Installation of (2) 6” Class 1500 control valves, associated flanges, piping, supports, radiographic & ultrasonic testing of welds.

Closed Solicitation Posted

Solicitation number
N6660420R8176
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
236220 Commercial and Institutional Building Construction
PSC
C1EZ Architect And Engineering- Construction: Other Industrial Buildings
Place of performance
Newport RI 02841 USA

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

The purpose of amendment 0002

1) Dissolve the set-aside and re-solicit full and open

2) Extend the RFQ closing date to 25 June 2020 2:00 PM EST

3) Revise Section L to incorporate a requirement to the TECH EVAL FACTOR 1, Subfactor (b)

4) Schedule an additional site visit on 11 June 2020 9:00AM EST

5) Refresh and revise clauses

Posting Amendment 0001 responding to industry questions and clarifying the period of performance.

The Naval Undersea Warfare Center Division, Newport (NUWCDIVNPT) is a Naval research activity operating under the direction of the Commander, Naval Sea Systems Command (NAVSEA).   Project Description:  The work includes the installation of (2) 6” Class 1500 control valves, associated flanges, piping, supports, radiographic & ultrasonic testing of welds.

The Contractor shall provide all materials, equipment, labor, and supervision to repipe and replace high pressure valves for the ATF tank.

• All work to be performed at NUWCDIVNPT Building 1171C.

• Work to be performed in accordance with NUWCDIVNPT Drawings 19-039A (4 sheets) and statement of Work.

• NUWCDIVNPT to provide area for equipment and material storage.

• NUWCDIVNPT to provide access to area for workers and equipment.

• All Work to be in accordance with OSHA and Army Corp of Engineers Safety Manual, EM-385-1-1 Current Edition Safety requirements.

• All work to be completed in accordance with Safety and Health Standards for Construction Industry (29 CFR PART 1929 2007).

Update #2 ·

Posting Amendment 0001 responding to industry questions and clarifying the period of performance.

The Naval Undersea Warfare Center Division, Newport (NUWCDIVNPT) is a Naval research activity operating under the direction of the Commander, Naval Sea Systems Command (NAVSEA).   Project Description:  The work includes the installation of (2) 6” Class 1500 control valves, associated flanges, piping, supports, radiographic & ultrasonic testing of welds.

The Contractor shall provide all materials, equipment, labor, and supervision to repipe and replace high pressure valves for the ATF tank.

• All work to be performed at NUWCDIVNPT Building 1171C.

• Work to be performed in accordance with NUWCDIVNPT Drawings 19-039A (4 sheets) and statement of Work.

• NUWCDIVNPT to provide area for equipment and material storage.

• NUWCDIVNPT to provide access to area for workers and equipment.

• All Work to be in accordance with OSHA and Army Corp of Engineers Safety Manual, EM-385-1-1 Current Edition Safety requirements.

• All work to be completed in accordance with Safety and Health Standards for Construction Industry (29 CFR PART 1929 2007).

Update #1 ·

The Naval Undersea Warfare Center Division, Newport (NUWCDIVNPT) is a Naval research activity operating under the direction of the Commander, Naval Sea Systems Command (NAVSEA).   Project Description:  The work includes the installation of (2) 6” Class 1500 control valves, associated flanges, piping, supports, radiographic & ultrasonic testing of welds.

The Contractor shall provide all materials, equipment, labor, and supervision to repipe and replace high pressure valves for the ATF tank.

• All work to be performed at NUWCDIVNPT Building 1171C.

• Work to be performed in accordance with NUWCDIVNPT Drawings 19-039A (4 sheets) and statement of Work.

• NUWCDIVNPT to provide area for equipment and material storage.

• NUWCDIVNPT to provide access to area for workers and equipment.

• All Work to be in accordance with OSHA and Army Corp of Engineers Safety Manual, EM-385-1-1 Current Edition Safety requirements.

• All work to be completed in accordance with Safety and Health Standards for Construction Industry (29 CFR PART 1929 2007).

Files

File Type Posted
N6660420R81760002.pdf PDF
N6660420R81760001.pdf PDF
N6660420R8176 (1).pdf PDF

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors