John w. Keys III pump-generating plant discharge tube coating-lining rehabilitation

Active Definitive Contract Awarded Last action

Contract number
140R1020C0012
Awardee
Awarding agency
Obligated
$37,517,967

Award facts

Opportunity
Contract value 99% obligated
  • $37,726,650.97 Current, with exercised options
  • $37,867,050.97 Potential, with all options
Completion date 95% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 2 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Grand Coulee, WA 99133, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action P00052 · CO change $0
Change Order P00051 · MOD P051 P5 & P6 abatement & recoat. $2,877,831
Supplemental Agreement for work within scope P00050 · MOD P050 no cost time extension. $0
Supplemental Agreement for work within scope P00049 · MOD P049 REA coating material increase PG7. $70,461
Supplemental Agreement for work within scope P00047 · The purpose of this modification is REA VEQ cavitation overrun PG9. $460,544
Supplemental Agreement for work within scope P00045 $255,972
Definitize Change Order P00044 · The purpose of this modification is to definitize P00037 TAR abatement. -$145,581
Funding Only Action P00043 $7,677,365
Other Administrative Action P00042 $0
Supplemental Agreement for work within scope P00041 $109,016
Supplemental Agreement for work within scope P00040 $2,056
Supplemental Agreement for work within scope P00039 -$105,884
Supplemental Agreement for work within scope P00038 $538,672
Change Order P00037 $417,000
Definitize Change Order P00036 -$28,657
Supplemental Agreement for work within scope P00035 $556,148
Funding Only Action P00034 $828,695
Change Order P00033 $85,000
Supplemental Agreement for work within scope P00032 $0
Definitize Change Order P00031 -$2,353
Funding Only Action P00030 · 140R1020C0012 john w. Keys III pump-generating plant discharge tube coating-lining rehabilitation: incremental funding modification PG11 & PG12 $5,897,961
Supplemental Agreement for work within scope P00029 $53,194
Change Order P00028 $10,000
Supplemental Agreement for work within scope P00027 $30,807
Supplemental Agreement for work within scope P00026 $7,820
Supplemental Agreement for work within scope P00025 $12,030
Funding Only Action P00024 $4,339,749
Supplemental Agreement for work within scope P00023 $147,155
Supplemental Agreement for work within scope P00022 $499,608
Supplemental Agreement for work within scope P00021 $1,555
Funding Only Action P00020 $2,927,944
Supplemental Agreement for work within scope P00019 $25,369
Supplemental Agreement for work within scope P00018 $0
Supplemental Agreement for work within scope P00017 $89,952
Supplemental Agreement for work within scope P00016 $222,063
Definitize Change Order P00015 $0
Supplemental Agreement for work within scope P00014 $0
Funding Only Action P00013 $4,569,911
Supplemental Agreement for work within scope P00012 $20,755
Supplemental Agreement for work within scope P00011 $227,569
Supplemental Agreement for work within scope P00010 $0
Supplemental Agreement for work within scope P00009 $7,081
Change Order P00007 $1,616,887
Supplemental Agreement for work within scope P00006 $0
Change Order P00005 $0
Supplemental Agreement for work within scope P00004 $0
Supplemental Agreement for work within scope P00003 $0
Other Administrative Action P00002 $0
Supplemental Agreement for work within scope P00001 $76,368
Supplemental Agreement for work within scope P00008 $2,837
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

The Department of Interior, Bureau of Reclamation awarded a $37.9 million firm fixed-price definitive contract to Hartman-Walsh Painting Company for discharge tube coating-lining rehabilitation at the John W. Keys III Pump-Generating Plant on September 1, 2020, with no set-aside.

The originating pre-solicitation, posted November 1, 2019, sought relining, recoating, and repairs to discharge tubes, spiral cases, draft and suction tubes, and embedded piping systems for six pump units and six pump-generating units at the plant in Grand Coulee, Washington. Work includes complete removal and replacement of linings and coatings on interior and exterior discharge tubes, repacking of expansion joints, repairs to cavitation and corrosion, and replacement of discharge tube unwatering line sections. Period of performance is 56 months, with an ultimate completion date of February 16, 2027. NAICS code 237110 applies. Through fiscal year 2022, Hartman-Walsh Painting Company invoiced $4.6 million across 3.7 FTEs and 7,597 contractor hours at a derived rate of $602.25 per hour, self-performing all reported work with no subcontractors.

Quick answers

Who was awarded contract 140R1020C0012?

140R1020C0012 was awarded to Hartman-Walsh Painting Company by Departmental Offices (Department of the Interior) on September 1, 2020.

How much is contract 140R1020C0012 worth?

The government has obligated $37,517,967 on 140R1020C0012. Its current value, with exercised options, is $37,726,651. Its potential value, with all options, is $37,867,051.

Was contract 140R1020C0012 competed?

The extent of competition for 140R1020C0012 was full and open competition. The government received 2 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award