Maintenance, Repair or Alteration of Real Property
Award Notice Posted
- Solicitation number
- N4008413R0101
- Agency
-
Naval Facilities Engineering Command
Department of the Navy, Department of Defense
- Awarded
- to Meccs-Urayasu Joint Venture
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- N4008414C0107 Federal contract award
- NAICS code
- 236118 Residential Remodelers
- PSC
- Not on record
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
The project will perform whole house revitalization of existing five buildings (Bldg 4315, 4317, 4321, 4322 and 4323) in Yokosuka, Japan. This project also includes replacement of existing mechanical and electrical equipments in three mechanical equipment facilities (Bldg 4316, 4318, and 4325). The work includes the miscellaneous repairs, improvements, painting, removal and disposal of materials, clean-up, and related miscellaneous work. The project provides a complete and usable facility.
The Contractor shlla be required to complete the entire work, ready for use, not later than 586 calendar days including the mailing period after the date of Award. The mailing period includes the days for mailing of the Notice of Award and the submission of the required bonds and Certificate of Insurance.
The time for completion shall include final clean up of the premises. Completion schedule for design preparation is 138 days after date of award and on-site construction shall be completed 448 days after completion of design, total contract term is 586 calendar days.
The complete soliciatation package will be posted around 2 May 2013.
Update #1 ·
The project will perform whole house revitalization of existing five buildings (BLDG 4315, 4317, 4321, 4322 and 4323) in Yokosuka, Japan. This project also includes replacement of existing mechnical and electrical equipments in three mechanical equipment facilities (BLDG 4316, 4318, and 4325). The work includes the miscellaneous repairs, improvements, painting, removal and disposal of materials, clean-up, and related miscellaneous work. The project provides a complete and usable facility.
The Contractor shall be required to complete the entire work, ready for use, not later than 586 calendar days including the mailing period after the date of Award. The mailing period includes the days for mailing of the Notice of Award and the submission of the required bonds and Certificate of Insurance.
The time for completion shall include final clean up of the premises. Completion schedule for design preparation is 138 days after date of award and on-site construction shall be completed 448 days after completion of design, total contract term is 586 calendar days.
The complete solicitation package will be posted around 25 April 2013, Japan time.