John W. Keys III Pump-Generating Plant Discharge Tube Coating-Lining Rehabilita
Closed Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- 140R1020R0003
- Agency
-
Bureau of Reclamation
Department of the Interior
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237110 Water and Sewer Line and Related Structures Construction
- More information
Notice details come from SAM.gov. Updated .
About this opportunity
This pre-solicitation notice is for rehabilitation services at the John W. Keys III Pump-Generating Plant located in Washington. The Bureau of Reclamation seeks to reline, recoat, and perform necessary repairs to the discharge tubes, spiral cases, draft/suction tubes, and embedded piping systems for six pump units and six pump-generating units. The work is expected to have a period of performance of 56 months. The solicitation will be issued on November 25, 2019 and available at www.fedconnect.net. Proposals will be due by May 8, 2020.
The procurement has a NAICS code of 237110 with a $39.5 million small business size standard and is set aside for small businesses. The order of magnitude is estimated between $25-50 million. Work will include complete removal and replacement of linings and coatings for the interior and exterior discharge tubes, repacking of expansion joints, repairs to cavitation and corrosion, and replacement of sections of the discharge tube unwatering lines.
Notice text
3 versions
Update #3 · Latest ·
Synopsis for Solicitation 140R1020R0003:
Updated 14 Apr 20: As a note to interested offerors. The previous versions of the presolicitation notice did anticipate this requirement would be a small business set-aside however, as the acquisition process progressed the determination was made in the best interest of the Government to compete as full and open once the solicitation was posted.
The Bureau of Reclamation (BOR), Pacific Northwest Region, John W. Keys III Pumping Plant at Grand Coulee Dam, adjacent to the Cities of Grand Coulee and Coulee Dam, Washington, approximately 90 miles west of Spokane, Washington, in Grant and Okanogan Counties, has a need for construction services for the Pump-Generating Plant Discharge Tube Coating-Lining Rehabilitation. This requirement will include:
The Grand Coulee Pump-Generating Plant contains twelve pumps that lift water from the Columbia River up the hillside through discharge tubes to a canal that flows into Banks Lake, which provides irrigation water to over 670,000 acres in the Columbia Basin Project. Six of the pumps can then be reversed to generate hydroelectric when demand exists. Work will be composed of the following:
1. Complete lining removal and replacement (re-lining) of the discharge tube interior upper slope sections for Pump-Generating (PG) units PG7-PG12.
2. Repacking of expansion joints on upper slopes for PG7-PG12.
a. Includes:
1) Disassembly and testing of expansion joints for asbestos.
2) Disposal of existing joint material.
3) Installation of New expansion joint material.
3. Complete removal and replacement (re-coating) of the upper slope discharge tube exteriors for PG7-PG12, including non-skid coating on pipe crown.
4. Complete removal and replacement (re-coating) of the discharge tube exteriors inside pumping plant for Pump (P) units P1-P6 and PG7-PG12.
5. Complete removal and replacement (re-lining) for the lower slope and bottom portions discharge tubes of P1-P6 and PG7-PG12.
6. Complete removal and replacement (re-lining) of the spiral cases of P1-P6 and PG7-PG12 including cavitation and corrosion repairs as necessary.
7. Complete removal and replacement (re-lining) of the draft/suction tubes for P1-P6 and PG7-PG12.
8. Complete removal and replacement (re-lining) of embedded small diameter piping systems: Bypass piping, air vent piping, draft tube unwatering line, discharge tube unwatering line for P1-P6 and PG7-PG12.
9. P1-P6 and PG7-PG12: Replacement of exposed discharge tube unwatering line "S" sections and elbows in plant.
It is expected the period of performance (POP) will be 60 months. The North American Industry Classification System (NAICS) code associated with this project is 237110. The small business size standard applicable to this project is $39.5 million in gross annual receipts averaged over the previous three 1-year accounting periods. The order of magnitude for this project is between $25,000,000 and $50,000,000. Prospective contractors shall be registered in the System for Acquisition Management (SAM). For more information regarding registering in SAM, please visit https://www.sam.gov/portal/public/SAM/. Contractors shall note that this procurement will be issued approximately November 25, 2019. When the solicitation is issued it will be available electronically at www.fedconnect.net.
Update #2 ·
Synopsis for Solicitation 140R1020R0003:
The Bureau of Reclamation (BOR), Pacific Northwest Region, John W. Keys III Pumping Plant at Grand Coulee Dam, adjacent to the Cities of Grand Coulee and Coulee Dam, Washington, approximately 90 miles west of Spokane, Washington, in Grant and Okanogan Counties, has a need for construction services for the Pump-Generating Plant Discharge Tube Coating-Lining Rehabilitation. This requirement will include:
The Grand Coulee Pump-Generating Plant contains twelve pumps that lift water from the Columbia River up the hillside through discharge tubes to a canal that flows into Banks Lake, which provides irrigation water to over 670,000 acres in the Columbia Basin Project. Six of the pumps can then be reversed to generate hydroelectric when demand exists. Work will be composed of the following:
1. Complete lining removal and replacement (re-lining) of the discharge tube interior upper slope sections for Pump-Generating (PG) units PG7-PG12.
2. Repacking of expansion joints on upper slopes for PG7-PG12.
a. Includes:
1) Disassembly and testing of expansion joints for asbestos.
2) Disposal of existing joint material.
3) Installation of New expansion joint material.
3. Complete removal and replacement (re-coating) of the upper slope discharge tube exteriors for PG7-PG12, including non-skid coating on pipe crown.
4. Complete removal and replacement (re-coating) of the discharge tube exteriors inside pumping plant for Pump (P) units P1-P6 and PG7-PG12.
5. Complete removal and replacement (re-lining) for the lower slope and bottom portions discharge tubes of P1-P6 and PG7-PG12.
6. Complete removal and replacement (re-lining) of the spiral cases of P1-P6 and PG7-PG12 including cavitation and corrosion repairs as necessary.
7. Complete removal and replacement (re-lining) of the draft/suction tubes for P1-P6 and PG7-PG12.
8. Complete removal and replacement (re-lining) of embedded small diameter piping systems: Bypass piping, air vent piping, draft tube unwatering line, discharge tube unwatering line for P1-P6 and PG7-PG12.
9. P1-P6 and PG7-PG12: Replacement of exposed discharge tube unwatering line "S" sections and elbows in plant.
It is expected the period of performance (POP) will be 60 months. The North American Industry Classification System (NAICS) code associated with this project is 237110. The small business size standard applicable to this project is $39.5 million in gross annual receipts averaged over the previous three 1-year accounting periods. The order of magnitude for this project is between $25,000,000 and $50,000,000. This procurement is limited to small business concerns. Prospective contractors shall be registered in the System for Acquisition Management (SAM). For more information regarding registering in SAM, please visit https://www.sam.gov/portal/public/SAM/. Contractors shall note that this procurement will be issued approximately November 25, 2019. When the solicitation is issued it will be available electronically at www.fedconnect.net.
Update #1 ·
Synopsis for Solicitation 140R1020R0003:
The Bureau of Reclamation (BOR), Pacific Northwest Region, John W. Keys III Pumping Plant at Grand Coulee Dam, adjacent to the Cities of Grand Coulee and Coulee Dam, Washington, approximately 90 miles west of Spokane, Washington, in Grant and Okanogan Counties, has a need for construction services for the Pump-Generating Plant Discharge Tube Coating-Lining Rehabilitation. This requirement will include:
The Grand Coulee Pump-Generating Plant contains twelve pumps that lift water from the Columbia River up the hillside through discharge tubes to a canal that flows into Banks Lake, which provides irrigation water to over 670,000 acres in the Columbia Basin Project. Six of the pumps can then be reversed to generate hydroelectric when demand exists. Work will be composed of the following:
1. Complete lining removal and replacement (re-lining) of the discharge tube interior upper slope sections for Pump-Generating (PG) units PG7-PG12.
2. Repacking of expansion joints on upper slopes for PG7-PG12.
a. Includes:
1) Disassembly and testing of expansion joints for asbestos.
2) Disposal of existing joint material.
3) Installation of New expansion joint material.
3. Complete removal and replacement (re-coating) of the upper slope discharge tube exteriors for PG7-PG12, including non-skid coating on pipe crown.
4. Complete removal and replacement (re-coating) of the discharge tube exteriors inside pumping plant for Pump (P) units P1-P6 and PG7-PG12.
5. Complete removal and replacement (re-lining) for the lower slope and bottom portions discharge tubes of P1-P6 and PG7-PG12.
6. Complete removal and replacement (re-lining) of the spiral cases of P1-P6 and PG7-PG12 including cavitation and corrosion repairs as necessary.
7. Complete removal and replacement (re-lining) of the draft/suction tubes for P1-P6 and PG7-PG12.
8. Complete removal and replacement (re-lining) of embedded small diameter piping systems: Bypass piping, air vent piping, draft tube unwatering line, discharge tube unwatering line for P1-P6 and PG7-PG12.
9. P1-P6 and PG7-PG12: Replacement of exposed discharge tube unwatering line “S†sections and elbows in plant.
It is expected the period of performance (POP) will be 56 months. The North American Industry Classification System (NAICS) code associated with this project is 237110. The small business size standard applicable to this project is $39.5 million in gross annual receipts averaged over the previous three 1-year accounting periods. The order of magnitude for this project is between $25,000,000 and $50,000,000. This procurement is limited to small business concerns. Prospective contractors shall be registered in the System for Acquisition Management (SAM). For more information regarding registering in SAM, please visit https://www.sam.gov/portal/public/SAM/. Contractors shall note that this procurement will be issued approximately November 25, 2019. When the solicitation is issued it will be available electronically at www.fedconnect.net.
Notice history
| Notice | Type | Posted |
|---|---|---|
| John W. Keys III Pump-Generating Plant Discharge T | Award Notice | |
| John W. Keys III Pump-Generating Plant Discharge T | Solicitation | |
| This notice | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Bonneville Powerhouse II Unwatering Pump Replacement | ENDIST Portland | Total Small Business | |
| East Bear Creek Pumping Plant and Pipeline Moderni | — | No set-aside | |
| PIP-II F-37 building LWC pump room piping system installation | Fermi National Accelerator Laboratory | No set-aside | |
| LLA Navigation Lock Switchgear | ENDIST Walla Walla | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity