J062--Replace street light pole concrete bases Solicitation / Cancellation

Closed Solicitation Posted

Solicitation number
36C26326Q0712
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
St. Cloud VA Health Care System 4801 Veterans Drive St. Cloud MN 56303

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 23 issued a Small Business Set-Aside RFQ for replacement of streetlight pole concrete bases at St. Cloud VA Health Care System, with quotations originally due June 1, 2026, but the solicitation has been cancelled as of June 24, 2026 due to pricing that could not be evaluated as fair and reasonable; no award will be made.

Place of performance is St. Cloud, Minnesota (4801 Veterans Drive). The NAICS code is 238210 (Electrical Contractors and Other Wiring Installation Contractors); the PSC is J062. The statement of work required replacement of 26 existing streetlight pole concrete bases (30 feet high) with new bases 2-foot diameter by 8-foot-6-inch tubes set 6 feet below grade and 2 feet-6 inches above ground, with minimum compressive strength of 5,000 PSI after 14 days; replacement of approximately 7,600 feet of wiring between poles; replacement of light pole head feeds and fuses at 26 locations; and paint repair on approximately 31 light poles. All materials required copper cables only (aluminum cables prohibited). The contractor was required to maintain operational street lighting nightly throughout the project. The anticipated contract period was 90 calendar days from Notice to Proceed, with performance between July 1 and September 30, 2026. The Government budgeted $19 million for the contract award. A mandatory site visit was scheduled for May 26, 2026 at 10:00 AM CDT. Technical questions were due May 27, 2026 at 12:00 PM CDT. Evaluation criteria, in descending order of importance, were Technical Approach, Past Performance (three relevant projects within the last six years), and Price. All offerors were required to be registered and current in SAM at time of submission.

Notice text

4 versions

Update #4 · Latest ·

Amendment of Solicitation / Cancellation

Update #3 ·

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the

offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY

is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not,

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter

or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to

the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print)

(Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign)

(Signature of Contracting Officer)

1

4

0002

05-28-2026

None

36C263

DEPARTMENT OF VETERANS AFFAIRS

NETWORK CONTRACTING OFFICE 23

316 ROBERT STREET N, SUITE 506

SAINT PAUL MN 55101

36C263

DEPARTMENT OF VETERANS AFFAIRS

NETWORK CONTRACTING OFFICE 23

316 ROBERT STREET N, SUITE 506

SAINT PAUL MN 55101

To all Offerors/Bidders

36C26326Q0712

X

X

X

X

1

The purpose of the amendment is to provide answers to interested vendor questions.

See continuation pages

Curt LaRose

Contracting Officer

CONTINUATION PAGE

Q1. There is a discrepancy in the SOW. On page 5 of the Solicitation, under New Light Pole concrete base, paragraph 1, it states that a 3/4 thick grounding rod is to be used. On page 6 of the Solicitation, under Material Components, paragraph 5, it states that a 5/8 thick grounding rod to be used. What is the size that you are asking to be used?

A1. Answer: 5/8 thick grounding rod, as stated in the Material Components section, is the correct size.

Q2. On light pole 1-10 there is an additional box attached to it. What s in the box and does it require special treatment?

A2. Answer: The box contains chains to barricade the adjacent road if needed. No electricity in the box. Paint as needed.

Q3. The Overview, paragraph 2, of the SOW states that there are approximately 31 light poles that require paint repair, not entire repaint. There are 26 poles that have the bases being replaced that are identified. Please confirm that those same 26 are the ones that require paint repair and identify the five (5) additional poles require this paint.

A3. Answer: For the 26 poles receiving new concrete bases; re-paint/rust repair treatment shall be required for the entire pole (including its breakaway base), and re-stencil with its corresponding pole ID number.

For the other 17 poles, affected by this project, but not receiving a new concrete base, they will be required to receive re-paint/rust repair treatment (touched up), where needed. Re-stencil with its corresponding pole ID number if necessary.

Q4. To what extent must the poles be painted? Is the expectation to remove rust and flaking old paint and re-paint the entire pole?

A4. Answer: Refer to the answer A3.

Q5. It was stated at the site visit that there might be conduit in the poles that is metal and not PVC. The Solicitation states on page five (5) under the New Light Pole concrete base section in paragraph 2, Conduit installed and the conductors shall be the same size and type as the ones removed. Please confirm that you want these to be replaced with PVC conduit and that PVC is to be used on all. That wiring being replaced is to be the same size and type but will likely need to be longer than existing to accommodate the taller light pole bases.

A5. Answer: Yes. PVC is to be the material to be used for the new concrete base conduits.

Q6. Do you know how deep the current bases extend into the ground?

A6. Answer: The current depth of the existing concrete bases is unknown.

Q7. Can you identify what type of surface is around light poles that need to be replaced and how many of each type (Grass/lawn, Asphalt, Concrete, Gravel)?

A7. Answer: The surface around the light poles is grass/lawn, except pole 113-8 which is asphalt pavement.

Q8. Please confirm that work and updates to wiring within the light pole will be completed by the VA in the time that the pole is downed, while the old base is removed and the new base is being created & cured.

A8. Answer: Yes. The VA will perform this work.

Q9. Please confirm that all light poles and break-away bases are intended to be re-used.

A9. Answer: Yes. All the light poles and break-away bases are intended to be re-used.

Q10. To what extent is the contractor expected to restore the grass/lawn in the affected area?

A10. Answer: The contractor is expected restore the surface around the pole with in kind materials.

Q11. There is indicated 26 bases needing replacement and 31 poles to touch-up. Are the 31 poles in addition to the 26 base replacement count for a total of 57 poles?

A11. Answer: Refer to the answer A3.

Q12. The poles can be placed proximal to the removed bases. Can they be painted or touched up at that same location or moved to an on-site lay down area?

A12. Answer: Yes.

Q13. Will fencing be required at each base when performing work? Steel or orange fence?

A13. Answer: Yes. An orange snow fence can be used.

Q14. Will concrete testing be required?

A14. Answer: Yes. The Contractor is required to do the concrete testing, as per your structural engineer of record recommendations.

Q15. Will a structural engineer be required for the base construction?

A 15. Answer: Yes.

Q16. Bullet point a page 5 of the 41 page RFP indicates to re-pull conductors if in good condition . Does this mean some existing conductors be used at other locations? Or all conductors must be new?

A16. Answer: All underground conductors should be replaced with new. Above ground conductors inside pole can be reused, if in good condition.

Q17. If precast bases are employed are there any special tamping requirements?

A17. Answer: This will be as per your structural engineer of record recommendations.

Q18. There is no reference to a bid bond/bonds. Will these be required and if so, is there is magnitude for the overall project?

A18. Answer: No bid bond/bonds.

Q19. We would like to know if this is a brand new contract OR if there is (was) an incumbent performing these services. If not brand new, could you please provide the current / previous contract number?

A19. Answer: This project is a new contract.

Q20. We are looking to verify whether or not this RFQ is only to be bid on by SBE/DBE companies or if all responses will be considered. I am referring to small or disadvantaged businesses as the below statement is outlined on page 40 of the RFQ provided for this project.

A20. Answer: This requirement is a Small Business Set-Aside.

Q21. Could you kindly email me the list of GC bidders or plan holders for this project? Alternatively, if you could direct me to someone who would have this information, please let me know.

A21. Answer: We do not have a list of G.C. bidders or plan holders for this project.

Q22. We would like to know if this is a brand new contract OR if there is (was) an incumbent performing these services.

If not brand new, could you please provide the current / previous contract number?

A22. Answer: This is a new contract

Provide answers to interested vendors questions

Update #2 ·

Update the site visit attendance due date and time. See attached Document

Update #1 ·

RFQ Replace existing streetlight pole concrete bases for St. Cloud VA Health Care System.

This is a combined synopsis/solicitation for commercial items.

This announcement constitutes the only solicitation information that is being requested.

Solicitation number 36C26326Q0712 is issued as a request for quotation (RFQ).

This procurement is a Small Business Set-Aside. Prospective offerors must be registered and current in the System for Award Management (SAM) database at time of offer to the Government (https://www.sam.gov).

Additional requirements are listed within the attached solicitation document.

Site Visit Information: May 26, 2026, at 10:00AM CDT at Facilities Management Office

Building 3, Second Floor

St. Cloud VA Health Care System

4801 Veterans Drive

St. Cloud, MN 56303

Conference Room 207C

POC: Mayda I. Vazquez Velez

Phone number: (320) 252-1670 x 7785

Technical questions on this solicitation are due via e-mail only to Safa Shleiwet, contract specialist at safa.shleiwet@va.gov no later than 12:00 PM Central Day Time (CDT), 05/27/2026.

Responses are due to the Contracting Office by 5:00 PM CDT, 06/01/2026. Responses are required to be emailed to safa.shleiwet@va.gov prior to the solicitation closing date and time. It is the responsibility of the offeror to ensure their quote is received in its entirety by the Contracting Officer before the solicitation closing.

Files

File Type Posted
36C26326Q0712 0003.docx DOCX document
SF 30 MOD.pdf PDF
36C26326Q0712 0002_1.docx DOCX document
36C26326Q0712 0001_1.docx DOCX document
AMENDMENT.pdf PDF
Wage Determination.pdf PDF
POLE BASE REPLACEMENT DET 1 - 20260506l.pdf PDF
RFQ 36C26326Q0712.pdf PDF
LPB-01 NORHT HALF LIGHT POLE BASE REPLACEMENT 20260506.pdf PDF
LPB-02 SOUTH HALF LIGHT POLE BASE REPLACEMENT 20260506.pdf PDF
36C26326Q0712_1.docx DOCX document
Show all 11

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity