HQ Expansion Phase 1 and 2, Camp Commando, Kabul Province, Afghanistan
Award Notice Posted
- Solicitation number
- W5J9JE-18-R-0016
- Agency
-
ENDIST Middle East
US Army Corps of Engineers, Department of Defense
- Awarded
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- W5J9JE-18-C-0013 Federal contract award
- NAICS code
- 236220 Commercial and Institutional Building Construction
- PSC
- Not on record
- Place of performance
- Kabul, Afghanistan, United States
Notice details come from SAM.gov. Updated .
Notice text
3 versions
Update #3 · Latest ·
Full and Open Solicitaiton (Phase 1 Only) for the design and construction of the site infrastructure and the construction of 5 buildings for the HQ Phase 1 AND 2 - Camp Commando, Kabul, Afghanistan. Phase 1 Due April 11, 2018 at 3:00PM, Local Kabul Time.
Only proposals from offerers determined to be base access eligible by the Joint Contingency Contracting System (https://www.jccs.gov/) at the time of proposal due date, shall be evaluated.
The North American Industry Classification System (NAICS) Code is 236220. All firms and prime contractors doing business with the Federal Government shall be registered in the System for Award Management (SAM) database at www .sam.gov prior to award of a contract
The contractor shall be responsible for the design, material, labor, and equipment to accomplish the following requirements:
Construct two headquarter buildings, one conference center, one Joint Operations Center (JOC), one fusion cell building, utilities (water, electrical distribution, communications, sewer lines), demolition and other infrastructure. The Contractor shall provide a Geotechnical Report, a complete surface and topographical survey and shall design all Site and Utility features.
The Contractor shall be responsible for searching for, identifying and clearing all unexploded ordnance in all areas that the Contractor shall excavate below 1 meter in depth. All other areas have been cleared to a 1 meter depth.
Pursuant to the Federal Acquisition Regulation Supplements (FAR) 36.204, the magnitude for this project is between $5.0 million (M) and $10.0M.
Update #2 ·
The US Army Corps of Engineers (USACE), Transatlantic Afghanistan District plans to Issue a Full and Open Solicitaiton on our about 14 March 2018 (Phase 1 Only) for the design and construction of the site infrastructure and the construction of 5 buildings for the HQ Phase 1 AND 2 - Camp Commando, Kabul, Afghanistan
Only proposals from offerers determined to be base access eligible by the Joint Contingency Contracting System (https://www.jccs.gov/) at the time of proposal due date, shall be evaluated.
The North American Industry Classification System (NAICS) Code is 236220. All firms and prime contractors doing business with the Federal Government shall be registered in the System for Award Management (SAM) database at www .sam.gov prior to award of a contract
The contractor shall be responsible for the design, material, labor, and equipment to accomplish the following requirements:
Construct two headquarter buildings, one conference center, one Joint Operations Center (JOC), one fusion cell building, utilities (water, electrical distribution, communications, sewer lines), demolition and other infrastructure. The Contractor shall provide a Geotechnical Report, a complete surface and topographical survey and shall design all Site and Utility features.
The Contractor shall be responsible for searching for, identifying and clearing all unexploded ordnance in all areas that the Contractor shall excavate below 1 meter in depth. All other areas have been cleared to a 1 meter depth.
Pursuant to the Federal Acquisition Regulation Supplements (FAR) 36.204, the magnitude for this project is between $5.0 million (M) and $10.0M.
Update #1 ·
The US Army Corps of Engineers (USACE), Transatlantic Afghanistan District plans to Issue a Full and Open Solicitaiton on our about 14 March 2018 (Phase 1 Only) for the design and construction of the site infrastructure and the construction of 5 buildings for the ANASOC Corps HQ Phase 1 AND 2 - Camp Commando, Kabul, Afghanistan
Only proposals from offerers determined to be base access eligible by the Joint Contingency Contracting System (https://www.jccs.gov/) at the time of proposal due date, shall be evaluated.
The North American Industry Classification System (NAICS) Code is 236220. All firms and prime contractors doing business with the Federal Government shall be registered in the System for Award Management (SAM) database at www .sam.gov prior to award of a contract
The contractor shall be responsible for the design, material, labor, and equipment to accomplish the following requirements:
Construct two headquarter buildings, one conference center, one Joint Operations Center (JOC), one fusion cell building, utilities (water, electrical distribution, communications, sewer lines), demolition and other infrastructure. The Contractor shall provide a Geotechnical Report, a complete surface and topographical survey and shall design all Site and Utility features.
The Contractor shall be responsible for searching for, identifying and clearing all unexploded ordnance in all areas that the Contractor shall excavate below 1 meter in depth. All other areas have been cleared to a 1 meter depth.
Pursuant to the Federal Acquisition Regulation Supplements (FAR) 36.204, the magnitude for this project is between $5.0 million (M) and $10.0M.
Files
Notice history
| Notice | Type | Posted |
|---|---|---|
| This notice | Award Notice | |
| Headquarters expansion phases 1 and 2, camp commando, kabul province, afghanistan | Pre-Solicitation |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity