Helena National Forest Warm Springs Creek Tailings Project
Award Notice Posted
- Solicitation number
- AG-03H6-S-13-0003
- Agency
-
Region 1 - Northern Region
Forest Service, Department of Agriculture
- Set-aside
- Total Small Business
Opportunity facts
- Contract number
- AG-03H6-C-13-0005 Federal contract award
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Not on record
- Place of performance
- Warm Spring Creek Clancy, Montana 59634, United States
Notice details come from SAM.gov. Updated .
Notice text
3 versions
Update #3 · Latest ·
Due 4 September at 3:00 pm.
Update #2 ·
Site Visit will be 8 August 2013 at 9:00 am. Meeting place will be the Clancy exit on I-15 (east side).
Update #1 ·
The Helena National Forest desires to conduct a Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) removal action that consists of removing approximately 40,000 cubic yards of heavy metal laden mill tailings from the Warm Springs Creek drainage located near Clancy, Montana, and placing the tailings into a nearby constructed repository. Work will include but is not limited to the placement of erosion control features, development of the repository, excavation/transport/placement of the tailings, shaping and covering of the tailings in the repository, re-contouring of the excavated areas, stream reconstruction within the tailings removal area, blading of the haul road, and seeding and fertilizing of all disturbed areas.
Solicitation will be published around the first of July. Estimated magnitude of construction is between $500,000 and $1,000,000. SUBJECT TO AVAILABILITY OF FUNDS.