- Solicitation number
- DTFH6817B00034
- Agency
-
Federal Highway Administration
Department of Transportation
- Awarded
- to Maui Kupono Builders LLC
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- 6982AF18C000019 Federal contract award
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- PSC
- Not on record
- Place of performance
- Island of Maui Maui, Hawaii, United States
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
THIS IS AN INVITATION FOR BID. PLANS AND SPECIFICATIONS ARE NOW AVAILABLE.
PROJECT DETAILS: HI FTNP HALE 10(2), Main Haleakala Park Road
The project is located on the island of Maui, Hawaii, approximately 10 miles southeast of Pukalani.
This project is for full-depth pavement reclamation and paving of approximately 3.8 miles of Main Haleakala Park Road.
Significant items:
Item | Unit | Estimated Quantity |
Aggregate Base | TON | 100 |
Pulverizing | SQYD | 60,000 |
Hot-asphalt concrete pavement | TON | 7,500 |
Open-graded friction course | TON | 2,300 |
Asphalt Curb, 4-inch | LNFT | 20,000 |
It is anticipated that the project will be awarded in late February, 2018. The estimated period of performance is April, 2018 through October, 2018. Estimated total cost is $5 million to $10 million.
Update #1 ·
THIS IS NOT AN INVITATION FOR BID. PLANS AND SPECIFICATIONS ARE NOT AVAILABLE AT THIS TIME.
PROJECT DETAILS: HI FTNP HALE 10(2), Main Haleakala Park Road
The project is located on the island of Maui, Hawaii, approximately 10 miles southeast of Pukalani.
This project is for full-depth pavement reclamation and paving of approximately 3.8 miles of Main Haleakala Park Road.
Significant items:
Item | Unit | Estimated Quantity |
Aggregate Base | TON | 100 |
Pulverizing | SQYD | 60,000 |
Hot-asphalt concrete pavement | TON | 7,500 |
Open-graded friction course | TON | 2,300 |
Asphalt Curb, 4-inch | LNFT | 20,000 |
It is anticipated that the project will be advertised in January, 2018. The estimated period of performance is April, 2018 through October, 2018. Estimated total cost is $5 million to $10 million.
Files
Show all 14
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity