Inspection of a Radial Thrust Bearing Assembly
Closed Solicitation Posted
- Solicitation number
- W912ES26QA0110001
- Agency
-
ENDIST St Paul
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 333914 Measuring, Dispensing, and Other Pumping Equipment Manufacturing
- Place of performance
- Fountain City, Wisconsin 54629, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Army Corps of Engineers, St. Paul Engineering District is soliciting inspection and potential repair services for a radial thrust bearing assembly installed on a VOSTA HPD 550-1350-280 dredge pump. The procurement comprises two phases: Phase 1 requires a comprehensive inspection to document component condition, identify the cause of oil leakage, and provide a detailed written report with repair/replacement cost estimates; Phase 2, contingent upon government approval, involves performing repairs or replacements to restore the assembly to full operational capability in accordance with OEM and industry standards. Contractors must comply with applicable standards including ISO 13709/API 610, ISO 5199, and ISO 281, utilize only OEM-certified parts, and follow manufacturer procedures throughout the work. The evaluation criteria emphasize technical qualifications, compliance with industry standards, and the ability to deliver thorough documentation including photographic evidence and functional testing verification. The proposal deadline is December 30, 2025, with a performance period extending to January 15, 2026, and the overall project scheduled for completion by March 15, 2026.
This solicitation is set aside as a Total Small Business contract, with no identified incumbent contractors. The contract vehicle is structured as a firm fixed-price arrangement, though specific award values or budget ranges are not disclosed in the available documentation. Phase 1 work must include return shipping to the Corps' Facility and Civil Works Service Base location, while Phase 2 execution is contingent on separate government approval and competitive consideration among other vendors. Should the Phase 1 contractor not win the Phase 2 repair contract, reassembly and safe packaging of the unit must be completed within 14 business days of notification. The work will be performed at the Army Corps of Engineers Civil Works Service Base located in Fountain City, Wisconsin 54629.
Notice text
Statement of Work (SOW)
Radial Thrust Bearing Assembly Inspection and Repair
1. Scope
This Statement of Work (SOW) defines a two-part effort for the inspection and repair of the radial thrust bearing assembly installed on the VOSTA HPD 550-1350-280 dredge pump.
Phase 1 – Inspection, Report, and Repair Estimate
The contractor shall perform a full inspection of the radial thrust bearing assembly to document component condition, identify the cause of oil leakage, and produce a written inspection report with a detailed repair/replacement cost estimate. The phase 1 price will include return shipping to the Corps’ FCSB location.
Phase 2 – Repair and Replacement (Upon Government Approval)
Repair or replacement activities shall occur only after the Government issues written approval. The objective is to restore the assembly to full operational capability in accordance with OEM and industry standards.
Oil leakage has been observed at the seals; therefore, special attention shall be given to seal condition, integrity, and lubrication during both inspection and repair.
The Corps reserves the right to compete the repair among other vendors. Should the firm awarded the inspection contract not win the contract for repair work the unit will be, reassembled (if needed), safely packaged, and returned to the Corps’ FCSB location no later than 14 business days from notification.
2. Applicable Documents
The following documents shall guide this effort.
The contractor shall have permission for use and access to the following company provided documents:
- VOSTA HPD 550-1350-280 Operation and Maintenance Manual
- OEM technical drawings, specifications, and service bulletins
The work shall comply with the latest revisions of the following standards:
Standard
Description
ISO 13709 / API 610
Centrifugal Pumps for Petroleum, Petrochemical, and Natural Gas Industries (primary heavy-duty pump specification).
ISO 5199
Technical specifications for centrifugal pumps — Class II.
ISO 281
Rolling bearings — Dynamic load ratings and rating life.
ISO 1940-1
Mechanical vibration — Balance quality for rigid rotors.
ANSI/ABMA 9
Load Ratings and Fatigue Life for Ball Bearings.
ANSI/ABMA 11
Load Ratings and Fatigue Life for Roller Bearings.
ANSI/ABMA 7
Shaft and Housing Fits for Metric Radial Ball and Roller Bearings.
ANSI/EASA AR100
Recommended practice for repair of rotating electrical apparatus—Section 2.2 regarding bearings.
3. Requirements
3.1 Phase 1 – Inspection Requirements
The contractor shall:
- Perform a complete inspection of the radial thrust bearing assembly to identify wear, damage, or defects.
- Document the condition of all bearing components, including races, rollers, cages, seals, lubrication channels, and other related parts.
- Evaluate and document the source and extent of oil leakage, including photographs and corrective recommendations.
- Provide a written inspection report identifying components requiring replacement.
- Include photographic documentation of all damaged or worn components.
- Provide a detailed cost estimate for repairs or replacements, including part lead times.
3.2 Phase 2 – Replacement of Damaged Components (Upon Approval)
The contractor shall:
- Remove and replace only Government-approved components identified in Phase 1.
- Use OEM-certified replacement parts only.
- Install components using OEM procedures and correct torque specifications.
- Apply proper lubrication, seals, and fasteners in accordance with OEM guidance.
- Document all replaced components with photographs.
3.2.1 Government Approval Requirement
No removal, replacement, or repair work shall begin without written authorization from the Contracting Officer (CO). Any unauthorized repair work shall be performed at no cost to the Government.
3.3 Testing and Verification – to be priced as part of any repair submission.
After completion of approved repairs, the contractor shall:
- Perform alignment and functional checks.
- Verify rotational performance, load capacity, and lubrication flow per OEM standards.
- Provide documentation of all test results.
4. Materials and Workmanship
- All replacement parts shall be new, OEM-certified, and free of defects.
- All work shall comply with OEM instructions and accepted industry best practices.
- Personnel performing the work shall be qualified in heavy-duty pump bearing maintenance.
5. Deliverables
The contractor shall provide:
- Phase 1 inspection report, including findings, required replacements, and photos.
- Repair cost estimate.
6. Quality Assurance and Acceptance
Government representatives may witness inspection, repair, and testing activities.
Final acceptance shall be based on:
- Compliance with this SOW
7. Schedule
- The contractor shall submit a detailed schedule for inspection, reporting, approval, repair, and testing no later than 15 January 2026.
- All work, to include any authorized repair, shall be completed no later than 15 March 2026.
8. Shipping, Delivery, and Reporting
- The contractor is responsible for all shipping costs and logistics for transporting the unit to and from their facility.
- The unit is Approx. 8,000 pounds, is on cribbing and can be loaded and unloaded from/to the Army Corp. facility 0730-1500 Mon-Friday.
- Loading/unloading from Corp. facility shall be completed by the contractor.
- Pick up/Shipping Address:
431 North Shore Drive
PO Box 397
Fountain City, WI 54629 - All documentation shall be submitted to the Government Technical Point of Contact (TPOC).
- All replaced components shall be returned to the Government for inspection and final disposition.
Files
| File | Type | Posted |
|---|---|---|
| Solicitation - W912ES26QA011.pdf | ||
| Solicitation Amendment W912ES26QA0110001 SF 30.pdf | ||
| Image of packed RTB.jpg | JPG image |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| W912EE27BA001 - Lease of One Cutterhead, Hydraulic Pipeline Dredge (Not Less Than 18-Inch Diameter) Fully Operated with Attendant Plant and Personnel, and with a Draft not to Exceed 9 Feet, for Construction and Maintenance Dredging - MS River Harbors | ENDIST Vicksburg | No set-aside | |
| Dworshak Skeleton Bay Draft Tube Bulkhead Rehabilitation | ENDIST Walla Walla | Total Small Business | |
| Duluth Vessel Yard Phase III Repairs | ENDIST Detroit | Total Small Business | |
| Pump, axial pistons & axial piston parts kit | — | Total Small Business | |
| Pump Unit, Hydraulic | Land and Maritime | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity