ISP Upgrade
Closed Solicitation Posted
- Solicitation number
- F5N3SC0149AC01
- Agency
-
Reserve Command
Air Force, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 517311 Wired Telecommunications Carriers
- PSC
- D322 It And Telecom- Internet
- Place of performance
- Chicopee MA 01022 USA
Notice details come from SAM.gov. Updated .
Notice text
3 versions
Update #3 · Latest ·
September 3, 2020: Questions/Answers attached (End)
September 1, 2020: 1) The site visit is not required. 2) Building 1800 (Dmarc) is 800 Ellipse Dr, Chicopee MA. (End)
SEE ATTACHED COMPLETE COMBINED SYNOPSIS/SOLICITATION AND STATEMENT OF WORK
Description of Requirement: The Contractor shall provide all personnel, equipment, materials, supervision, transportation, labor, and other items and services necessary to provide commercial high-speed fiber internet service to Westover ARB that will include either connecting to existing Charter Communications fiber feed which is currently terminated in Building 1800 (Demarcation) or provide a new fiber feed to Building 1800 (Demarcation) utilizing the Westover Manhole Duct System. Government will provide fiber connection from Building 1800 (Demarcation) to Building 1510 where Contractor will install Router/Gateway device and Firewall to provide high-speed fiber internet at Westover ARB.
(See the attached PWS for additional details.)
Acquisition: The government will issue a single award, Firm Fixed Price contract with an estimated period of performance starting October 1, 2020 and ending March 30, 2026, base year plus 5 option periods.
SAM Registration: Prior to supplying a proposal, interested offerors must have an active registration in the System for Award Management (SAM). Firms can register via the SAM internet web-site at https://www.sam.gov/SAM/.
Milestone Dates :
August 19, 2020 11AM EST - Register for Site visit (see COVID restrictions)
August 26, 2020 11AM EST – Site Visit
September 3, 2020 11AM EST – *Question Period ends
September 9, 2020 11AM EST – *Proposal Submittal Date - (Also Required at time of Proposal Submittal is the Answer to FAR Clause 52.212-3, section (v)(2).) Your proposal will be considered Non-responsive if the clause is not answered at submittal.
Update #2 ·
September 1, 2020: 1) The site visit is not required. 2) Building 1800 (Dmarc) is 800 Ellipse Dr, Chicopee MA. (End)
SEE ATTACHED COMPLETE COMBINED SYNOPSIS/SOLICITATION AND STATEMENT OF WORK
Description of Requirement: The Contractor shall provide all personnel, equipment, materials, supervision, transportation, labor, and other items and services necessary to provide commercial high-speed fiber internet service to Westover ARB that will include either connecting to existing Charter Communications fiber feed which is currently terminated in Building 1800 (Demarcation) or provide a new fiber feed to Building 1800 (Demarcation) utilizing the Westover Manhole Duct System. Government will provide fiber connection from Building 1800 (Demarcation) to Building 1510 where Contractor will install Router/Gateway device and Firewall to provide high-speed fiber internet at Westover ARB.
(See the attached PWS for additional details.)
Acquisition: The government will issue a single award, Firm Fixed Price contract with an estimated period of performance starting October 1, 2020 and ending March 30, 2026, base year plus 5 option periods.
SAM Registration: Prior to supplying a proposal, interested offerors must have an active registration in the System for Award Management (SAM). Firms can register via the SAM internet web-site at https://www.sam.gov/SAM/.
Milestone Dates :
August 19, 2020 11AM EST - Register for Site visit (see COVID restrictions)
August 26, 2020 11AM EST – Site Visit
September 3, 2020 11AM EST – *Question Period ends
September 9, 2020 11AM EST – *Proposal Submittal Date - (Also Required at time of Proposal Submittal is the Answer to FAR Clause 52.212-3, section (v)(2).) Your proposal will be considered Non-responsive if the clause is not answered at submittal.
Update #1 ·
SEE ATTACHED COMPLETE COMBINED SYNOPSIS/SOLICITATION AND STATEMENT OF WORK
Description of Requirement: The Contractor shall provide all personnel, equipment, materials, supervision, transportation, labor, and other items and services necessary to provide commercial high-speed fiber internet service to Westover ARB that will include either connecting to existing Charter Communications fiber feed which is currently terminated in Building 1800 (Demarcation) or provide a new fiber feed to Building 1800 (Demarcation) utilizing the Westover Manhole Duct System. Government will provide fiber connection from Building 1800 (Demarcation) to Building 1510 where Contractor will install Router/Gateway device and Firewall to provide high-speed fiber internet at Westover ARB.
(See the attached PWS for additional details.)
Acquisition: The government will issue a single award, Firm Fixed Price contract with an estimated period of performance starting October 1, 2020 and ending March 30, 2026, base year plus 5 option periods.
SAM Registration: Prior to supplying a proposal, interested offerors must have an active registration in the System for Award Management (SAM). Firms can register via the SAM internet web-site at https://www.sam.gov/SAM/.
Milestone Dates :
August 19, 2020 11AM EST - Register for Site visit (see COVID restrictions)
August 26, 2020 11AM EST – Site Visit
September 3, 2020 11AM EST – *Question Period ends
September 9, 2020 11AM EST – *Proposal Submittal Date - (Also Required at time of Proposal Submittal is the Answer to FAR Clause 52.212-3, section (v)(2).) Your proposal will be considered Non-responsive if the clause is not answered at submittal.
Files
| File | Type | Posted |
|---|---|---|
| ISP Upgrade Question 3 Sept 20.pdf | ||
| SOW ISP Service 2020.pdf | ||
| Combined Synopsis Solicitation ISP Upgrade 2021 Final.pdf |