-Build or Construction Manager at Risk (CMAR), where your team was integrated into the design phase. What specific pre-construction services did you provide?

12.  For the projects listed in response to Q11, identify the major subcontractor(s) used and describe their qualifications. Detail the teaming relationship and contract structure between the construction contractor, the owner, and the Designer of Record. Explain how your team's involvement improved the final design quality, accelerated the delivery schedule, and reduced overall project cost.

4.0 Response Submission Instructions

  • Format: Responses to the survey must be submitted via the link provided.  The capability statement must be submitted in PDF format, single-spaced, using 11-point font or larger.
  • Submission Deadline: October 23, 2026 – 5:00 PM
  • Submission Channel: Complete the survey at https://forms.osi.apps.mil/r/8B5GPKqrMh
  • Submit capability statement via email to the Agreement Officer (AO) at Jennifer.L.Murphy@usace.army.mil and copy Sabrina.Bastine@usace.army.mil with the subject line: "USACE OTA Market Intelligence Response TFS - [Company Name]".
  • Proprietary Information: Any proprietary, sensitive, or business-confidential information must be clearly marked as such on each page to ensure proper handling by USACE SAS.

Files

File Type Posted
Request for Information Notice TSF.docx DOCX document

Similar open opportunities

Opportunity Agency Set-aside Responses due
RFI: Fort Wolters H Barracks Mineral Wells, Texas 76067, United States · NAICS 236220 ENDIST Fort Worth No set-aside
Sources Sought - Construction Repair Building 6413 Secure Space (511669 & 519580) Barksdale AFB Barksdale AFB, Louisiana 71110, United States · NAICS 236220 ENDIST Fort Worth No set-aside
Market Intelligence Notice – Child Development Centers (CDC) - Volumetric modular housing, Kit-of-Parts facilities, 3-D Printed Savannah, Georgia, United States ENDIST Savannah No set-aside
Request for Information for On-Site Fabrication and Assembly of a Three-Bay High-Performance Magazine (HPM) Structure Fort Polk, Louisiana 71459, United States · NAICS 238120 Engineer Research and Development Center No set-aside
REQUEST FOR INFORMATION (RFI) / MARKET RESEARCH NOTICE RELATED TO SEVERAL UPCOMING PROJECTS at WRIGHT-PATTERSON AFB, OHIO Wright Patterson AFB, Ohio 45433, United States · NAICS 236220 ENDIST Louisville No set-aside