About this opportunity

The U.S. Army Corps of Engineers, Baltimore District, intends to issue a solicitation for the construction of a 120,000 square foot Command and Control Facility and 174,000 square foot parking garage at Fort Belvoir North Area in Springfield, Virginia. The project is a design-bid-build contract that will be evaluated using best value tradeoff procedures. Proposals are due January 26, 2024. The facility must meet DoD antiterrorism standards and have a design life of 40 years.

There is no set-aside designated for this project. The NAICS code is 236220 for Commercial and Institutional Building Construction with a size standard of $45 million. The period of performance is three years. The project budget was not disclosed but it is estimated to cost over $100 million based on the size and specialized requirements of the facilities. Construction must be completed within 1095 calendar days to support over 650 personnel by bolstering long-range mission facility needs.

Notice text

3 versions

Update #3 · Latest ·

****1/19/2024: The RFP has been posted; however, it is not linked to this because it was generated through PIEE. Use this link to access - https://sam.gov/opp/266b1050799e4dbdb0b9c8586482cc95/view 

The U.S. Army Corps of Engineers (USACE), Baltimore District, intends to issue an RFP for construction services of the HQ Annex at FBNA. This project will be a competitive design-bid-build contract procured in accordance with FAR Part 15, Contracting by Negotiation, under a Best Value-Tradeoff Process.

The North American Industry Classification System (NAICS) for this requirement is 236220 (Commercial and Institutional Building Construction) Business Size Standard of $45.0 Million. The Period of Performance (PoP) is three (3) years, 1095 days.

Project Description: Construct a Command and Control Facility (C2F)[120K SF] and a Parking garage [174K SF]. Project serves as the Annex to an Department of Defense Agencyat FBNA and includes a secured administrative building divided into specified security zones and operations area that includes special use space for a Secure Area, Data Center, and Network Operations Center. Construction includes redundant mechanical and electrical systems with backup power, secure (within confines of secured campus) organizational vehicle parking, loading service areas, information systems, fire protection and alarm systems, Intrusion Detection System (IDS) installation, and Energy Monitoring Control Systems (EMCS) connection. Sustainability and energy enhancement measures are included. Supporting facilities include site development, utilities and connections, lighting, paving, parking, walks, curbs and gutters, storm drainage, information systems, landscaping and signage. Heating and air conditioning will be provided by self-contained systems within C2F. Measures in accordance with the Department of Defense (DoD) Minimum Antiterrorism for Buildings standards will be provided. Comprehensive building and furnishings related interior design services are required. Access for individuals with disabilities will be provided. Facilities will be designed to a minimum life of 40 years in accordance with DoD's Unified Facilities Criteria (UFC 1-200-02) including energy efficiencies, building envelope and integrated building systems performance.

This project is required to bolster the long-range mission facility support requirements of The Department of Defense. This project is to provide an adequate Command and Control Facility (C2F) and Parking Garage to support the Department of Defense. This Command-and-Control Facility (C2F) is required to provide appropriate suites, staff offices, administrative support areas, Secure Sensitive Area and support areas at Fort Belvoir. This project includes space for currently 650 personnel and associated specialized support equipment. This project will provide increased operational efficiencies in support of Command-and-Control services and proceedings through consolidation of dispersed functions, appropriate security zoning, and Secure Sensitive Areas. Supporting directorates of the Headquarters command staff are identified to occupy the Command-and-Control Facility (C2F) based on operational priorities. The Command-and-Control Facility (C2F) will meet Command and Control Facility (C2F) functions and tasks across the full spectrum of missions and operations.

This requirement will be solicited -- full and open competition. The solicitation requirements will be posted electronically on or about 8 January 2024 via the SAM Website at www.sam.gov with proposal submissions due approximately 30 days after issuance of the solicitation.

*Note: The previous solicitation number was W912DR23R0089 and a placeholder, W912DR24Z9999, was used until an FY24 ID could be obtained. The official RFP number will be W912DR24R0010.

Update #2 ·

The U.S. Army Corps of Engineers (USACE), Baltimore District, intends to issue an RFP for construction services of the HQ Annex at FBNA. This project will be a competitive design-bid-build contract procured in accordance with FAR Part 15, Contracting by Negotiation, under a Best Value-Tradeoff Process.

The North American Industry Classification System (NAICS) for this requirement is 236220 (Commercial and Institutional Building Construction) Business Size Standard of $45.0 Million. The Period of Performance (PoP) is three (3) years, 1095 days.

Project Description: Construct a Command and Control Facility (C2F)[120K SF] and a Parking garage [174K SF]. Project serves as the Annex to an Department of Defense Agencyat FBNA and includes a secured administrative building divided into specified security zones and operations area that includes special use space for a Secure Area, Data Center, and Network Operations Center. Construction includes redundant mechanical and electrical systems with backup power, secure (within confines of secured campus) organizational vehicle parking, loading service areas, information systems, fire protection and alarm systems, Intrusion Detection System (IDS) installation, and Energy Monitoring Control Systems (EMCS) connection. Sustainability and energy enhancement measures are included. Supporting facilities include site development, utilities and connections, lighting, paving, parking, walks, curbs and gutters, storm drainage, information systems, landscaping and signage. Heating and air conditioning will be provided by self-contained systems within C2F. Measures in accordance with the Department of Defense (DoD) Minimum Antiterrorism for Buildings standards will be provided. Comprehensive building and furnishings related interior design services are required. Access for individuals with disabilities will be provided. Facilities will be designed to a minimum life of 40 years in accordance with DoD's Unified Facilities Criteria (UFC 1-200-02) including energy efficiencies, building envelope and integrated building systems performance.

This project is required to bolster the long-range mission facility support requirements of The Department of Defense. This project is to provide an adequate Command and Control Facility (C2F) and Parking Garage to support the Department of Defense. This Command-and-Control Facility (C2F) is required to provide appropriate suites, staff offices, administrative support areas, Secure Sensitive Area and support areas at Fort Belvoir. This project includes space for currently 650 personnel and associated specialized support equipment. This project will provide increased operational efficiencies in support of Command-and-Control services and proceedings through consolidation of dispersed functions, appropriate security zoning, and Secure Sensitive Areas. Supporting directorates of the Headquarters command staff are identified to occupy the Command-and-Control Facility (C2F) based on operational priorities. The Command-and-Control Facility (C2F) will meet Command and Control Facility (C2F) functions and tasks across the full spectrum of missions and operations.

This requirement will be solicited -- full and open competition. The solicitation requirements will be posted electronically on or about 8 January 2024 via the SAM Website at www.sam.gov with proposal submissions due approximately 30 days after issuance of the solicitation.

*Note: The previous solicitation number was W912DR23R0089 and a placeholder, W912DR24Z9999, was used until an FY24 ID could be obtained. The official RFP number will be W912DR24R0010.

Update #1 ·

The U.S. Army Corps of Engineers (USACE), Baltimore District, intends to issue an RFP for construction services of the HQ Annex at FBNA. This project will be a competitive design-bid-build contract procured in accordance with FAR Part 15, Contracting by Negotiation, under a Best Value-Tradeoff Process.

The North American Industry Classification System (NAICS) for this requirement is 236220 (Commercial and Institutional Building Construction) Business Size Standard of $45.0 Million. The Period of Performance (PoP) is three (3) years, 1095 days.

Project Description: Construct a Command and Control Facility (C2F)[120K SF] and a Parking garage [174K SF]. Project serves as the Annex to an Department of Defense Agencyat FBNA and includes a secured administrative building divided into specified security zones and operations area that includes special use space for a Secure Area, Data Center, and Network Operations Center. Construction includes redundant mechanical and electrical systems with backup power, secure (within confines of secured campus) organizational vehicle parking, loading service areas, information systems, fire protection and alarm systems, Intrusion Detection System (IDS) installation, and Energy Monitoring Control Systems (EMCS) connection. Sustainability and energy enhancement measures are included. Supporting facilities include site development, utilities and connections, lighting, paving, parking, walks, curbs and gutters, storm drainage, information systems, landscaping and signage. Heating and air conditioning will be provided by self-contained systems within C2F. Measures in accordance with the Department of Defense (DoD) Minimum Antiterrorism for Buildings standards will be provided. Comprehensive building and furnishings related interior design services are required. Access for individuals with disabilities will be provided. Facilities will be designed to a minimum life of 40 years in accordance with DoD's Unified Facilities Criteria (UFC 1-200-02) including energy efficiencies, building envelope and integrated building systems performance.

This project is required to bolster the long-range mission facility support requirements of The Department of Defense. This project is to provide an adequate Command and Control Facility (C2F) and Parking Garage to support the Department of Defense. This Command-and-Control Facility (C2F) is required to provide appropriate suites, staff offices, administrative support areas, Secure Sensitive Area and support areas at Fort Belvoir. This project includes space for currently 650 personnel and associated specialized support equipment. This project will provide increased operational efficiencies in support of Command-and-Control services and proceedings through consolidation of dispersed functions, appropriate security zoning, and Secure Sensitive Areas. Supporting directorates of the Headquarters command staff are identified to occupy the Command-and-Control Facility (C2F) based on operational priorities. The Command-and-Control Facility (C2F) will meet Command and Control Facility (C2F) functions and tasks across the full spectrum of missions and operations.

This requirement will be solicited -- full and open competition. The solicitation requirements will be posted electronically on or about 8 January 2023 via the SAM Website at www.sam.gov with proposal submissions due approximately 30 days after issuance of the solicitation.

*Note: The previous solicitation number was W912DR23R0089 and a placeholder, W912DR24Z9999, was used until an FY24 ID could be obtained. The official RFP number will be W912DR24R0010.

Notice history

Notice Type Posted
HQ Annex, Fort Belvoir North Area, Springfield, VA Award Award Notice
HQ Annex, Fort Belvoir North Area, Springfield, VA Latest solicitation Solicitation
This notice Pre-Solicitation
HEADQUARTERS ANNEX at FORT BELVOIR NORTH AREA (FBNA), SPRINGFIELD, VIRGINIA Original Special Notice

Similar open opportunities

Opportunity Agency Set-aside Responses due
Renovation at Truman Hall Headquarters in Fort Belvoir, VA NAICS 236220 ENDIST Louisville No set-aside
Design-Build Maintenance and Repair Army Reserve (MRAR) of Equipment Concentration Site (ECS), B-56767, at North Fort Hood, TX Bldg. 56767 Equipment Concentration Site (ECS) #6428th St. and Park Ave.North Fort Hood, TX Gatesville, Texas 76528, United States · NAICS 236220 ENDIST Louisville Total Small Business
613-22-700 | EHRM Infrastructure Upgrades Construction | Martinsburg, WV West Virginia 25405, United States · NAICS 236220 VA Technology Acquisition Center No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors