La Mina and Big Tree Trail Rehabilitation Construction Project
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 12445222R0011
- Agency
-
Forest Service
Department of Agriculture
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Forest Service is soliciting offers for a single award, firm-fixed price construction contract valued between $1,000,000 to $5,000,000. The scope of work includes rehabilitation of the La Mina and Big Tree trails located in El Yunque National Forest, Puerto Rico and consists of construction surveying, erosion control measures, clearing and grubbing, constructing and rehabilitating trails, stairs, interpretive sites and bridges, installing culverts, constructing retaining walls, drainage features, and underdrain systems. Proposals are due April 25, 2022 in response to a forthcoming solicitation. Offerors must meet small business qualifications and evaluation will be based on past performance, technical approach, experience, bonding capacity, and pricing.
This opportunity is set aside for total small businesses under NAICS codes 237990 and 237310. The current contractor is unknown. Work will be performed over an 18 month period within the boundaries of the La Mina and Big Tree Trails Forest Recreation Area in El Yunque National Forest, Puerto Rico.
Notice text
3 versions
Update #3 · Latest ·
Update 3/24/2022: The purpose of this update is to incorporate Amendment P00001 into the solicitation. All other terms and conditions remain the same.
Update 3/17/2021: An amendment to the solicitation is forthcoming. The purpose of the amendment is to:
1. Revise the drawings to remove options.
2. Add two site visit dates and include a cutoff date for questionss
3. Extend the POP from 180 days to 18 monnths
//break//
The U.S. Forest Service is soliciting offers for a single award, firm-fixed price contract type with an estimated magnitude for the base and options between $1,000,000 and $5,000,000. The Government anticipates awarding a sole contract for La Mina and Big Tree Trail Rehabilitation Construction Project located in El Yunque National Forest, Puerto Rico. Additional awards, at Forest Service discretion, may be considered depending on Forest Service need and results for proposal evaluations. Prospective offerors are required to submit proposals in accordance with the forthcoming solicitation.
This will be set aside for total small businesses.
Scope of Work:
This work shall consist of: construction surveying and staking, erosion control measures, silt fencing and dewatering structures installation and removal after final acceptance, clearing and grubbing, the removal and resetting of historic rocks/stones located on the boundary of the trail surface, constructing trail widening, constructing trail passing areas, restoration of existing stairs, construction of new stairs, and reconstruction of damaged stairs, constructing new and rehabilitating existing interpretive sites, excavation, geotextile placement, constructing masonry walls with foundations, constructing and erecting new gabion baskets, trail re-surfacing, installing (1) culvert, constructing one (1) mechanically stabilized earth (MSE) wall, constructing open drainages, constructing underdrain systems, removal and demolition of existing bridges and individual tree(s) as specified in drawings, removal of existing invasive plant species, tree planting and mulching, riprap armoring, placing and colored grouted riprap, constructing two (2) new trail bridges and rehabilitating one (1) existing trail bridge #11, removal, replacement, and constructing bridge guardrails, removal, replacement, and constructing trail handrails, removal, replacement, and constructing stair handrails, demolition and disposal of identified existing shelters, hauling off of excessive excavated and accumulated sediment material, and contractor testing of materials.
Location(s):
La Mina Trail Head Coordinates: 18.30055556, -65.78444444
La Mina Falls Bridge #11 Coordinates: 18.30327, -65.77699
Big Tree Trail Head Coordinates: 18.308866, -65.775056
All work within this solicitation will be located on the El Yunque National Forest which is approx. 6.90 miles (11.1 Km) south of Rio Grande, Puerto Rico. All construction is within the El Yunque National Forest boundaries within the La Mina and Big Tree Trail’s Forest Recreation Area sites and trails. A vicinity and project location map are provided and enclosed in the attached solicitation drawings.
Disclaimer:
This notice does not commit the Government to contract for any supply or service. Respondents are advised that the United States (U.S.) Government will not pay for any information or administrative cost incurred in response to this notice. All costs associated with responding to this notice will be solely at the responding party's expense.
Please be advised that all submissions become Government property and will not be returned. Responses to this notice are not offers and cannot be accepted by the U.S Government to form a binding contract.
Submit questions and/or concerns to:
Edward McKee, Contracting Officer
edward.mckeejr@usda.gov
and
Jose Gutierrez, Contract Specialist
jose.gutierrez4@usda.gov
Update #2 ·
Update 3/17/2021: An amendment to the solicitation is forthcoming. The purpose of the amendment is to:
1. Revise the drawings to remove options.
2. Add two site visit dates and include a cutoff date for questionss
3. Extend the POP from 180 days to 18 monnths
//break//
The U.S. Forest Service is soliciting offers for a single award, firm-fixed price contract type with an estimated magnitude for the base and options between $1,000,000 and $5,000,000. The Government anticipates awarding a sole contract for La Mina and Big Tree Trail Rehabilitation Construction Project located in El Yunque National Forest, Puerto Rico. Additional awards, at Forest Service discretion, may be considered depending on Forest Service need and results for proposal evaluations. Prospective offerors are required to submit proposals in accordance with the forthcoming solicitation.
This will be set aside for total small businesses.
Scope of Work:
This work shall consist of: construction surveying and staking, erosion control measures, silt fencing and dewatering structures installation and removal after final acceptance, clearing and grubbing, the removal and resetting of historic rocks/stones located on the boundary of the trail surface, constructing trail widening, constructing trail passing areas, restoration of existing stairs, construction of new stairs, and reconstruction of damaged stairs, constructing new and rehabilitating existing interpretive sites, excavation, geotextile placement, constructing masonry walls with foundations, constructing and erecting new gabion baskets, trail re-surfacing, installing (1) culvert, constructing one (1) mechanically stabilized earth (MSE) wall, constructing open drainages, constructing underdrain systems, removal and demolition of existing bridges and individual tree(s) as specified in drawings, removal of existing invasive plant species, tree planting and mulching, riprap armoring, placing and colored grouted riprap, constructing two (2) new trail bridges and rehabilitating one (1) existing trail bridge #11, removal, replacement, and constructing bridge guardrails, removal, replacement, and constructing trail handrails, removal, replacement, and constructing stair handrails, demolition and disposal of identified existing shelters, hauling off of excessive excavated and accumulated sediment material, and contractor testing of materials.
Location(s):
La Mina Trail Head Coordinates: 18.30055556, -65.78444444
La Mina Falls Bridge #11 Coordinates: 18.30327, -65.77699
Big Tree Trail Head Coordinates: 18.308866, -65.775056
All work within this solicitation will be located on the El Yunque National Forest which is approx. 6.90 miles (11.1 Km) south of Rio Grande, Puerto Rico. All construction is within the El Yunque National Forest boundaries within the La Mina and Big Tree Trail’s Forest Recreation Area sites and trails. A vicinity and project location map are provided and enclosed in the attached solicitation drawings.
Disclaimer:
This notice does not commit the Government to contract for any supply or service. Respondents are advised that the United States (U.S.) Government will not pay for any information or administrative cost incurred in response to this notice. All costs associated with responding to this notice will be solely at the responding party's expense.
Please be advised that all submissions become Government property and will not be returned. Responses to this notice are not offers and cannot be accepted by the U.S Government to form a binding contract.
Submit questions and/or concerns to:
Edward McKee, Contracting Officer
edward.mckeejr@usda.gov
and
Jose Gutierrez, Contract Specialist
jose.gutierrez4@usda.gov
Update #1 ·
The U.S. Forest Service is soliciting offers for a single award, firm-fixed price contract type with an estimated magnitude for the base and options between $1,000,000 and $5,000,000. The Government anticipates awarding a sole contract for La Mina and Big Tree Trail Rehabilitation Construction Project located in El Yunque National Forest, Puerto Rico. Additional awards, at Forest Service discretion, may be considered depending on Forest Service need and results for proposal evaluations. Prospective offerors are required to submit proposals in accordance with the forthcoming solicitation.
This will be set aside for total small businesses.
Scope of Work:
This work shall consist of: construction surveying and staking, erosion control measures, silt fencing and dewatering structures installation and removal after final acceptance, clearing and grubbing, the removal and resetting of historic rocks/stones located on the boundary of the trail surface, constructing trail widening, constructing trail passing areas, restoration of existing stairs, construction of new stairs, and reconstruction of damaged stairs, constructing new and rehabilitating existing interpretive sites, excavation, geotextile placement, constructing masonry walls with foundations, constructing and erecting new gabion baskets, trail re-surfacing, installing (1) culvert, constructing one (1) mechanically stabilized earth (MSE) wall, constructing open drainages, constructing underdrain systems, removal and demolition of existing bridges and individual tree(s) as specified in drawings, removal of existing invasive plant species, tree planting and mulching, riprap armoring, placing and colored grouted riprap, constructing two (2) new trail bridges and rehabilitating one (1) existing trail bridge #11, removal, replacement, and constructing bridge guardrails, removal, replacement, and constructing trail handrails, removal, replacement, and constructing stair handrails, demolition and disposal of identified existing shelters, hauling off of excessive excavated and accumulated sediment material, and contractor testing of materials.
Location(s):
La Mina Trail Head Coordinates: 18.30055556, -65.78444444
La Mina Falls Bridge #11 Coordinates: 18.30327, -65.77699
Big Tree Trail Head Coordinates: 18.308866, -65.775056
All work within this solicitation will be located on the El Yunque National Forest which is approx. 6.90 miles (11.1 Km) south of Rio Grande, Puerto Rico. All construction is within the El Yunque National Forest boundaries within the La Mina and Big Tree Trail’s Forest Recreation Area sites and trails. A vicinity and project location map are provided and enclosed in the attached solicitation drawings.
Disclaimer:
This notice does not commit the Government to contract for any supply or service. Respondents are advised that the United States (U.S.) Government will not pay for any information or administrative cost incurred in response to this notice. All costs associated with responding to this notice will be solely at the responding party's expense.
Please be advised that all submissions become Government property and will not be returned. Responses to this notice are not offers and cannot be accepted by the U.S Government to form a binding contract.
Submit questions and/or concerns to:
Edward McKee, Contracting Officer
edward.mckeejr@usda.gov
and
Jose Gutierrez, Contract Specialist
jose.gutierrez4@usda.gov
Files
Notice history
| Notice | Type | Posted |
|---|---|---|
| La Mina and Big Tree Trail Rehabilitation Construction Project | Award Notice | |
| This notice | Solicitation | |
| La Mina and Big Tree Trail Rehabilitation Construction Project | Pre-Solicitation |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity