IDIQ MACC NAICS 236220 general construction projects within feads yuma and EL centro AOR

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
N6247321R0030
Agency
Responses due
Set-aside
Service-Disabled Veteran-Owned Small Business

Opportunity facts

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation is seeking proposals for an Indefinite Delivery Indefinite Quantity (IDIQ) Multiple Award Construction Contract (MACC) under NAICS code 236220 for general construction projects at government installations within the Facilities Engineering Acquisition Division (FEAD) Yuma and El Centro Area of Responsibility (AOR) for the Naval Facilities Engineering Command (NAVFAC SW). Proposals are due by June 13, 2023 and the contract is set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB).

The solicitation is set aside for SDVOSBs and is for general construction projects within the FEAD Yuma and El Centro AOR under NAICS code 236220. The place of performance will be at government installations within the specified AOR. The solicitation does not provide estimated award values or quantity of projects but seeks multiple awards for an indefinite delivery of construction services. Visit https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=N6247321R0030 for additional details on the requirements.

Notice text

9 versions

Update #9 · Latest ·

The purpose of amendment 7 is to update RFP Parts 2 - 6, Provide answers to submitted RFIs, and change the proposal due date to 13 Jun 2023. The purpose of amendment 6 is to update RFP Part 1 - Contract Forms and Documents, 5. Site Visit. The site visit limit from each contractor has changed from two (2) to four (4). The purpose of Amendment 5 is to update RFP Part 1 - Contract Forms and Documents, 5. Site Visit. The pre-proposal site visit will be conducted at 9:00AM (local), May 23, 2023. The purpose of amendment 4 is to close Phase One and open Phase Two for the subject solicitation. This amendment incorporates revisions to Section 00 21 16 Instructions to Proposers, Factor 4 Safety, Factor 5 Technical Solution, and Exhibit F Safety Data and Narrative. This amendment also updates FAR and DFARS clauses and provisions and incorporates provision DFARS 252.225-7059, Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region ? Certification, and clause at DFARS 252.225-7060, Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region. The purpose of Amendment 0003 is to Incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 2-Experience, (1) Construction Experience. The following sentence has been removed from this section Note: The Offeror may not utilize the experience of large business concerns to demonstrate construction experience under this evaluation factor. This amendment also revises the answer to RFI question #4 and extends the proposal due date from 27 July 2022 to 10 August 2022. The purpose of Amendment 0002 is to incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 2-Experience, Basis of Evaluation. Paragraph 3 has change from $100,000 to $500,000. Offerors must acknowledge both Amendment 0001 - Amendment 0002 in Standard Form 1442, Block 19. The purpose of this amendment is to update RFI Form - Phase One. The answer to RFI #4 was not viewable when posted along with Solicitation Amendment 0001. The purpose of Amendment 0001 is to incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 1-Technical Approach, Factor 2-Experience, Factor 3-Past Performance. This amendment also updates FAR Clause 52.228-1, incorporates the Offerors Team Consent Form, provide answers to submitted RFIs. INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ) MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) SERVICE DISABLEDVETERAN-OWNED SMALL BUSINESS (SDVOSB) SET-ASIDE UNDER NAICS CODE 236220 GENERAL CONSTRUCTION PROJECTS ATGOVERNMENT INSTALLATIONS UNDER NAVAL FACILIITES ENGINEERING SYSTEMS COMMAND (NAVFAC SW) WITHIN FACILITIESENGINEERING ACQUISITION DIVISION (FEAD) YUMA AND EL CENTRO AREA OF RESPONSIBILITY (AOR).

Update #8 ·

The purpose of amendment 6 is to update RFP Part 1 - Contract Forms and Documents, 5. Site Visit. The site visit limit from each contractor has changed from two (2) to four (4). The purpose of Amendment 5 is to update RFP Part 1 - Contract Forms and Documents, 5. Site Visit. The pre-proposal site visit will be conducted at 9:00AM (local), May 23, 2023. The purpose of amendment 4 is to close Phase One and open Phase Two for the subject solicitation. This amendment incorporates revisions to Section 00 21 16 Instructions to Proposers, Factor 4 Safety, Factor 5 Technical Solution, and Exhibit F Safety Data and Narrative. This amendment also updates FAR and DFARS clauses and provisions and incorporates provision DFARS 252.225-7059, Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region ? Certification, and clause at DFARS 252.225-7060, Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region. The purpose of Amendment 0003 is to Incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 2-Experience, (1) Construction Experience. The following sentence has been removed from this section Note: The Offeror may not utilize the experience of large business concerns to demonstrate construction experience under this evaluation factor. This amendment also revises the answer to RFI question #4 and extends the proposal due date from 27 July 2022 to 10 August 2022. The purpose of Amendment 0002 is to incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 2-Experience, Basis of Evaluation. Paragraph 3 has change from $100,000 to $500,000. Offerors must acknowledge both Amendment 0001 - Amendment 0002 in Standard Form 1442, Block 19. The purpose of this amendment is to update RFI Form - Phase One. The answer to RFI #4 was not viewable when posted along with Solicitation Amendment 0001. The purpose of Amendment 0001 is to incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 1-Technical Approach, Factor 2-Experience, Factor 3-Past Performance. This amendment also updates FAR Clause 52.228-1, incorporates the Offerors Team Consent Form, provide answers to submitted RFIs. INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ) MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) SERVICE DISABLEDVETERAN-OWNED SMALL BUSINESS (SDVOSB) SET-ASIDE UNDER NAICS CODE 236220 GENERAL CONSTRUCTION PROJECTS ATGOVERNMENT INSTALLATIONS UNDER NAVAL FACILIITES ENGINEERING SYSTEMS COMMAND (NAVFAC SW) WITHIN FACILITIESENGINEERING ACQUISITION DIVISION (FEAD) YUMA AND EL CENTRO AREA OF RESPONSIBILITY (AOR).

Update #7 ·

The purpose of Amendment 5 is to update RFP Part 1 - Contract Forms and Documents, 5. Site Visit. The pre-proposal site visit will be conducted at 9:00AM (local), May 23, 2023. The purpose of amendment 4 is to close Phase One and open Phase Two for the subject solicitation. This amendment incorporates revisions to Section 00 21 16 Instructions to Proposers, Factor 4 Safety, Factor 5 Technical Solution, and Exhibit F Safety Data and Narrative. This amendment also updates FAR and DFARS clauses and provisions and incorporates provision DFARS 252.225-7059, Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region ? Certification, and clause at DFARS 252.225-7060, Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region. The purpose of Amendment 0003 is to Incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 2-Experience, (1) Construction Experience. The following sentence has been removed from this section Note: The Offeror may not utilize the experience of large business concerns to demonstrate construction experience under this evaluation factor. This amendment also revises the answer to RFI question #4 and extends the proposal due date from 27 July 2022 to 10 August 2022. The purpose of Amendment 0002 is to incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 2-Experience, Basis of Evaluation. Paragraph 3 has change from $100,000 to $500,000. Offerors must acknowledge both Amendment 0001 - Amendment 0002 in Standard Form 1442, Block 19. The purpose of this amendment is to update RFI Form - Phase One. The answer to RFI #4 was not viewable when posted along with Solicitation Amendment 0001. The purpose of Amendment 0001 is to incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 1-Technical Approach, Factor 2-Experience, Factor 3-Past Performance. This amendment also updates FAR Clause 52.228-1, incorporates the Offerors Team Consent Form, provide answers to submitted RFIs. INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ) MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) SERVICE DISABLEDVETERAN-OWNED SMALL BUSINESS (SDVOSB) SET-ASIDE UNDER NAICS CODE 236220 GENERAL CONSTRUCTION PROJECTS ATGOVERNMENT INSTALLATIONS UNDER NAVAL FACILIITES ENGINEERING SYSTEMS COMMAND (NAVFAC SW) WITHIN FACILITIESENGINEERING ACQUISITION DIVISION (FEAD) YUMA AND EL CENTRO AREA OF RESPONSIBILITY (AOR).

Update #6 ·

The purpose of amendment 4 is to close Phase One and open Phase Two for the subject solicitation. This amendment incorporates revisions to Section 00 21 16 Instructions to Proposers, Factor 4 Safety, Factor 5 Technical Solution, and Exhibit F Safety Data and Narrative. This amendment also updates FAR and DFARS clauses and provisions and incorporates provision DFARS 252.225-7059, Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region ? Certification, and clause at DFARS 252.225-7060, Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region. The purpose of Amendment 0003 is to Incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 2-Experience, (1) Construction Experience. The following sentence has been removed from this section Note: The Offeror may not utilize the experience of large business concerns to demonstrate construction experience under this evaluation factor. This amendment also revises the answer to RFI question #4 and extends the proposal due date from 27 July 2022 to 10 August 2022. The purpose of Amendment 0002 is to incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 2-Experience, Basis of Evaluation. Paragraph 3 has change from $100,000 to $500,000. Offerors must acknowledge both Amendment 0001 - Amendment 0002 in Standard Form 1442, Block 19. The purpose of this amendment is to update RFI Form - Phase One. The answer to RFI #4 was not viewable when posted along with Solicitation Amendment 0001. The purpose of Amendment 0001 is to incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 1-Technical Approach, Factor 2-Experience, Factor 3-Past Performance. This amendment also updates FAR Clause 52.228-1, incorporates the Offerors Team Consent Form, provide answers to submitted RFIs. INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ) MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) SERVICE DISABLEDVETERAN-OWNED SMALL BUSINESS (SDVOSB) SET-ASIDE UNDER NAICS CODE 236220 GENERAL CONSTRUCTION PROJECTS ATGOVERNMENT INSTALLATIONS UNDER NAVAL FACILIITES ENGINEERING SYSTEMS COMMAND (NAVFAC SW) WITHIN FACILITIESENGINEERING ACQUISITION DIVISION (FEAD) YUMA AND EL CENTRO AREA OF RESPONSIBILITY (AOR).

Update #5 ·

The purpose of Amendment 0003 is to Incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 2-Experience, (1) Construction Experience. The following sentence has been removed from this section Note: The Offeror may not utilize the experience of large business concerns to demonstrate construction experience under this evaluation factor. This amendment also revises the answer to RFI question #4 and extends the proposal due date from 27 July 2022 to 10 August 2022. The purpose of Amendment 0002 is to incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 2-Experience, Basis of Evaluation. Paragraph 3 has change from $100,000 to $500,000. Offerors must acknowledge both Amendment 0001 - Amendment 0002 in Standard Form 1442, Block 19. The purpose of this amendment is to update RFI Form - Phase One. The answer to RFI #4 was not viewable when posted along with Solicitation Amendment 0001. The purpose of Amendment 0001 is to incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 1-Technical Approach, Factor 2-Experience, Factor 3-Past Performance. This amendment also updates FAR Clause 52.228-1, incorporates the Offerors Team Consent Form, provide answers to submitted RFIs. INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ) MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) SERVICE DISABLEDVETERAN-OWNED SMALL BUSINESS (SDVOSB) SET-ASIDE UNDER NAICS CODE 236220 GENERAL CONSTRUCTION PROJECTS ATGOVERNMENT INSTALLATIONS UNDER NAVAL FACILIITES ENGINEERING SYSTEMS COMMAND (NAVFAC SW) WITHIN FACILITIESENGINEERING ACQUISITION DIVISION (FEAD) YUMA AND EL CENTRO AREA OF RESPONSIBILITY (AOR). *Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=N6247321R0030' to obtain more details.*

Update #4 ·

The purpose of Amendment 0002 is to incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 2-Experience, Basis of Evaluation. Paragraph 3 has change from $100,000 to $500,000. Offerors must acknowledge both Amendment 0001 - Amendment 0002 in Standard Form 1442, Block 19. The purpose of this amendment is to update RFI Form - Phase One. The answer to RFI #4 was not viewable when posted along with Solicitation Amendment 0001. The purpose of Amendment 0001 is to incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 1-Technical Approach, Factor 2-Experience, Factor 3-Past Performance. This amendment also updates FAR Clause 52.228-1, incorporates the Offerors Team Consent Form, provide answers to submitted RFIs. INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ) MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) SERVICE DISABLEDVETERAN-OWNED SMALL BUSINESS (SDVOSB) SET-ASIDE UNDER NAICS CODE 236220 GENERAL CONSTRUCTION PROJECTS ATGOVERNMENT INSTALLATIONS UNDER NAVAL FACILIITES ENGINEERING SYSTEMS COMMAND (NAVFAC SW) WITHIN FACILITIESENGINEERING ACQUISITION DIVISION (FEAD) YUMA AND EL CENTRO AREA OF RESPONSIBILITY (AOR). *Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=N6247321R0030' to obtain more details.*

Update #3 ·

The purpose of this amendment is to update RFI Form - Phase One. The answer to RFI #4 was not viewable when posted along with Solicitation Amendment 0001. The purpose of Amendment 0001 is to incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 1-Technical Approach, Factor 2-Experience, Factor 3-Past Performance. This amendment also updates FAR Clause 52.228-1, incorporates the Offerors Team Consent Form, provide answers to submitted RFIs. INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ) MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) SERVICE DISABLEDVETERAN-OWNED SMALL BUSINESS (SDVOSB) SET-ASIDE UNDER NAICS CODE 236220 GENERAL CONSTRUCTION PROJECTS ATGOVERNMENT INSTALLATIONS UNDER NAVAL FACILIITES ENGINEERING SYSTEMS COMMAND (NAVFAC SW) WITHIN FACILITIESENGINEERING ACQUISITION DIVISION (FEAD) YUMA AND EL CENTRO AREA OF RESPONSIBILITY (AOR). *Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=N6247321R0030' to obtain more details.*

Update #2 ·

The purpose of Amendment 0001 is to incorporate the revisions to Section 00 21 16-Instructions to Proposers, Basis for Award, Factor 1-Technical Approach, Factor 2-Experience, Factor 3-Past Performance. This amendment also updates FAR Clause 52.228-1, incorporates the Offerors Team Consent Form, provide answers to submitted RFIs. INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ) MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) SERVICE DISABLEDVETERAN-OWNED SMALL BUSINESS (SDVOSB) SET-ASIDE UNDER NAICS CODE 236220 GENERAL CONSTRUCTION PROJECTS ATGOVERNMENT INSTALLATIONS UNDER NAVAL FACILIITES ENGINEERING SYSTEMS COMMAND (NAVFAC SW) WITHIN FACILITIESENGINEERING ACQUISITION DIVISION (FEAD) YUMA AND EL CENTRO AREA OF RESPONSIBILITY (AOR). *Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=N6247321R0030' to obtain more details.*

Update #1 ·

INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ) MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC) SERVICE DISABLEDVETERAN-OWNED SMALL BUSINESS (SDVOSB) SET-ASIDE UNDER NAICS CODE 236220 GENERAL CONSTRUCTION PROJECTS ATGOVERNMENT INSTALLATIONS UNDER NAVAL FACILIITES ENGINEERING SYSTEMS COMMAND (NAVFAC SW) WITHIN FACILITIESENGINEERING ACQUISITION DIVISION (FEAD) YUMA AND EL CENTRO AREA OF RESPONSIBILITY (AOR). *Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=N6247321R0030' to obtain more details.*

Notice history

Similar open opportunities

Opportunity Agency Set-aside Responses due
Sources sought for indefinite delivery indefinite quantity (IDIQ) multiple award construction contract (MACC) for projects under NAICS 236220 located within the naval facilities engineering systems command (NAVFAC) northwest area of responsibility. Bremerton, Washington, United States · NAICS 236220 Naval Facilities Engineering Command Total Small Business
HAFB Multiple Award Construction Contract V (MACC V) Hill AFB, UT (Davis County) Utah Test and Training Range (Uttr) Little Mountain Test Facility (Lmtf) Utah Air National Guard (Utang) Base Boulder Seismic Site, WY Other: Geographically separated units (GSU) under the responsibility of 75 ABW/CC · NAICS 236220 Air Force Sustainment Center Total Small Business
Sources sought notice - VISN 7 construction MATOC 36C24726R0026 Decatur, Georgia 30033, United States · NAICS 236220 Veterans Integrated Service Network 7 Service-Disabled Veteran-Owned Small Business
FY27 MACC Shaw Air Force Base, Poinsett Weapons Range, Wateree Recreation Facility, and other multiple mini-mute sites, not to include Military Family Housing, as requirements arise. Shaw AFB, South Carolina 29152, United States · NAICS 236220 Air Combat Command Total Small Business
2027-2034 Wright-Patterson Air Force Base Multiple Award Construction Contract (MACC) Wright-Patterson Air Force Base 45433 · NAICS 236220 AFLCMC Wright Patterson AFB Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors